Uploaded by teploeutro 14

Master Thesis - Kubilay Bekarlar - August 2016 (1)

advertisement
Steel–Concrete–Steel Sandwich Immersed Tunnels
For Large Spans
August 2016
Thesis
Kubilay Bekarlar
HASKONINGDHV NEDERLAND B.V.
INFRASTRUCTURE
George Hintzenweg 85
Postbus 8520
3009 AM Rotterdam
+31 10 443 36 66
Telefoon
Fax
info@rotterdam.royalhaskoning.com
www.royalhaskoningdhv.com
Amersfoort 56515154
Document title
Status
Date
Project name
Reference
Author
E-mail
Internet
KvK
Steel-Concrete-Steel Sandwich
Immersed Tunnels For Large Spans
Final Thesis
August 2016
Master Thesis
Kubilay Bekarlar
Kubilay Bekarlar
Collegiale toets
Datum/paraaf
………………….
………………….
………………….
………………….
Vrijgegeven door
Datum/paraaf
A company of Royal HaskoningDHV
Preface
This thesis is written to complete the master Hydraulic Engineering – Hydraulic Structures, at the
technical university of Delft in the Netherlands. This research has been performed in collaboration
with Royal HaskoningDHV.
I would like to thank my graduation committee, consisting of Prof. Dr. Ir. S.N. Jonkman, Dr. Ir. K.J.
Bakker, Dr. Ir. drs. C.R. Braam, Ir. C.M.P ‘t Hart, for all their assistance during this research
project. I also would like to thank Dr. Ir. M.A.N. (Max) Hendriks, Ir. E. van Putten, A. Doorduyn
and H. Meinderts for their contribution for this thesis.
This research has been performed at the office of Royal HaskoningDHV in Rotterdam. I would like
to thank Royal HaskoningDHV for providing me the required facilities and assistance. I have had a
good time with my colleagues of the infrastructure department and I am grateful for their warm
welcome and their help during my stay.
Kubilay Bekarlar
Delft, August 2016
Kubilay Bekarlar – Master Thesis
ii
August – 2016
Abstract
The steel-concrete-steel (SCS) sandwich immersed tunnel is a type of tunnel which has been
constructed in Japan the last two decades. Recent developments in immersed tunnel engineering
show the trend that also other countries started applying SCS sandwich tunnels more often. The
SCS sandwich tunnel has several advantages compared with the traditional reinforced concrete
immersed tunnel among others, to be applied in shallow waters, able to resist higher loads on the
structure.
Traditional reinforced concrete tunnels show limits regarding large spans (for roof and floor
element) in the cross direction. There was a lack of knowledge whether the SCS sandwich tunnel
can be a solution for tunnels with extreme large spans. Also research was needed to understand
the structural response of a large span SCS tunnel to the load applied. For the detailed analysis of
the distribution of internal forces a finite element program was used.
In order to compare a SCS sandwich tunnel for a large span with a reinforced tunnel, two base
case tunnels were designed. From this comparison the critical span for each type was determined.
It was seen that the reinforced tunnel critical span is 18 / 19 m, whereas the SCS tunnel could be
designed for a span of 27 m (boundary condition reference project).
In this thesis two 2-D models have been analysed in DIANA: one simplified model and a detailed
model. Both models use linear-elastic material behaviour. The results of the hand calculations are
first compared with that from the simplified model, to verify the simplified model. The results of
both FEM models are compared and the differences are investigated.
From the stress / strain analysis of the SCS tunnel cross section for a large span, it was seen that
the tensile strength of the concrete was reached. This would result in the formation of tensile
cracks. The allowable compressive stresses / strains were only locally exceeded. Concrete cracking
and plasticity however may have impact on the degree of connection between the steel and
concrete. Due to the cracks the shear stiffness of the steel and concrete connection can decrease.
This may have impact on the overall stiffness of the structure. From the durability point of view
these cracks have no impact on the durability of the structure since the concrete is situated in a
confined space. Although the other side the exceedance of the stress is only locally, it might result
in a redistribution of forces.
By using a detailed FEM analysis, detailed insight was obtained in the distribution of internal design
forces. This resulted in a significant reduction of the amount of steel applied. Namely 21 %. In
absolute values, this is a reduction of 2,51 m3 of steel per meter in the axial direction.
Since the reinforced concrete tunnel was not able to have a span up to 27 m, it was investigated,
whether prestressing (post tensioning) the tunnel could be a solution. From the new design it was
concluded that a span of 27 m is not a feasible solution when using prestressing. This is due to the
large size of the prestress tendon anchors and the large axial forces which the concrete cross
section could not resist. Further there was observed that a steel shell tunnel is a feasible solution
for tunnels with large spans up to 28 m.
From the costs analysis it was seen that steel shell tunnel variant 1 (regular steel shell) would cost
315 000 euros per meter length. Steel shell tunnel variant 2 (with steel cover plates on the inner
side) is slightly more expensive than variant 1. The costs for this tunnel per meter length is 351
000 euros. The same analysis was performed for the SCS tunnel. This variant is with 421 000
euros per meter length, more expensive than the other two steel shell tunnel variants.
Kubilay Bekarlar – Master Thesis
iii
August – 2016
It can be stated that in terms of costs, a reinforced concrete tunnel is the preferred solution for
tunnels with a span up to 18 / 19 m. This is also the limiting span for a reinforced concrete tunnel.
For a span from 19 till 28 m, the steel shell is a more cost efficient solution than the SCS tunnel.
However, applying the SCS for spans shorter than 29 m, has some advantages as well, since the
shear force and bending moment capacity of a SCS tunnel are larger than in case of a steel shell
tunnel. This advantage can be important for changing boundary conditions or accidental loading on
the tunnel structure, e.g. an earthquake loading, explosion, sunken ship on top of the tunnel, extra
loading due to sedimentation on top of the tunnel, erosion below the tunnel floor or more ductile
behaviour. When the construction area is in a region where the risks for earthquakes are
significant, the SCS sandwich is the preferred solution for a span between 19-28 m. This is the
case for the reference project Sharq Crossing (Qatar). Finally it can be stated that the SCS
sandwich tunnel is the only solution available for spans larger than 28 m.
Kubilay Bekarlar – Master Thesis
iv
August – 2016
Graduation committee members:
Chairman:
Prof. Dr. Ir. S.N. Jonkman TU Delft - Section Hydraulic Engineering
Supervisor TU Delft:
Dr. Ir. K.J. Bakker - Bored and immersed tunnels
Supervisor TU Delft:
Dr. Ir. drs. C.R. Braam - Concrete structures
Supervisor Royal Haskoning DHV:
Ir. C.M.P ‘t Hart – Senior Engineer Royal Haskoning DHV – TEC
Author:
K.Z. Bekarlar
Student ID: 1239724
Kubilay Bekarlar – Master Thesis
v
August – 2016
TABLE OF CONTENTS
RESEARCH APPROACH PLAN
2
1
INTRODUCTION
1.1
SCS sandwich tunnel
1.2
SCS sandwich tunnel projects
1.3
Earlier Studies
2
2
3
4
2
PROBLEM DESCRIPTION
2.1
Research objectives
2.2
Research questions
4
5
5
BASE CASE
3
BASE CASE
3.1
Purpose of the base case calculation
7
7
4
REINFORCED CONCRETE TUNNEL
4.1
Dimensions reinforced concrete tunnel
4.2
Loading on the reinforced concrete tunnel
4.3
Design moment calculation
4.3.1
Capacity reinforced concrete tunnel
4.3.2
Roof element
4.3.3
Floor element
4.3.4
Determination of the dimensions of the outer walls
4.4
Uplift and immersion calculations
4.5
Drawing of the reinforce concrete base case design
8
8
8
11
12
13
21
24
25
28
5
SCS SANDWICH TUNNEL
5.1
Loading on SCS sandwich tunnel
5.2
Design moment calculation
5.3
Capacity SCS tunnel
5.3.1
Shear capacity SCS tunnel (ULS)
5.3.2
Moment capacity SCS tunnel (ULS)
5.3.3
Design of stud connectors and stiffeners
5.4
Uplift and immersion calculations
5.5
Drawing of the SCS base case design
29
29
31
31
33
35
38
43
46
6
BASE CASE SUMMARY
47
FEA MODEL ANALYSIS
7
FEA MODEL
7.1
7.2
7.3
7.3.1
7.3.2
7.4
Introduction
2-D or 3-D Analysis
Material model
Material model - concrete linear elastic
Material model - steel linear elastic
Schematization of the SCS sandwich tunnel element
Kubilay Bekarlar – Master Thesis
vi
50
50
50
50
50
51
51
August – 2016
7.4.1
7.4.2
7.4.3
Constraints
Type of elements
Dimensions of the roof, floor and wall
51
52
53
8
LINEAR ELASTIC ANALYSIS SIMPLIFIED MODEL
8.1
Material properties sandwich elements
8.2
Determination of the passion ratio of composite material
8.3
Determination of the bedding constant
8.4
Main Dimensions being modeled
53
53
55
56
56
9
MODELLING SIMPLIFIED MODEL IN IDIANA - LINEAR ELASTIC ANALYSIS
9.1
Geometry definition
9.2
Boundary conditions
9.3
Meshing
9.4
Loads
9.5
Material and physical properties
57
57
57
57
57
58
10
RESULTS OF THE SIMPLIFIED LINEAR ELASTIC ANALYSIS
10.1
Moment distribution and deflection
10.1.1
Lc1 – Load case 1
10.1.2
Lc2 - Load case 2
10.1.3
Lc3 - Load case 3
10.1.4
Lc4 - Load case 4
10.1.5
Lc5 - Load case 5
10.1.6
Lcc - Load case total
10.1.7
Displacement Lcc – Load case total
58
58
58
58
59
59
60
60
61
11
VALIDATION OF THE MODEL
61
11.1
Validation of moment distribution - deflections per load case
61
11.1.1
Load case 1 – self weight of the structure
61
11.1.2
Load case 2 – vertical loading on top of the structure
63
11.1.3
Load case 3 – Vertical hydraulic loading on the bottom of the structure64
11.1.4
Load case 4 – Loading on the left side of the tunnel element
65
11.1.5
Load case 5 – Loading on the right side of the tunnel element
66
12
ANALYSIS RESULTS FROM THE SIMPLIFIED LINEAR ELASTIC ANALYSIS
12.1
Axial force distribution - All load cases (Lcc)
12.2
Shear force distribution - Lcc
12.3
Moment distribution Lcc
12.4
Primary stress distribution Lcc
12.5
Principal stress distribution
12.6
Analysis of moment and shear capacity (fully connected composite)
69
69
70
71
72
73
73
13
LINEAR ELASTIC ANALYSIS DETAILED MODEL
13.1
Schematization of detailed SCS sandwich tunnel model
13.2
Input IDIANA – Detailed linear elastic analysis
13.2.1
Geometry
13.2.2
Boundary constraints
13.2.3
Meshing
13.2.4
Loads
13.2.5
Variable loading
75
75
77
77
78
78
79
79
Kubilay Bekarlar – Master Thesis
vii
August – 2016
13.2.6
13.3
13.4
14
Accidental loading
Material and physical properties
Composed elements
80
81
82
LINEAR ELASTIC ANALYSIS OF DETAILED MODEL
82
14.1
Comparison of the simplified and detailed model (fully connected SCS)82
14.1.1
Load case 1 – self weight of the structure
82
14.1.2
Load case 2 – vertical loading on top of the structure
83
14.1.3
Load case 3 – Vertical hydraulic loading on the bottom of the structure84
14.1.4
Load case 4 – Loading on the left side of the tunnel element
85
14.1.5
Load case 5 – Loading on the right side of the tunnel element
86
14.2
Axial, moment, shear force distribution and deflection
87
14.2.1
Axial force distribution – All load cases (Lcc)
87
14.2.2
Moment distribution Lcc
88
14.2.3
Shear force distribution Lcc
90
14.2.4
Deflection as a result of all load cases
91
14.3
Analysis of the stress distribution
92
14.3.1
Analysis of stress in concrete core
92
14.3.2
Analysis of stress in steel
93
14.3.3
Analysis of moment and shear capacity of a detailed fully connected
composite element
93
OPTIMIZATION
15
PARTIALLY CONNECTED SCS SANDWICH MODEL
15.1
Determination of the linear and tangential stiffness of the interfaces
15.1.1
Approach 1 - Gelfi and Giuriani (1987)
15.1.2
Approach 2 - D.J. Oehlers, M.A. Bradford (1995)
15.2
Detailed analysis of the stress distribution in concrete core
15.2.1
Stress and strain distribution in the roof
15.2.2
Stress distribution in the floor
15.2.3
Stress distribution in the walls
15.2.4
Stress distribution in steel parts
15.3
Principal vector stress analysis of concrete core
15.4
Conclusions of the stress analysis
95
95
96
98
98
99
101
103
104
104
107
16
ULTIMATE MOMENT CAPACITY INTERACTION AXIAL FORCE – MOMENT
16.1
Interaction axial force and bending moment
16.1.1
Roof element – Outside part (inclination)
16.1.2
Roof element – Mid span
16.1.3
Floor element – Outside part (inclination)
16.1.4
Floor element – Mid span
16.1.5
Wall element - Outside part (inclination)
16.1.6
Wall element – Mid span
107
107
107
109
110
110
111
112
17
OPTIMIZATION OF THE DESIGN USING DETAILED LINEAR STRUCTURAL
ANALYSIS
17.1
Optimization due to detailed analysis of the internal forces
112
112
Kubilay Bekarlar – Master Thesis
viii
August – 2016
DESIGN AND COST COMPARISON OF TUNNEL VARIANTS
18
TRANSVERSE PRESTRESSED (POST TENSIONED) REINFORCED CONCRETE
TUNNEL
118
18.1
Roof element
118
18.2
Floor element
123
19
STEEL SHELL TUNNEL
19.1
Variant 1
19.1.1
Floor element
19.1.2
Roof element
19.1.3
Amount of materials applied variant 1
19.2
Variant 2
19.2.1
Roof element
19.2.2
Floor element
19.2.3
Amount of materials applied variant 2
19.3
Critical span steel shell tunnel
127
127
127
132
135
138
138
140
142
144
20
SCS SANDWICH
145
21
COMPARE THE COSTS OF VARIANTS
21.1
Comparing the material quantities
21.2
Comparing the costs
146
146
147
CONCLUSION AND RECOMMENDATIONS
22
CONCLUSION AND RECOMMENDATIONS
22.1
Conclusions
22.2
Recommendations
151
151
155
APPENDIX
23
LITERATURE
157
24
APPENDIX A
158
25
APPENDIX B
164
26
APPENDIX C
168
27
APPENDIX D
174
28
APPENDIX E
175
29
APPENDIX F
188
30
APPENDIX G
197
Kubilay Bekarlar – Master Thesis
ix
August – 2016
NOMENCLATURE
Symbol
Description
Unit
γ
Specific weight of material
[kN/m ]
Φ soil
Angle of internal friction
[Degrees]
K0
Coefficient of lateral earth pressure
[-]
fy
Steel characteristic yield strength
[N/mm ]
γs
Material factor steel
[-]
fy,d
Steel design yield strength
[N/mm ]
fc,d
Concrete design strength
[N/mm ]
γc
Material factor concrete
[-]
fc,d
Concrete design strength
[N/mm ]
fc,t,k 0,05
Concrete characteristic tensile strength
[N/mm ]
fc,t,d
Concrete characteristicdesign strength
[N/mm ]
Esteel
Elastic modulus of steel
[N/mm ]
Econcrete
Elastic modulus of concrete
[N/mm ]
Ic
Mass moment of inertia
[m ]
Wc
Second moment area
[m ]
Sz
First moment inertia
[m ]
Ac
Surface of concrete
[m ]
Ø
Diameter reinforcement bar
[mm]
d
Distance reinforcement bar from a reference point
[mm]
σ
Stress
[N/mm ]
ε
Strain
[-]
ρ
Reinforcement ratio
[-]
θ
Angle between struts and the beam axis
[Degrees]
α
Angle between the shear reinforcement and the beam axis
[Degrees]
t
Thickness steel plate
[mm]
ts,c
Thickness compressive steel plate
[mm]
ts,t
Thickness tensile steel plate
[mm]
tweb
Thickness of diaphragm
[mm]
τrd,c
Design shear strength concrete
[N/mm ]
k
Bedding constant
[kN/m ]
xu
Height of the compression zone in concrete
[mm]
hc
Height of the concrete part of an element
[mm]
q
Distributed load
[kN/m]
f
Drape of the prestress tendon
[mm]
R
Radius of the prestress tendon
[m]
Kubilay Bekarlar – Master Thesis
3
2
2
2
2
2
2
2
2
4
3
3
2
2
2
3
x
August – 2016
Pm0
Initial prestressing load
[kN]
fp,k
Characteristic tensile strength of prestress cable
[N/mm ]
Ep
Elastic modulus of the prestress tendon
[N/mm ]
σpm0
Initial tensile stress in prestress steel
[N/mm ]
Ap
Surface of the prestress tendon
[mm ]
Sr,max
maximum crack spacing
[mm]
εsm
mean strain in the reinforcement
[-]
εcm
mean strain in concrete between cracks
[-]
ρeff
effective reinforcement ratio
[-]
kt
factor dependent on the duration of the load
[-]
Kubilay Bekarlar – Master Thesis
2
2
2
2
xi
August – 2016
RESEARCH APPROACH PLAN
1
INTRODUCTION
An immersed tunnel is one of the options to cross a waterway. At the moment there are about 180
immersed tunnels built worldwide ever since 1893. Compared with other types of tunnels built this
is a rather low number. This also means that this technique is still in its infancy. Initially it may
seem that immersed tunnelling is a narrow field. But the opposite is the case, since there are a
number of disciplines required for an immersed tunnel project such as: structural engineering,
hydraulic engineering, geotechnical engineering etc.
The countries where the immersed tunnels are constructed more often are the US, the Netherlands
and Japan. There is a significant difference between the immersed tunnels constructed in these
countries. In the US the immersed tunnels are constructed more often with a single or double steel
shell. As for the Netherlands the traditional tunnel is built out of reinforced concrete segments. In
Japan reinforced concrete, steel plate or steel concrete steel composite (sandwich) tunnels are
constructed more often.
Also in Japan, till around 1990 immersed tunnels were constructed as either reinforced concrete
with or without a steel plate structure. However more recent tunnels are made out of steel
concrete composite structures. Steel concrete steel (SCS) composite tunnels can be divided into
full sandwich structures and open sandwich structures. Full sandwich structures are structures in
which concrete is sandwiched between two steel plates. The open sandwich tunnel however is a
composite structure where the one surface is covered with a steel plate and where the reinforced
concrete side is exposed to the atmosphere.
On locations where two tunnel parts have to fuse to one tunnel, large spans are inevitable.
However this is not easy to realize since there are some restrictions to it. From earlier preliminary
studies there was seen that there possibly are some limitations regarding the span for reinforced
concrete tunnel. With this research there is aimed to know what the restrictions are for different
types of immersed tunnels and which tunnel variant is the best solution for an immersed tunnel
with a large span.
1.1
SCS sandwich tunnel
Recent developments in the immersed tunnel engineering show a trend that also European
countries apply SCS sandwich tunnels more often. This has several advantages regarding the
traditional reinforced concrete immersed tunnel, as being able to immerse a tunnel in shallow
waters, able to have larger span width in the tunnel cross section as well as being able to resist
higher loads on the structure and several more.
The SCS sandwich tunnel consists of a concrete layer which is sandwiched between two steel
shells. Both the inner as well as the outer shells are load carrying and both act compositely with
the inner concrete layer (detailed description in Appendix B). The concrete inner core is made out
of low shrinkage self-compacting concrete and is unreinforced. For detailed information about selfcompacting concrete see Appendix C. Stiffness is added to the steel plates by welding L-shaped
ribs on its inner sides. These L-shaped ribs also create bond between the steel plates and the
concrete inner core. The stiffeners are sometimes combined with steel studs that are also welded
on the steel plates. Studs are steel pins with a flat head creating extra bond between the concrete
and steel. They also transfer shear forces. Once the concrete is cured it accounts for the
compression forces and also gives stiffness to the steel shells. The steel shell carries the tensile
Kubilay Bekarlar – Master Thesis
2
August – 2016
forces acting on the tunnel segment. In figure 1 below there is a concept of a SCS sandwich
element given.
Figure 1: Concept of a SCS sandwich element
1.2
SCS sandwich tunnel projects
The Osaka Port Sakishima Tunnel is an application of the sandwich tunnel structure. This tunnel
was finished in December 1977. It is an open sandwich tunnel structure where the floor and walls
were constructed as an open sandwich structure and the roof slab as a reinforced concrete
structure.
The Osaka Yumeshima Tunnel is a rail-road tunnel finished in 2009. This tunnel is a partly full
sandwich and partly open sandwich structure. As for the roof and walls, these are made as full
sandwich structures. However the floor slab is an open sandwich structure .
In Okinawa Naha a full sandwich tunnel structure was applied for all members including the floor
slabs. This structure was opened for use in 2010, see figure 2.
Figure 2: Longitudinal profile and cross section of the Okinawa Naha Immersed Tunnel
Tunnel Engineering Consultants (TEC) is designing 5 tunnels for the Sharq Crossing in Doha Qatar,
whereof three are made by cut-cover technique and two by immersed tunnel technique. One of the
two immersed tunnels will be executed as a sandwich tunnel structure. This will be the first
sandwich tunnel structure in this part of the world, see figure 3. From the hydrodynamic point of
view, it will not be the biggest challenge which was encountered for the execution of the immersed
tunnel, since the Persian / Arabian Gulf is a relative calm sea. But one can think that casting good
quality concrete under high temperatures will be a challenge, due to cracking that might occur.
Figure 3: SCS sandwich immersed tunnel, Doha - Qatar
Kubilay Bekarlar – Master Thesis
3
August – 2016
1.3
Earlier Studies
Report: Centrum Ondergronds Bouwen, 2000: “Stalen en composiet staalbeton tunnelconstructies
– Staalbeton sandwichelementen, Deel 2: Modelvorming en rekenregels” in English: “Steel and
composite steel concrete tunnel structures – Steel concrete sandwich elements”.
This report of COB focusses on the numerical and analytical modelling of sandwich elements. It
also compares the results gathered by both methods.
Paper: N. Foundoukos, J.C. Chapman, 2007: “Finite element analysis of steel concrete steel
sandwich beams”.
This study focused on the static behaviour of SCS sandwich beams where the beam was simulated
by using a FEM program. The results from the model were compared with test results, which
showed good agreement.
Report: European Commission Technical Steel Research, 1997: “Double skin composite
construction for submerged tube tunnels”.
In this report there are two main focusses, one is the focus on the test results carried out at the
University of Wales Cardiff. The other focus is on the design rules to give dimensions to the
elements under a certain loading.
These studies and more are described in more detail in the literature study part.
2
PROBLEM DESCRIPTION
As stated before the steel concrete steel (SCS) sandwich tunnel is designed and constructed the
last few decades, predominantly in Japan. These SCS tunnels have an ideal configuration of tensile
and compressive elements compared with a reinforced concrete tunnel for example because the
outer steel plates account for tensile stress and the inner concrete core for compressive stress. This
results in the structure being designed as a more slender structure.
For tunnels with a short span in the cross section, both the SCS and the reinforced concrete tunnel
are applicable. The most suitable solution for that particular situation will be chosen, taking into
consideration the financial and executional characteristics. However no thoroughgoing research has
been performed for SCS and reinforced concrete tunnels for a large span in the cross section. First
of all it is unknown what the maximum span is for a SCS tunnel element. The same holds for the
conventional reinforced concrete tunnel. In other words, first the maximum span for both types of
tunnel need to be investigated and the cause of the limitations will be understood. Because of the
lack of knowledge on this topic, it’s impossible to say which type of tunnel is the most feasible
solution for a tunnel with a large span. For the feasibility the financial and executional aspects
should be studied.
As stated before, the SCS sandwich tunnel is a tunnel which can be designed as a slender
structure. This will reduce the amount of materials applied, hereby also the costs. On the other
hand high loads on a slender structure may lead to local high stress / strain concentration points,
which might exceed the design stress / strain. It is not known how high the stresses will be for a
SCS tunnel element with a large span. There should be investigated whether the design stresses /
strains are exceeded or not. Also in case there is local exceedance of design stresses / strains, then
there should be examined what the consequence might be for the durability of the structure. Since
there is a complicated steel, concrete and stud interaction, hereby stress concentration points
cannot be determined by hand calculations. A finite element method (FEM) program should be
Kubilay Bekarlar – Master Thesis
4
August – 2016
used. With the insight gathered from the FEM model, some conclusions can be drawn how the
structure will respond to loading on a SCS tunnel with a large span.
2.1
Research objectives
One of the objectives of this research is to learn what the maximum span in the cross section is for
a SCS and a reinforced concrete tunnel. While determining the maximum span for both types of
tunnel there will be understood what the causes are for the limit in the span.
Another aim of this research is to know how high the maximum stresses will be for a SCS tunnel
element for large spans. There should be investigated whether the design stresses / strains are
exceeded or not. From the scale of the stress / strain exceedance, some conclusions will be drawn
about the response of the structure to the stress / strain exceedance. Due to the complexity of the
structure a FEM program will be used and this will also give detailed insight on the location of the
potential stress / strain exceedance.
Because of the lack of knowledge on this topic, it’s impossible to say which type of tunnel is the
most ideal solution for a tunnel with a large span. With all previous research objectives achieved,
there is enough knowledge to conclude which type of tunnel is the most ideal solution for a tunnel
with a large span in the cross direction.
2.2
Research questions
Main research question:
Is a SCS sandwich immersed tunnel the most ideal solution for tunnels with large span in the cross
direction?
Sub questions:
How to design a Steel – Concrete - Steel sandwich immersed tunnel?
What is the critical span of a Reinforced concrete tunnel and a SCS immersed tunnel?
How to schematize and model SCS sandwich elements in a FEM program?
How are internal forces (stresses) distributed over a SCS sandwich tunnel element for a large
span?
How to optimize a design of a SCS sandwich immersed tunnel with a detailed FEM analysis?
Is a prestressed reinforced concrete tunnel and a steel shell tunnel a feasible solution for tunnels
with a large span in the cross direction?
How does a SCS immersed tunnel relate to other types of tunnels for large spans in terms of
materials and cost?
Kubilay Bekarlar – Master Thesis
5
August – 2016
Base case calculation of reinforced concrete
tunnel and SCS sandwich tunnel
Kubilay Bekarlar – Master Thesis
6
August – 2016
3
BASE CASE
3.1
Purpose of the base case calculation
TEC (Tunnel Engineering Consultants) prepared the validated concept design of two immersed
tunnels and three cut and cover tunnels for the Sharq crossing in Doha – Qatar (for more see
Appendix D). The northern immersed tunnel is 2,8 km long and the southern is 3,1 km long. These
two immersed tunnels connect the north side of the Sharq bay with the middle and south side and
vice versa. Whereas the cut and cover tunnels connect the land with the bridges in the bay by
crossing under the shoreline, see figure 4.
Figure 4: Overview Sharq bay with the Sharq crossing drawn as a line
The northern immersed tunnel connection and the middle bay connection come together and both
continue in the southern immersed tunnel, see intersection of the line in figure 5. Both the
northern and the middle connection are 2x2 lane road connections with safety lanes on both sides.
Consequently at the connection of both roads a 2x4 lane with safety lanes on each side is
necessary. This is also the position where the southern immersed tunnel will start. The 2x4 plus
safety lane connection is gradually reduced to a 2x3 and safety lanes tunnel connection. This will
continue all the way to the southern side of the bay.
Special attention needs to be paid to the immersed tunnel part with a 2x4 lane formation and the
transition of this part to a 2x3 formation. For a 2x4 lane with safety lanes on both sides a tunnel
the span of each cross sectional tube is about 27 meters. With a gallery width of 3,25 m the total
width of the immersed tunnel would be around 60 meters. The 2x2 lane and 2x3 lane immersed
tunnel will be constructed as conventional reinforced concrete tunnel. Applying the conventional
reinforced concrete immersed tunnel for this 2x4 lane cross section is a challenge, if not
impossible.
Figure 5: Top view transition zone
In short, the aim of the base case study is to investigate whether or not the transition zone of a
2x4 lane to a 2x3 lane immersed tunnel can be executed as a reinforced concrete tunnel part and
what are its limits regarding the cross sectional span. Another aim of the base case design is that
there will be checked whether or not a SCS sandwich tunnel element can realize a 2x4 lane with
Kubilay Bekarlar – Master Thesis
7
August – 2016
safety lanes on both sides. Consequently by making these calculations, insight will be generated in
the design rules and parameters to design a reinforced concrete / SCS sandwich tunnel. The
designed base case for the SCS sandwich tunnel element will be analysed in more detail during this
research project.
4
REINFORCED CONCRETE TUNNEL
4.1
Dimensions reinforced concrete tunnel
First the dimensions of the tunnel elements will be determined. This can be done either by rules of
thumb or from experience. Later on these dimensions will be checked on moment, shear and
normal force resistance and if needed the dimensions can be adjusted. The dimensions are listed in
table 1 and figure 6 below.
Table 1: Dimensions
Dimensions
Width of gallery
3250
[mm]
Thickness floor
1900
[mm]
Thickness roof
1600
[mm]
Thickness outer wall
1500
[mm]
Thickness inner wall
1300
[mm]
Inner height tunnel
7900
[mm]
Figure 6: Tunnel cross section
Now the total height can be calculated, see table 2, which is the sum of the inner height, thickness
of floor and roof.
Table 2: Total height
Total height tunnel
4.2
11400
[mm]
11,4
[m]
Loading on the reinforced concrete tunnel
To determine the loading on the tunnel first the material properties, dimensions of the elements,
thickness of the materials applied as well as the depth below the water surface need to be
specified. These are listed in table table 3 below, in the first column the specific weight of the
materials applied are listed, in the second column the dimensions of the tunnel and in the last
column the water and ground levels.
Kubilay Bekarlar – Master Thesis
8
August – 2016
Table 3: Material properties, dimensions and levels
Material properties
Dimensions
3
γsediment [kN/m ]
17,5
[m]
Reference levels
Protection layer
1,0
Design HWL
3,0
20
Roof thickness
1,6
Ground level
-8,46
γrock [kN/m ]
22
Asphalt thickness
0,12
Road level
-17,64
3
10,35
Ballast concrete
1,1
Bottom level
-20,66
3
γbackfill [kN/m ]
3
γwater [kN/m ]
φ soil [deg]
30
Floor thickness
1,9
K0
0,5
Inner height
7,9
First the hydraulic loading on the tunnel element will be determined. For this the hydraulic stresses
over the height of the tunnel cross section will be determined. Hereafter the total vertical stress will
be determined. Subtracting the hydraulic stress from the total vertical stress will give the effective
vertical stress. With the angle of internal friction of 30⁰ the coefficient of lateral earth pressure at
( )
rest becomes
. This way the effective horizontal stress can be
calculated, by multiplying the effective vertical stress with the coefficient of lateral earth pressure.
Now the total horizontal stress on the tunnel can be determined by adding the hydraulic stress with
the effective horizontal stress. These calculations can be seen in table 4 below.
Table 4: Hydraulic stress distribution over a tunnel
Levels
[m]
3
σhydraulic [kN/m ]
3
3
3
σsoil [kN/m ]
σeff [kN/m ]
σkh [kN/m ]
3
σh [kN/m ]
Water level
3
0,00
0,00
0,00
0,00
0,00
Ground level
-8,46
118,61
118,61
0,00
0,00
118,61
Top side roof
-9,46
128,96
140,61
11,65
5,82
134,79
Bottom side roof
-11,06
145,52
172,61
27,09
13,55
159,07
Top side floor
-18,96
227,29
330,61
103,33
51,66
278,95
Bottom side floor
-20,86
246,95
368,61
121,66
60,83
307,78
The next step is determining the other loads on the structure. These are compacting
-weight, earth load (back fill), rock protection, ballast concrete and traffic load. For these load
types the following load factors are applied, table 5.
Table 5: Load types and load factors
Load types
SLS
ULS
ULS - favorable
Self-Weight
Permanent
1,00
1,25
0,95
Hydrostatic load MWL
Permanent
1,00
1,15
0,95
Earth Load
Permanent
1,00
1,15
0,95
Rock protection
Permanent
1,00
2,00
0,95
Ballast concrete
Permanent
1,00
1,25
0,95
Traffic load
Variable
1,00
1,50
0,00
With these load factors the total loading on the tunnel in SLS and ULS will be determined.
However, still the self-weight of the elements need to be determined. For this the concrete and
steel area is multiplied with its specific mass. The steel area can be estimated by applying the
Kubilay Bekarlar – Master Thesis
9
August – 2016
maximum reinforcement ratio of about 2%. Consequently the total self-weight of the roof and floor
slabs is determined as follows, table 6 and table 7.
Table 6: Material properties
Material properties
3
Density
[kN/m ]
Water
10,35
Concrete
23,2
Steel
77
Ballast concrete
23,2
Table 7: Surface area of steel / concrete and the self-weight of the roof / floor.
Self-weights
Self-weight roof
Ac-roof
As-roof
q
83360000
1563200
2
83,36
2
1,5632
[mm ]
[mm ]
[m2]
39,59
[kN/m]
[m2]
2,46
[kN/m]
Total
42,05
[kN/m]
Self-weight floor
2
92,815
[m2]
44,08
[kN/m]
2
1,8563
[m2]
2,93
[kN/m]
Total
47,01
[kN/m]
Ac-floor
92815000
[mm ]
As-roof
1856300
[mm ]
Finally the total loading on the tunnel can be determined. In order to do so the self-weight of the
element, hydrostatic load, load due to ballast concrete, rock load and soil load will be summed up.
The total loading on the roof, floor and outer wall is displayed in SLS and ULS in table 8 below.
Table 8: The q-load on the elements in SLS and ULS
Elements
Roof
SLS [kN/m]
ULS [kN/m]
Floor
SLS [kN/m]
ULS [kN/m]
Self-Weight
42,05
52,56
Hydrostatic load MWL
-246,95
-283,99
Hydrostatic load MWL
128,96
148,30
Self-Weight
47,01
44,66
Rock protection
11,65
23,30
Ballast concrete
11,9505
11,35
Traffic load UDL
10,00
0,00
Total
182,66
224,17
Total
-177,9895
-227,98
Walls – Top
SLS [kN/m]
ULS [kN/m]
Wall - Bottom
SLS [kN/m]
ULS [kN/m]
Hydrostatic load MWL
134,79
155,0085
Hydrostatic load MWL
307,78
353,947
Back fill
5,83
6,7045
Back fill
60,31
69,3565
Total
140,62
161,713
Total
368,09
423,3035
Kubilay Bekarlar – Master Thesis
10
August – 2016
4.3
Design moment calculation
The occurring moment MEd changes for different spans in the cross section of the tunnel. Initially
the MEd was calculated by using a rule of thumb which is:
. Later this value is
checked by using a framework program Matrixframe.
The design moment MEd is determined by hand calculation for different spans of the tunnel
structure. These moments will be compared with the moment resistance of the cross sectional
elements. At a certain span the design moment or crack width will be bigger than the moment
resistance or maximum allowable crack of an element, with the maximum reinforcement ratio
already applied. In that case there can be concluded that the limit of a reinforced concrete tunnel is
achieved. Besides moment capacity check and crack width control, the same steps will be repeated
for the normal stress check, shear capacity check. The check which results in the smallest span is
the limiting factor and will determine the limit for the span. The hand calculation of the design
forces has been performed. The results are only shown for a span of 27 m see table 9, the results
for the other spans can be found in Appendix (28.1).
Table 9: Hand calculation of the design forces for different spans
Design forces 27 Span
Internal Forces - approximation – ULS
Internal Forces - approximation – SLS
Med - roof
16341,99
kNm
Med - roof
13315,91
kNm
Med - floor
-16619,7
kNm
Med - floor
-12975,5
kNm
V-roof
3026,295
kN
V-roof
2465,91
kN
V-floor
-3077,73
kN
V-floor
-2402,87
kN
N-roof
1294,513
kN
N-roof
1125,679
kN
N-floor
2040,044
kN
N-floor
1773,968
kN
Structural calculation software Matrixframe is used to check the hand calculations for the ULS case.
The bedding is assumed to be uniform. This analysis is done for spans of 15m, 20m, 25m, and
27m. The result is only shown for 27 m in figure 9 below, where the results for the other spans can
be found in Appendix (28.1).
Internal forces - Span 27 m
Kubilay Bekarlar – Master Thesis
11
August – 2016
Figure 7: Internal forces (ULS) for different spans from Matrixframe.
There can be concluded from the results that the hand calculation is in accordance with the results
from the software program Matrixframe. The differences that are present between the hand
calculation and the model can be explained by the assumptions made for the bedding boundaries.
For all other normal, moment and shear force distributions both methods coincide.
4.3.1
Capacity reinforced concrete tunnel
Since the dimensions of the elements and the loading on the reinforced concrete tunnel have been
determined, now the capacity of the tunnel can be calculated. To do so first the material properties
classes are specified. Reinforcing steel B500 and concrete class C35 is applied. The yielding
stresses of these materials will be divided by material factors to get the design yield stresses. For
concrete this is done for the compressive as well as the tensile stresses. In table 10 on the right
side the Young’s modulus for steel and concrete have been given.
Table 10: Material characteristics for steel and concrete
Material properties
2
Elasticity modulus
2
2]
Steel
[N/mm ]
Concrete
[N/mm ]
E - steel
200000
[N/mm
fy
500
fck
35,0
E - concrete
34000
[N/mm2]
γs
1,15
γc
1,5
fyd
434,8
fcd
23,3
fctk, 0,05
2,0
fctd
1,33
The dimensions of the elements and the loadings that will be used for the calculations, as
determined earlier, are summarized in table 11 below.
Kubilay Bekarlar – Master Thesis
12
August – 2016
Table 11: Dimensions of the elements and summary of the loading
Dimensions
4.3.2
Loads
ULS
SLS
Width of gallery
3,25
[m]
q roof
224,2
[kN/m]
182,7
[kN/m]
Thickness floor
1,9
[m]
q floor
-227,9
[kN/m]
-177,9
[kN/m]
Thickness roof
1,6
[m]
q side wall - top
161,7
[kN/m]
140,6
[kN/m]
Thickness outer wall
1,5
[m]
q side wall - bottom
423,3
[kN/m]
368,1
[kN/m]
Thickness inner wall
1,3
[m]
Inner height tunnel
7,9
[m]
Roof element
Since the cross sectional dimensions, the loadings, the material properties and safety factors have
been determined, now the capacity of the concrete tunnel element can be calculated. First the
moment resistance capacity of the roof will be determined. To do so the position of the
reinforcement and its area needs to be determined. In table 12 below the cross sectional
parameters are summarized and in figure 8 the layout of the reinforcement is drawn.
Table 12: Parameters
Parameters
Ic
Wc,top
Wc,bottom
0,341
0,427
4
Ø -stirrup
16
[mm]
3
Ø -tensile/compression
28
[mm]
3
[m ]
[m ]
0,427
[m ]
Ø -tensile/compression
40
[mm]
1
[m]
Spacing reinforcement – 1
50
[mm]
1,6
[m]
Spacing reinforcement – 2
50
[mm]
Ac, eff
1,6
2
[m ]
Spacing reinforcement – 3
95
[mm]
Cover
91
[mm]
Width roof /m
Height roof
Figure 8: Layout reinforcement (tensile: 8-40ɸ; 8-32 ɸ; 8-32 ɸ Compressive 8-28 ɸ; 8-28 ɸ)
4.3.2.1 Moment capacity – span 22 m (ULS)
These calculations are initially made for a span of 22m, this in order to do the unity check for each
capacity. Later on several other spans will be checked as well. After the parameters for the cross
section of the roof have been chosen, the amount of tensile, compressive reinforcement and the
stirrups can be determined. Specifying their position is of importance, because it will result in an
internal level arm, which will lead to the design moment resistance of the cross section. First the
strains in the roof element need to be calculated. With the cross sectional area and the ULS strain
Kubilay Bekarlar – Master Thesis
13
August – 2016
in the concrete there is only one parameter missing to calculate the strain in each element of the
cross section. This parameter is the compression zone height Xu. Since the compression zone
height can be determined by an iterative calculation a spreadsheet program has been used. From
the calculations carried out the compression zone height is 345,5mm. Now the strains can be
calculated as shown in Table 13 below.
Table 13: Reinforcement area, layout and the strains
Distances
1st layer
ds
1486
Tensile reinforcement
[mm]
1st layer
4926
Compressive reinforcement
2
1st layer
4926
[mm ]
2
2nd layer
4926
[mm ]
804,2
[mm ]
Asw
8,47
[mm /mm]
[mm ]
2nd layer
1422
[mm]
2nd layer
4926
[mm ]
3th layer
1313
[mm]
3th layer
10053
[mm ]
2
2
2
Stirrups
1st layer
d eff
1382,79
[mm]
Total
2
2
19905
[mm ]
Stirrups
Effective depths
Strains
ε'cu,3
-3,50%
ds1
1486
[mm]
ε s1
5,26%
ρtensile
1,25 %
ds2
1422
[mm]
ε s2
4,88%
ρcompressive
0,62 %
ds3
1313
[mm]
ε s3
4,24%
ds4
91
[mm]
ε s4
-2,96%
ds5
155
[mm]
ε s5
-2,59%
2
After the strains have been determined, now the forces in the reinforcement and the concrete
compression zone can be calculated. From the horizontal force equilibrium the sum of the forces
should be equal to the axial loading on the element. Then the design moment resistance M,rd of
the roof element can be calculated by multiplying the forces with their eccentricities. This moment
of resistance will be compared with the occurring moment due to loading MEd. In case the moment
resistance of the cross section is larger than the occurring moment due to loading, then the cross
section will fulfill the moment capacity check. These steps are summarized in the spreadsheet
below for a roof element, table 14.
Table 14: Forces and moment resistance
Steel, concrete forces
N'cd;1
Moment resistance
-6046,25
[kN]
MN'cd;1
-812,61
[kNm]
Ns1
2141,91
[kN]
MNs1
3167,89
[kNm]
Ns2
2141,91
[kN]
MNs2
3000,82
[kNm]
Ns3
4371,23
[kN]
MNs3
5586,43
[kNm]
Ns4
-2141,91
[kN]
MNs4
-194,91
[kNm]
Ns5
-1761,53
[kN]
MNs5
-297,70
[kNm]
Nd
1294,51
[kN]
MNd
1035,61
[kNm]
ΣMRd
11485,53
[kNm]
Eccentricity e0
Kubilay Bekarlar – Master Thesis
14
0,05
[m]
August – 2016
Med
10918,87
[kNm]
U-check
0,95
4.3.2.2 Normal stress capacity – span 22 m check (ULS)
The second check that will be made is the compressive stress check in the roof element as the
result of the normal force and the moment. This can be calculated as follows:
( )
In which:
N is the normal force in the floor element
Ac,eff is the effective cross sectional area of the floor
M is the design moment
W is the sectional modulus
Table 15: Normal stresses
Normal stresses
2
fcd
-23,33
[N/mm ]
σc,top
-26,24
[N/mm ]
2
U-check
1,124501
2.4.1.3 - Shear force capacity – span 22 m check (ULS)
The structure is also checked for the shear capacity. This is first done for the case without shear
reinforcement (stirrups). The following formula is applied to calculate the shear resistance for
concrete.
[
(
)
]
In which:
√
d = effective depth in [mm]
ρ = reinforcement ratio
As = reinforcement area
b = width of the cross section in tensile area
σcp = stress due to axial loading
Ned = axial force in the cross section due to loading (in case of compression)
Ac = area of concrete cross section
fcd = design concrete compressive stress
Kubilay Bekarlar – Master Thesis
15
August – 2016
These calculations are made for all the spans that are investigated. The results for a span of 22 m
are listed in table 15 below. As can be seen the cross section is not able to bear the shear force in
case no shear reinforcement is applied. This means that shear reinforcement has to be applied and
the shear capacity check has to be done again, now for the shear reinforced cross section. The
formula that is applied for the calculation of the shear reinforcement is:
(
)
In which:
Asw = cross sectional area of shear reinforcement
S = spacing of stirrups
z = 0,9 d = effective depth of the cross section
fyd = design yield strength of shear reinforcement
θ = angle of inclined strut
α = coefficient for the compression chord
b = width of the cross section
v1 = strength reduction factor for concrete in shear
The minimum value of the two calculated shear force resistances will be used to calculate the unity
check.
(
)
The unity check for the shear capacity of the cross section with 8,47 mm 2/mm of shear
reinforcement, shows that for a span of 22m the working shear force can be carried, table 16.
Table 16: Shear force resistance
Shear resistance
Ved
2465,87
[kN]
Nd
1294,5128
[kN]
Bearing capacity without stirrups
Bearing capacity with stirrups
Crd,c
0,12
[-]
θ
45
⁰
αcw
K
1,38
[-]
α
90
⁰
V1
k1
0,15
[-]
cot θ
ρ1
0,0146556
[-]
1
Asw
8,47
tan θ
1
2
[mm /mm]
2
σcp
0,81
[N/mm ]
Vrd,c
1002,8
[kN]
Vrs,d
4501,9
[kN]
Ved
2465,9
[kN]
Vrd,max
8556,5
[kN]
Ved
2465,9
[kN]
U-check
1
0,6
2,46
U-check
0,55
There can be seen that the shear force capacity is fulfilled. However the angle of compression Θ
can vary from 21,8˚ to 45˚. This would mean that the value of Vrs,d and Vrd,max can change. By
Kubilay Bekarlar – Master Thesis
16
August – 2016
reducing the value of Θ the value of Vrd,max will reduce and Vrs,d will increase, doing so a larger unity
check will appear. That would mean that the rest shear capacity would increase, which means that
there is room for further optimization of the stirrups.
Table 17: Applied stirrups
Ø
16
mm -
200
mm
2
pcs
Asw
2
2,01
[mm /mm]
Table 18: Unity check for the optimized stirrup layout
Asw, new
Θ
α
2,01
mm²/mm
25
°
90
°
Vrs,d
2831
[kN]
Vrd,max
6964
[kN]
2465,9
[kN]
Ved
cot θ
2,14
-
U-check 0,87
Now the new unity check is performed for the optimized stirrup layout. The results can be seen in
table 18 above. The newly applied stirrup Asw is 2,01 mm2/mm and an angle of compression
diagonal of 25˚ results in a new unity check of 0,87. This is indeed more optimal solution shear
force reinforcement.
4.3.2.3 Crack width control reinforced concrete tunnel (SLS)
The next check will be the crack width control check. This is a serviceability limit state (SLS) check,
which means that the moments and normal forces in SLS will be used. In order to calculate the
crack width, first the concrete compression zone is determined. For this a spreadsheet model is
used, since this is an iterative process. With the moment and force balance ΣM = 0 and Σ N = 0
the unknown strain in concrete εc and the compression zone x in SLS can be determined.
Consequently the stress distribution over the height can be determined. This will result in the force
distribution over the cross section. From the balance of forces principle the sum of the forces
should be zero. With the force in the reinforcing steel the stress in the reinforcing steel will be
calculated. These calculations are listed in table 19 below.
Table 19: Strain, forces, moments and steel stress
Strain, force, stress, moment SLS
Nrep
1125,7
[kN]
Eccentricities
Mrep,sls
- 8840,74
Strains
ec
619
[mm]
ε'c
-1,14
‰
es1
679
[mm]
ε s1
1,97
‰
es2
601
[mm]
ε s2
1,80
‰
es3
478
[mm]
ε s3
1,55
‰
es4
709
[mm]
ε s4
-0,95
‰
Kubilay Bekarlar – Master Thesis
17
x
543,4
e'c3
0,00175
August – 2016
es5
631
[mm]
ε s5
Forces
-0,79
‰
Moments
N'c
-6213,0
kN
MN'c
3845,0
[kNm]
Ns1
1939,4
kN
MNs1
1316,9
[kNm]
Ns2
1777,8
kN
MNs2
1068,4
[kNm]
Ns3
3107,7
kN
MNs3
1485,5
[kNm]
Ns4
-937,8
kN
MNs4
664,9
[kNm]
Ns5
-776,1
kN
MNs5
489,7
[kNm]
Nrep
1125,7
kN
Mrep
8840,7
[kNm]
σs
393,715
Since the stress in the reinforcing steel has been determined, the crack width that will occur can be
calculated. In order to do so the following formula is used:
(
)
In which:
Sr,max = maximum crack spacing
εsm = mean strain in the reinforcement
εcm = mean strain in concrete between cracks
(
)
σs = stress in the reinforcement
fct, eff = concrete tensile stress
α = ratio Es / Ecm
ρeff = effective reinforcement ratio
Es = Elasticity modulus steel
kt = factor dependent on the duration of the load
As = reinforcement steel area
Ac,eff = effective concrete area
These calculation steps have been carried out by making use of a spreadsheet program and the
results are given in table 20 below.
Table 20: Crack width check
Crack width
εsm - εcr
1,74
αe
5,88
ρp,eff
0,033
heff
604,54
Ac,eff
fct,eff
604544,84
3,21
‰
s1
125
[mm]
wk
0,788
[mm]
s1,max
525
[mm]
wmax
0,3
[mm]
[-]
sr,max
453
[mm]
[mm]
k1
0,8
[-]
U-check
2,63
k2
0,5
[-]
k3
3,4
[-]
2
[mm ]
2
[N/mm ]
Kubilay Bekarlar – Master Thesis
18
August – 2016
ξ1
1
[-]
k4
0,425
[-]
kt
0,4
[-]
φeq
28
[mm]
kx
1
[-]
As can be seen from the unity check in table 18 above, the occurring crack width exceeds the
maximum allowed crack width. This is valid for a span of 22 m and current reinforcement ratio of
ρtensile :1,25 % ρcompression :0,62%. It means that additional measures have to be taken, such as
applying more reinforcement or more reinforcement with a smaller diameter or concrete with
better tensile stress properties.
4.3.2.4 Determination of the critical span of the reinforced concrete roof element
The calculations above were given for a span of 22 m. In the tables below the unity checks are
summarized for different spans in order to determine the critical span each check.
Table 21: Moment capacity check
Roof - Moment capacity check
Span 15 m
[kNm]
Span 20 m
[kNm]
Span 25 m
[kNm]
Span 27 m
[kNm]
Mrd
11485,53
Mrd
11485,53
Mrd
11485,53
Mrd
11485,53
Med
5043,83
Med
8966,8
Med
14010,63
Med
16341,99
Unity check
0,439147
Unity check
0,78
Unity check
1,22
Unity check
1,42
Span 22 m
[kNm]
Span 23 m
[kNm]
Mrd
11485,53
Mrd
11485,53
Med
10849,83
Med
11858,59
Unity check
0,94
Unity check
1,03
Interpolation
In table 21, the critical span for the moment capacity is determined by interpolation. There can be
stated that for the applied reinforcement ratio of ρtensile :1,25 % ρcompression :0,62%, the maximum
span for a reinforced concrete tunnel will be about 22 m for the roof element.
Table 22: Normal stress check
Roof - Normal stress check
2
2
2
2
Span 15 m
[N/mm ]
Span 20 m
[N/mm ]
Span 25 m
[N/mm ]
Span 27 m
[N/mm ]
fcd
-23,33
fcd
-23,33
fcd
-23,33
fcd
-23,33
σc,top
-12,63
σc,top
-21,83
σc,top
-33,65
σc,top
-39,11
Unity check
0,54
Unity check
0,94
Unity check
1,44
Unity check
1,68
Span 21m
[N/mm ]
fcd
-23,33
σc,top
-23,98
Unity check
1,028
Interpolation
2
In the table 22 above the normal stresses for different spans are summed up. There can be seen
that for a span larger than 20 m the normal stress capacity will be exceeded, which means that the
limiting span is about 20 m.
Kubilay Bekarlar – Master Thesis
19
August – 2016
Table 23: Shear force capacity check without shear reinforcement
Roof - Shear force capacity - concrete without shear reinforcement
Span 15 m
[kN]
Span 20 m
[kN]
Span 25 m
[kN]
Span 27 m
[kN]
Vrd,c
1002,78
Vrd,c
1002,78
Vrd,c
1002,78
Vrd,c
1002,78
Ved
1681,28
Ved
2241,70
Ved
2802,13
Ved
3026,30
Unity check
1,68
Unity check
2,24
Unity check
2,79
Unity check
3,02
Span 8 m
[kN]
Span 9 m
[kN]
Vrd,c
1002,78
Vrd,c
1002,78
Ved
896,68
Ved
1008,77
Unity check
0,89
Unity check
1,01
Interpolation
First the shear force capacity has to be checked in case no shear force reinforcement (stirrups) is
applied. In table 23 there can be seen that in case no shear reinforcement is applied the maximum
span that is possible is about 8 m. This is too short, which means that shear reinforcement has to
be applied. The results are given in table 24 below.
Table 24: Shear force capacity check with shear reinforcement
Roof - Shear force capacity - concrete with shear reinforcement
Span 15 m
[kN]
Span 20 m
[kN]
Span 25 m
[kN]
Span 27 m
[kN]
Vrs,d
4501,86
Vrs,d
4501,86
Vrs,d
4501,86
Vrs,d
4501,86
Vrd,max
8556,55
Vrd,max
8556,55
Vrd,max
8556,55
Vrd,max
8556,55
Ved
1681,28
Ved
2241,7
Ved
2802,13
Ved
3026,30
Unity check
0,37
Unity check
0,49
Unity check
0,62
Unity check
0,67
The applied shear reinforcement is 8,47 mm2/mm. This results in a span which is more than the
previous case without shear reinforcement. In this case the shear force capacity is not governing
the span of the cross section. Since the span is more than the maximum investigated span of 27
m.
4.3.2.5 Crack width – Roof element
From the calculations there was seen that the crack width boundary condition is the limiting
condition. With the current reinforcement ratio of ρtensile :1,25 % ρcompression :0,62% and its span of
approximately 16 m can be made. By increasing the reinforcement ratio to the maximum of ρ tensile
:1,82 % ρcompression :0,31%, the limit of span for a reinforced concrete tunnel can be determined.
This because the crack width control check is the governing check. For this reinforcement ratio for
all other checks were fulfilled.
Table 25: Crack width
Crack width
Span 15 m
wk
wmax
U-check
Span 17m
0,264919
[mm]
wk
0,3
[mm]
wmax
0,883062
Kubilay Bekarlar – Master Thesis
U-check
0,389518
[mm]
0,3
[mm]
1,298393
20
August – 2016
So after the reinforcement ratio is increased to its maximum of 2%, the maximum span is
determined again. This span will be the limit for the span since the crack width condition is
governing. The results are summarized in table 26.
Figure 9: New reinforcement layout (tensile: 10-40ɸ; 8-40 ɸ; 8-32 ɸ Compressive 8-28 ɸ)
Table 26: Unity check crack width
Span 15
Span 18
Crack width
Crack width
wk
0,16
[mm]
Wk
0,27
[mm]
wmax
0,3
[mm]
wmax
0,3
[mm]
U-check
0,541
U-check
0,91
Span 19
Span 20
Crack width
Crack width
wk
0,316182
[mm]
wk
0,35982
[mm]
wmax
0,3
[mm]
wmax
0,3
[mm]
U-check
1,04
U-check
1,199
From the table 24 above there can be seen that the maximum span for the roof with a
reinforcement ratio of ρtensile :1,82 % ρcompression :0,31%, is now about 18 -19 m.
4.3.3
Floor element
The cross sectional dimensions, the loadings, material properties and safety factors have been
determined, so the capacity of the concrete tunnel element can be calculated. First the moment
resistance capacity of the floor will be determined. The position of the reinforcement and its area
needs to be specified first. In table 27 below the cross sectional parameters are summarized.
Table 27: Parameters
Parameters
Ic
0,341
[m4]
Wc,top
0,427
[m ]
Wc,bottom
0,427
cover
91
[mm]
3
Ø -stirrup
16
[mm]
3
Ø -tensile/compression
28
[mm]
[m ]
Kubilay Bekarlar – Master Thesis
21
August – 2016
Width floor /m
1
[m]
Ø -tensile/compression
40
[mm]
Height floor
1,9
[m]
Spacing reinforcement - 1
Ac, eff
1,9
2
[m ]
Spacing reinforcement - 2
50
[mm]
cover
91
[mm]
Spacing reinforcement - 3
50
[mm]
Ø -stirrup
16
[mm]
[mm]
Figure 10: Layout reinforcement (tensile: 8-40ɸ; 8-40 ɸ; 8-40 ɸ Compressive 8-28 ɸ)
4.3.3.1 Capacity unity checks for a span of 20 m
The intermediate steps for the moment-, normal- , shear force capacity and the crack width will
not be listed here. Those numbers can be found in Appendix (28.2). The final results of the
calculation will only presented, see table 28.
Table 28: Unity checks for a span of 20 m
Unity checks
Moment resistance
Shear resistance
MRd
20048,90
[kNm]
Vrs,d
5578,5
[kN]
Med
9248,40
[kNm]
Vrd,max
10602,9
[kN]
U-check
0,46
Ved
2279,8
[kN]
U-check
0,41
Normal stresses
fcd
-23,33
σc,top
-16,23
U-check
0,695
2
Crack width check
2
wk
0,2485
[mm]
wmax
0,3
[mm]
U-check
0,83
[N/mm ]
[N/mm ]
There can be concluded that for a span of 20 m, that all unity checks are smaller than 1. This
means that the moment-, normal-, shear capacity as well as the crack width fulfill their conditions.
However what is again interesting is to find out what the limiting span is for the floor element. This
will be further elaborated in the chapter below.
4.3.3.5 - Determination of the critical span of the reinforced concrete floor element
The calculations above were given for a span of 20 m. In the tables below the unity checks are
summarized for different spans in order to determine the critical span.
Kubilay Bekarlar – Master Thesis
22
August – 2016
Table 29: Moment capacity check
Floor - moment capacity check
Span 15 m
[kNm]
Span 20 m
[kNm]
Span 25 m
[kNm]
Span 27 m
[kNm]
MRd
20048,9
MRd
20048,9
MRd
20048,9
MRd
20048,9
Med
5258,8
Med
9248,4
Med
14377,9
Med
16748,9
Unity-check
0,26
Unity-check
0,46
Unity-check
0,71
Unity-check
0,84
In table 29, the critical span for the moment capacity is determined by interpolation. There can be
stated that for the applied reinforcement ratio of ρtensile :1,59 % ρcompression :0,26%, the maximum
span for a reinforced concrete tunnel will more than 27 m. From experience of the previous
calculations there can be concluded that the moment capacity will not be the governing for the
critical span.
Table 30: Normal stress check
Roof - Normal stress check
2
2
2
2
Span 15 m
[N/mm ]
Span 20 m
[N/mm ]
Span 25 m
[N/mm ]
Span 27 m
[N/mm ]
fcd
-23,33
fcd
-23,33
fcd
-23,33
fcd
-23,33
σc,top
-9,60
σc,top
-16,23
σc,top
-24,8
σc,top
-28,70
Unity check
0,41
Unity check
0,70
Unity check
1,06
Unity check
1,23
In the table 30 above the normal stresses for different spans are summed up. There can be seen
that for a span larger than about 24 m the normal stress capacity will be exceeded, which means
that the limiting span is about 24 m.
Table 31: Shear force capacity check without shear reinforcement
Roof - Shear force capacity - concrete without shear reinforcement
Span 15 m
[kN]
Span 20 m
[kN]
Span 25 m
[kN]
Span 27 m
[kN]
Vrd,c
1350,1
Vrd,c
1350,1
Vrd,c
1350,1
Vrd,c
1350,1
Ved
1709,9
Ved
2279,8
Ved
2849,8
Ved
3026,30
Unity check
1,27
Unity check
1,69
Unity check
2,11
Unity check
2,28
The shear force capacity will first be checked in case no shear force reinforcement (stirrups) is
applied. In table 31 there can be seen that in case no shear reinforcement is applied the maximum
span that is possible is well below 15 m. This is too short, which means that shear reinforcement
has to be applied. The results for concrete with shear reinforcement are given in table 32 below.
Table 32: Shear force capacity check with shear reinforcement
Roof - Shear force capacity - concrete with shear reinforcement
Span 15 m
[kN]
Span 20 m
[kN]
Vrs,d
5578,5
Vrs,d
5578,5
Vrs,d
Vrd,max
10602,9
Vrd,max
10602,9
Vrd,max
Ved
1709,9
Ved
Unity check
0,31
Unity check
2279,8
0,41
Ved
Kubilay Bekarlar – Master Thesis
Span 25 m
Unity check
23
[kN]
Span 27 m
[kN]
5578,5
Vrs,d
5578,5
10602,9
Vrd,max
10602,9
2849,8
0,51
Ved
3077,7
0,55
Unity check
August – 2016
The applied shear reinforcement is 8,47 mm2/mm. This results in a span which is more than the
span in the previous case without shear reinforcement. In this case the shear capacity is not
governing the limit span. Since the span is more than the maximum investigated span of 27 m.
4.3.3.6 - Crack width – Floor element
For the floor element the crack width boundary condition is the limiting condition. With the current
reinforcement ratio of ρtensile :1,59 % ρcompression :0,26% the critical span will be determined with the
results in table 33.
Table 33: Crack width control
Span 15
Span 20
Crack width
Crack width
wk
0,09
[mm]
wk
0,274
[mm]
wmax
0,3
[mm]
wmax
0,3
[mm]
U-check
0,30
U-check
0,914646
Span 25
Span 27
Crack width
Crack width
wk
0,45
[mm]
wk
0,54
[mm]
wmax
0,3
[mm]
wmax
0,3
[mm]
U-check
1,48
U-check
1,79
The crack width check is interpolated in table 34 below.
Table 34: Crack width control
Span 22 m
Crack width
wk
0,319
[mm]
wmax
0,3
[mm]
U-check
1,06
From this unity check for the crack width there can be concluded that the critical span that can be
made is 21 m.
4.3.4
Determination of the dimensions of the outer walls
The steps above for the roof and floor are repeated for the outer wall and the results are shown
below. First the moment resistance capacity of the floor will be determined. Therefor the position of
the reinforcement and its area needs to be specified. In table 38 below the cross sectional
parameters are summarized.
Table 35: Parameters
Parameters
Ic
Wc,top
Wc,bottom
0,341
0,427
0,427
4
Ø -stirrup
16
[mm]
3
Ø -tensile/compression
28
[mm]
3
Ø -tensile/compression
40
[mm]
[m ]
[m ]
[m ]
Kubilay Bekarlar – Master Thesis
24
August – 2016
Width floor /m
1
[m]
Spacing reinforcement - 1
[mm]
Thickness outer wall
1,5
[m]
Spacing reinforcement - 2
50
[mm]
Ac, eff
1,5
2
[m ]
Spacing reinforcement - 3
50
[mm]
Cover
91
[mm]
Ø -stirrup
16
[mm]
Figure 11: Layout reinforcement (tensile: 8-40ɸ; 8-40 ɸ; 8-40 ɸ Compressive 8-28 ɸ)
The capacity checks will be performed for a span of the roof and floor of 20 m. This has to do with
the fact that the limiting span for the roof is about 19 m and for the floor it is about 21 m. Since
the smallest span is the governing span, 19 m should be taken. In order to have a small safety
margin 20 m span is taken as the loading on the structure, respectively on the outer wall.
4.3.3.1 Capacity unity checks for a span of 20 m
The intermediate steps for the moment-, normal- , shear force capacity and the crack width will
not be presented here. Those numbers can be found in Appendix (28.3). The final results of the
calculation will only presented, see Table 36.
Table 36: Unity checks for a span of 20 m
Unity checks
Moment resistance
Shear resistance
MRd
11343,53
[kNm]
Vrs,d
4401,8
[kN]
Med
5504,25
[kNm]
Vrd,max
8366,4
[kN]
U-check
0,485
Ved
1684,3
[kN]
U-check
0,38
Normal stresses
fcd
-23,33
σc,top
-15,85
U-check
0,68
2
Crack width check
2
wk
0,254
[mm]
wmax
0,3
[mm]
U-check
0,85
[N/mm ]
[N/mm ]
There can be concluded that for a span of 20 m, that all unity checks are smaller than 1. This
means that the moment-, normal-, shear capacity as well as the crack width fulfill its condition.
There can be concluded that the outer wall with these dimensions is feasible for a span of 20 m.
4.4
Uplift and immersion calculations
After the construction of a tunnel element is completed, both ends of the tunnel element are sealed
with bulkheads. Before the tunnel element is floated up, some ballast tanks are installed to have a
Kubilay Bekarlar – Master Thesis
25
August – 2016
controlled floating up as well as immersion. The tunnel elements should be designed such that
they can float up and be immersed. So, buoyancy balance equations should be used to check
whether the floating and immersing conditions hold. If this tunnel cross section does not hold the
balance conditions, then changes to the cross section should be made. The dimension for the span
of the element is taken as maximum, which is 18 m.
In the previous section the dimensions of the elements in a reinforced concrete tunnel have been
determined, now the uplift and immersion calculations can be made. For this the weight of the
tunnel element has to be determined first. In order to do so the concrete and steel area applied
has to be determined. These calculations are made in table 37 and table 38 below.
Table 37: Determination of the concrete area
Dimension
concrete
b [mm]
h [mm]
2
A [mm ]
Dimension
concrete
Floor
2
b [mm]
h [mm]
A [mm ]
Roof
Outer wall 1
1500
1900
2850000
Outer wall 1
1500
1600
2400000
Floor 2
18000
1900
34200000
Roof 2
18000
1600
28800000
Inner wall 2
1300
1900
2470000
Inner wall 2
1300
1600
2080000
Gallery floor 4
3250
1900
6175000
Gallery roof 4
3250
1600
5200000
Inner wall 3
1300
1900
2470000
Inner wall 3
1300
1600
2080000
Floor 6
18000
1900
34200000
Roof 6
18000
1600
28800000
Outer wall 4
1500
1900
2850000
Outer wall 4
1500
1600
2400000
Gallery floor 1
3250
1600
5200000
Walls
Outer wall 1
1500
7900
11850000
Inner wall 2
1300
7900
10270000
Inner wall 3
1300
7900
10270000
Outer wall 4
1500
7900
11850000
2
Total concrete area
206415000
[mm ]
Total concrete area
206,415
[m ]
2
Table 38: Determination of the steel area (ρ approximated)
Mass reinforcing steel
2
2
ρ
l [mm]
Ac [mm ]
As [m ]
Reinforcement floor
2%
44850
85215000
1704300
Reinforcement roof
2%
44850
71760000
1435200
Reinforcement outer wall
2%
22800
34200000
684000
Reinforcement inner wall
2%
22800
29640000
592800
0,02
2
Total steel area
[mm ]
Total steel area
2
[m ]
4416300
4,4163
With the calculated surfaces, the weight of the element can be determined by multiplying the area
with the specific weight. Consequently the total weight of the structure will be calculated. Only the
Kubilay Bekarlar – Master Thesis
26
August – 2016
amount of ballast concrete to be applied after immersion needs to be calculated. Since the total
height of the structure is already determined, the space for ballast concrete can be calculated as
follows:
In which:
hballast is the height of the ballast concrete
htotal is the total inner height of the structure
hfree traffic is the free height which is needed for the traffic
hequipment is the height needed for the installations
hasphalt is the height of the asphalt which will be executed at a slope of 2%
The dimensions of the elements which are needed in order to make a buoyancy balance calculation
are now known. For the floating up conditions the upward hydrostatic load, should be about 1%
larger than the weight of the tunnel element. For the immersing condition, in order to have a
safety margin against floating up the weight of the element need to be increased further by
applying ballast (first water later replaced with ballast concrete). This safety margin is about 7,5%.
The results of these calculations are listed in the table 39 and table 40 below.
(
)
Table 39: Floating calculation
Floating calculation
3
3
Total areas
[m ]
[kN/m ]
[kN]
[factor]
Concrete
206,42
23,50
4850,75
1,00
Steel
4,42
53,50
236,27
1,00
Ballast
0,00
23,50
0,00
1,00
Hydrostatic load
511,29
10,00
5112,90
1,00
Check
0,99
<1
height
0,72
1,08
>1
Table 40: Immersion calculation
Immersion calculation
3
3
Total areas
[m ]
[kN/m ]
[kN]
[factor]
Concrete
206,42
23,20
4788,83
1,00
Steel
4,42
77,00
340,06
1,00
Ballast
25,92
23,20
601,34
1,00
Earth
0,00
7,50
0,00
1,00
Hydrostatic load
511,29
10,35
5291,85
1,00
Check
From the calculations above there can be concluded that the designed reinforced concrete tunnel
element fulfils the floating and immersion conditions. For the immersing conditions a lower
concrete specific weight is assumed. This is done to account for the uncertainties regarding the
concrete density and inaccurate concrete thickness (casting inaccuracy).
Kubilay Bekarlar – Master Thesis
27
August – 2016
4.5
Drawing of the reinforce concrete base case design
Figure 12: Cross section of the reinforced concrete tunnel
Kubilay Bekarlar – Master Thesis
28
August – 2016
5
SCS SANDWICH TUNNEL
The first step is determining the dimensions of the tunnel element. Later on these dimensions will
be checked on moment, shear resistance and if needed these dimensions can be adjusted. The
dimensions are listed in table 41 below.
Table 41: Dimensions SCS sandwich elements
Roof
5.1
Floor
Walls
Dimensions
outside
inside
outside
inside
outside
inside
h [mm]
1600
1600
1900
1900
1600
1600
b [mm]
1500
1500
1500
1500
1500
1500
tsc [mm]
25
35
20
35
20
25
tst [mm]
35
25
35
20
25
20
hc [mm]
1540
1540
1845
1845
1455
1455
tweb [mm]
20
20
20
20
10
10
ctc web [mm]
1500
1500
1500
1500
1500
1500
Loading on SCS sandwich tunnel
In order to determine the loading on the tunnel the material properties, dimensions of the
elements, thickness of the materials applied as well as the depth below the water surface need to
be specified. These parameters are listed in the table 42 below, in the first column the specific
weight of the materials applied are listed, in the second column the dimensions of the tunnel and in
the last column the water and ground levels.
Table 42: Material properties, dimensions and levels
Material properties
γsediment
γbackfill
γrock
17,5
20
22
Dimensions
General levels
3
Protection layer
1,0
[m]
Design HWL
2,68
[m]
3
Roof thickness
1,6
[m]
Ground level
-8,46
[m]
3
Asphalt thickness
0,12
[m]
Road level
-17,64
[m]
3
Bottom level
-20,66
[m]
[kN/m ]
[kN/m ]
[kN/m ]
γwat
10,35
[kN/m ]
Ballast concrete
1,1
[m]
φ
30
[deg]
Floor thickness
1,9
[m]
K0
0,5
[-]
Inner height
7,9
[m]
Now the hydraulic loading on the tunnel element will be determined. To do so first the hydraulic
stress distribution over the tunnel element needs to be determined. By subtracting the hydraulic
stress from the total vertical stress, the effective vertical stress is determined. With the angle of
( )
internal friction of 30⁰ the coefficient of lateral earth pressure at rest becomes
. By multiplying this parameter with the effective vertical stress, the horizontal stress on
the tunnel element can be determined. By summing the hydraulic stress with the effective
horizontal stress, the total horizontal stress is calculated. These steps are summarized in table 43.
Table 43: Hydraulic stress distribution
3
3
3
3
3
Levels
[m]
σhydraulic [kN/m ]
σsoil [kN/m ]
σeff [kN/m ]
σkh [kN/m ]
σh [kN/m ]
Water level
3
0,00
0,00
0,00
0,00
0,00
Kubilay Bekarlar – Master Thesis
29
August – 2016
Ground level
-8,46
118,61
118,61
0,00
0,00
118,61
Top side roof
-9,46
128,96
140,61
11,65
5,82
134,79
Bottom side roof
-11,06
145,52
172,61
27,09
13,55
159,07
Top side floor
-18,96
227,29
330,61
103,33
51,66
278,95
Bottom side floor
-20,76
245,92
366,61
120,70
60,35
306,26
The following loads on the structure can be distinguished, from self-weight, earth load (back fill),
rock protection, ballast concrete and traffic load.
Table 44: Load types and load factors
Load types
SLS
ULS
ULS - favourable
Self-Weight
Permanent
1,00
1,25
0,95
Hydrostatic load MWL
Permanent
1,00
1,15
0,95
Earth Load
Permanent
1,00
1,15
0,95
Rock protection
Permanent
1,00
2,00
0,95
Ballast concrete
Permanent
1,00
1,25
0,95
Traffic load
Variable
1,00
1,50
0,00
With these load factors the total loading on the tunnel in SLS and ULS will be calculated. Now the
self-weight of the elements need to be determined, table 46. For this the concrete and steel area is
multiplied with its specific mass,
table 45.
Table 45: Material properties
Material properties
3
Density
[kN/m ]
Water
10,35
Concrete
23,2
Steel
77
Ballast concrete
23,2
Table 46: Steel / concrete area and the q-load
Self-weight
Self-weight roof
Ac-Roof
As-Roof
q
1535000
65000
2
[mm ]
2
[mm ]
1,535
0,065
2
35,612
[kN/m]
2
[m ]
5,005
[kN/m]
Total
40,617
[kN/m]
[m ]
Self- weight floor
Ac-Floor
As-Floor
q
1840000
60000
2
[mm ]
2
[mm ]
Kubilay Bekarlar – Master Thesis
1,84
0,06
2
42,688
[kN/m]
2
[m ]
4,62
[kN/m]
Total
47,308
[kN/m]
[m ]
30
August – 2016
The next step is the determination of the total loading on the tunnel roof / floor by summing the
self-weight of the structure, the ballast concrete, hydraulic pressure, rock protection and backfill.
This is done in table 47 below.
Table 47: Total loading on the elements
Element
Roof
SLS [kN/m]
ULS [kN/m]
Floor
SLS [kN/m]
ULS [kN/m]
Self-Weight
40,62
50,77
-245,92
-282,81
Hydrostatic load
MWL
Rock protection
128,96
148,30
Hydrostatic load
MWL
Self-Weight
47,308
44,94
11,65
23,30
Ballast concrete
11,9505
11,35
Traffic load UDL
10,00
0,00
Total
181,23
222,38
Total
-176,6615
-226,51
Walls - Top
SLS [kN/m]
ULS [kN/m]
Wall - Bottom
SLS [kN/m]
ULS [kN/m]
Hydrostatic load
MWL
Back fill
134,79
155,01
306,26
352,20
5,83
6,7045
Hydrostatic load
MWL
Back fill
60,35
69,40
Total
140,62
161,71
Total
366,61
421,60
Element
5.2
Design moment calculation
The design moment Med is determined for different spans of the tunnel cross section. This is done
by making use of an approximation (rule of thumb),
. These values were verified
by making use for a framework program Matrixframe, for the reinforced concrete tunnel. This
showed that the values of the hand calculation and the computer program do coincide.
The calculated design moment MEd will be compared with the moment resistance of the cross
section. When the design moment of a certain span exceeds the moment capacity of the cross
section, than the maximum span of that particular cross section is exceeded. The same holds for
the shear capacity. The span which results in a shear force which exceeds the shear force capacity
is also the limit span for the SCS tunnel cross section. The smallest span of these two checks is the
governing or limiting span. The calculated internal design forces for different spans can be found in
Appendix (28.1).
5.3
Capacity SCS tunnel
Provided the dimensions and the loading on the SCS tunnel elements are known, now the capacity
can be calculated. In order to do so first the materials that are applied need to be specified.
Concrete class C30 and steel class S355 is applied. The properties of these materials are listed in
table 48 below.
Kubilay Bekarlar – Master Thesis
31
August – 2016
Table 48: Material properties steel and concrete
Material properties
Steel S355
Elasticity modulus
2
[N/mm ]
Concrete
2
[N/mm ]
fy
355
fck
30,0
γs
1,1
γc
1,5
fyd
322,73
fcd
20,0
fctk, 0,05
E - steel
E - concrete
2
200000
[N/mm ]
34000
[N/mm ]
2
2,0
fctd
1,35
The preliminary dimensions of the cross section are summarized in table 57. In this table there is
calculated with a changing thickness of the outer steel and the inner steel over the length roof,
floor and wall. This has to do with the fact that the flexural moment causes different tensile and
compressive stresses on the inner and outer side of the over the length of the element. This
variation of the flexural moment over the length of the element causes different internal forces.
That is why the calculation will be done for the outer side and inner side of each element, figure 13
. In order to account for this difference, the calculations are performed for changing steel layout.
This will be explained in more detail in the moment capacity calculation.
Figure 13: Explanation of the outside and inside section of the roof (red) and floor (blue) elements
In the table 49, h is the total height of the element, b is the chosen width unit, t sc the thickness of
the steel plate compression zone, tst the thickness of the steel plate in the tensile zone, hc is the
height of the concrete only, tweb is the thickness of the diaphragm (web) and ctc web is the centre
to centre distance of the diaphragm.
Table 49: Dimensions of the elements
Dimensions
Roof
Floor
Walls
outside
inside
outside
inside
outside
Inside
h [mm]
1600
1600
1900
1900
1500
1500
b [mm]
1500
1500
1500
1500
1500
1500
tsc [mm]
25
35
20
35
20
25
tst [mm]
35
25
35
20
25
20
hc [mm]
1540
1540
1845
1845
1455
1455
tweb [mm]
20
20
20
20
10
10
ctc web [mm]
1500
1500
1500
1500
1500
1500
Kubilay Bekarlar – Master Thesis
32
August – 2016
5.3.1
Shear capacity SCS tunnel (ULS)
After the dimensions of the cross section are determined, the capacity checks can be made. In first
place the shear force capacity will be calculated. The shear force capacity has two components.
One is the concrete shear force capacity and the other the steel shear force capacity. First the
shear force capacity of the concrete part will be determined. The following steps will be performed,
consecutively the height of the concrete zone will be determined and hereafter the total concrete
area is calculated. With the ultimate allowable shear stress in concrete determined, the shear force
resistance of the concrete part will be calculated. These steps are shown in the formulas below.
(
)
In which:
h is the total height of the cross section
tsc is the thickness of the steel plate in the compression zone
tst is the thickness of the steel plate in the tensile zone
hc the height of the concrete
Ac is the concrete area
τrd,c,min is the allowable shear stress in concrete
fctd is the concrete tensile design stress
fctk is the concrete tensile characteristic stress
fcd is the compressive design stress of concrete
Ac is the concrete area
Vrd,c is the shear force resistance of the concrete part
Now the shear force resistance for the steel will be calculated. First the height of the diaphragm
(web) will be determined. This is used to calculate the total steel area that contributes to the shear
force resistance of the cross section. With this area and the design yield stress of the steel known,
the steel shear force resistance can be calculated. These steps are summarized below:
In which:
hs,web is the height of the web
Av,s is the steel area that contributes to the shear force resistance
Vrd,s is the shear force resistance by steel
Vrd,c+s is the total shear force resistance contributed by concrete and steel
Kubilay Bekarlar – Master Thesis
33
August – 2016
Table 50: Shear force capacity
Shear capacity
Roof
Floor
Walls
outside
inside
outside
inside
outside
inside
τrd,c,min [N/mm ]
0,54
0,54
0,54
0,54
0,54
0,54
Vrd,c [kN]
1249
1249
1496
1496
1180
1180
hs,web [mm]
2
1540
1540
1845
1845
1455
1455
Av,s [mm ]
30800
30800
36900
36900
14550
14550
Vrd,s [kN]
5739
5739
6875
6875
2711
2711
Vrd,c+s [kN]
6988
6988
8372
8372
3891
3891
Vrd [kN/m1]
4659
4659
5581
5581
2594
2594
2
This calculated shear force resistance of the cross section will be compared with the design shear
force Ved due to external loading and self-weight. The span, for which the acting shear force is
larger than the shear force resistance, is the limiting span for the shear force check. In table 51
below the design shear forces for different spans of the tunnel cross section is given.
Table 51: Design shear force for different spans
Ved (ULS)
Span 15 m
[kN]
Span 20 m
[kN]
Span 25 m
[kN]
Span 27m
[kN]
Ved – Roof
1667,81
Ved - Roof
2223,75
Ved - Roof
2779,69
Ved - Roof
3002,1
Ved - Floor
-1698,84
Ved Floor
-2265,12
Ved Floor
-2831,41
Ved Floor
-3057,9
Ved-Wall top
986,74
Ved-Wall top
986,74
Ved-Wall top
986,74
986,74
Ved-Wall
bottom
2032,79
Ved-Wall
bottom
2032,79
Ved-Wall
bottom
2032,79
Ved-Wall
top
Ved-Wall
bottom
2032,79
Because both, the shear force resistance and the design shear forces have been determined, the
unity checks for different span can be calculated. These values are summarized in table 52.
Table 52: Shear force capacity check of the roof floor and wall
Unity check Roof
Span 15 m
[kN]
Span 20 m
[kN]
Span 25 m
[kN]
Span 27 m
[kN]
Ved - Roof
1667,8
Ved - Roof
2223,8
Ved - Roof
2779,7
Ved - Roof
3002,1
Vrd - Roof
4659,0
Vrd - Roof
4659,0
Vrd - Roof
4659,0
Vrd - Roof
4659,0
Unity check
0,36
Unity check
0,48
Unity check
0,60
Unity check
0,64
Unity check Floor
Span 15 m
[kN]
Span 20 m
[kN]
Span 25 m
[kN]
Span 27 m
[kN]
Ved - Floor
1698,8
Ved - Floor
2265,1
Ved - Floor
2831,4
Ved - Floor
3057,9
Vrd - Floor
5581,0
Vrd - Floor
5581,0
Vrd - Floor
5581,0
Vrd - Floor
5581,0
Unity check
0,30
Unity check
0,41
Unity check
0,51
Unity check
0,55
Kubilay Bekarlar – Master Thesis
34
August – 2016
Unity check Wall top
[KN]
Unity check Wall bottom
[KN]
Ved - Wall
986,74
Ved - Wall
2032,8
Vrd - Wall
2594,0
Vrd - Wall
2594,0
Unity check
0,38
Unity check
0,78
As there can be seen in table 52 the SCS sandwich tunnel roof can resist the shear load for all
calculated spans. There can also be stated that it can resist the loads of even larger spans. The
same holds also for the floor, also here the loads of the largest span of 27 m can be carried. The
shear force resistance of the outer wall is not depending on the span of the cross section. Also this
element can resist the occurring design load on the top of the wall as well as on the bottom side.
There can be seen that the tunnel element has the biggest unity check value at the bottom side of
the outer wall.
5.3.2
Moment capacity SCS tunnel (ULS)
After the shear force resistance calculations, the moment capacity for the SCS tunnel element will
be checked. This will be done for the roof, floor and wall element of the SCS tunnel. These
calculations will be performed for each element in the changing tensile and compression zone.
Doing so, for each element two moment resistance calculations will be performed for the two
different steel plate configuration. The dimensions of the steel plates and concrete layer are
determined such that the moment resistance Mrd of the cross section is larger than the design
moment Med. In order to determine the moment resistance of the cross section the following
calculation steps are carried out.
In which:
B is the width
tsc is the thickness of the steel plate in the compression zone
tst is the thickness of the steel plate in the tension zone
fyd is the design yield strength of the steel
Nsc is the normal force in the steel plate in the compression zone
Nst is the normal force in the steel plate in the tensile zone
Ncu is the concrete compression force
fcd is the design compression strength of the concrete
hc is the height of the concrete
xu is the height of the compression zone in the ultimate limit state
The first step is the calculation of the compressive and tensile forces in the steel plates. This is
done by multiplying the steel area with the design yield strength of steel. This way the concrete
compressive force Ncu in the ultimate limit state can also be calculated. The force distribution and
the level arms over the cross section are illustrated in figure 14. These forces with their internal
level arms create a moment which is known as the moment resistance.
Kubilay Bekarlar – Master Thesis
35
August – 2016
Figure 14: Cross sectional forces in a scs tunnel element.
The moment resistance is calculated in two steps. First the moment due to the compressive forces
will be calculated, denoted as Mrd,c. This has two components the normal force in the steel
component and the concrete compressive force. By taking the centre of the bottom steel plate as
the reference line, the normal force in this element is left out of the moment equilibrium. This way
the moment resistance due to the compressive forces is determined. This is shown in figure 15.
Figure 15: Compressive forces, level arms and design moment resistance SCS sandwich element
The same is done for the moment as a result of the tensile force in the bottom steel plate, which is
denoted as Mrd,t. The internal level arm is chosen such that the force in the steel plate is left out of
the moment equilibrium calculation. This is illustrated in figure 16 below.
Figure 16: Tensile force, level arm and design moment resistance SCS sandwich element
The smallest moment out of these two determined moments will be taken as governing moment
which is used for the design. To get the moment per meter this value will also be divided by the
width. These steps were carried out in a spreadsheet program and the results are summarized in
table 53 below.
Kubilay Bekarlar – Master Thesis
36
August – 2016
Table 53: bending moment capacity
Bending capacity
Roof
Floor
Walls
outside
inside
outside
inside
outside
inside
Nsc, rd [kN]
12102
16943
9682
16943
9682
12102
Nst, rd [kN]
16943
12102
16943
9682
12102
9682
Ncu,rd [kN]
4841
-4841
7261
-7261
2420
-2420
N axial
1295
1295
2040
2040
2308
2308
x [mm]
308
308
369
369
291
291
Mpl,rd,c [kNm]
27612
21642
33737
23004
20556
17733
Mpl,rd, t [kNm]
27637
20037
33357
19761
19728
16151
Mpl,rd [kNm]
27612
20037
33357
19761
19728
16151
Mpl,rd/m [kNm/m]
18408
13358
22239
13174
13152
10768
As there can be seen in table 53, the steel plates are exerted to compressive and tensile stresses
over the length of the roof / floor. This has to do with the moment distribution that varies over the
element. For example the roof element is exposed to tensile forces on the outer side and
compressive forces on the inner side. This is only valid for the parts close to the connection with
the walls. The opposite is valid for the middle of the span, in which tensile forces on the bottom
and compressive on top. This results in a different moment capacity for the SCS roof element for
its mid-span and the sides. This difference is denoted in the table as inside and outside.
Now the design moment will be compared with the moment resistance. In the previous case the
biggest moment was used as the governing moment and the structure was designed on that. Also
a hand calculation was used to calculate the internal forces. However in this case the changing
moment distribution will be taken into account. The design moments will be the moment in the mid
span and the moment at the connection of the roof/floor-wall. This is the reason why the
Matrixframe output will be used, since it gives a detailed output of the moment distribution. As for
the floor element the moment distribution differs from the hand calculation, this has to do with the
uniform elastic soil bedding. While in reality the structure is not supported uniformly and there
might be gaps underneath the structure. If these moments were used than the structure capacity
would be overestimated. So since the loading on the floor element is only slightly bigger, the
moment distribution of the roof element can be used with a small safety margin. In figure 17 the
moment distribution for a span of 27 m is given. The dimensions of the steel plates and concrete
were chosen such that these moments plus safety margin won’t be bigger than the moment
resistance of the element.
Figure 17: Design moment distribution for a span of 27 m
Kubilay Bekarlar – Master Thesis
37
August – 2016
In table 54 below the design moments and the moment resistances are given. The added margin
on the floor design moment is 1000 kNm on top of the design moment of the roof. Also the unity
checks are given, which show that with the current dimensions the cross sectional moment
capacity is larger than the design moment.
Table 54: Unity check moment capacity
Bending capacity
5.3.3
Roof
Floor
Walls
outside
inside
outside
inside
outside
inside
Mpl,rd/m [kNm/m]
18408
13358
22239
13174
13152
10768
Med [kNm/m]
15247,4
10607,5
16247,4
11607,5
8029,1
0
Unity Check
0,829
0,794
0,73
0,881
0,611
0
Design of stud connectors and stiffeners
In order to have a good connection between the steel plate and the concrete stiffeners and /or
studs are applied. As the name states, the stiffeners also give the steel plate enough stiffness
which prevents it from deforming during concrete pouring. These elements are welded on both
sides of the steel plates. They transfer the forces in the steel plates to the concrete. In figure 18
the studs and stiffeners are illustrated for the upper steel plate of a sandwich element.
Figure 18: Illustration of stiffeners (L- shaped) and shear studs (straight)
First the design longitudinal shear force will be determined. For this a part of the cross section is
assumed to be shearing, see figure 19.
Figure 19: Longitudinal shear of a steel concrete connection
In the next stage the centre of gravity of the cross section will be determined. Here after the
moment of inertia Fizz, first moment of area Spa and the shear force per unit length Sax will be
determined.
The calculations for the roof element will be presented below:
Kubilay Bekarlar – Master Thesis
38
August – 2016
Figure 20: Dimensions used for a longitudinal shear calculation
(
)
Figure 21: Development of the longitudinal shear force in the SCS roof element
Since the longitudinal shear force per unit length is known the total longitudinal shear force can be
calculated as follows:
Another way to compute the longitudinal shear force can be done by using the moment:
Now the capacity of the stiffener is determined. This element will yield if the maximum stress of
the connection between the stiffener and the steel plate is reached. So the maximum moment the
stiffener can bear can be calculated as follows:
In which:
M is the moment
σ is the yielding stress fyd
w is the section modulus
t stiffener is the thickness of the stiffener
The resisting bending moment of the stiffener should be in balance with the bending moment
caused by the interaction of the stiffener and the concrete, figure 22. This is determined as follows:
Kubilay Bekarlar – Master Thesis
39
August – 2016
Figure 22: Forces acting on a stiffener
In which:
b is the width of the stiffener
fcd is the design compressive stress of concrete
So the force in the stiffener can be written as:
The only unknown is the “a” which can be acquired by solving the equation of the moments. This
results in:
√
The capacity of a stud is calculated with the following formula:
Figure 23: Variable dimensions of a steel stud element
The minimum length of a stud should be 4 times the stud diameter, where the diameter should be
in the range of 16 mm ≥ Ø ≤ 25 mm.
There are two possible failure mechanisms for steel studs one which is the shearing of the steel
stud, see figure 24 and the other being the crushing of the concrete, figure 25. The capacity of the
steel stud will be calculated for both cases. For determining the number of studs required the
lowest stud capacity will be used, since the lowest capacity is governing.
Figure 24: Shearing of a steel stud
The shear force capacity of the stud for shearing can be calculated as follows:
Kubilay Bekarlar – Master Thesis
40
August – 2016
In which:
fyd is the design yield stress of steel
d is the diameter of the steel stud
Figure 25: Crushing of concrete
The shear force capacity of the stud for concrete crushing can calculated with:
√
In which:
feck is the characteristic compressive strength of concrete
Ecm is the modulus of elasticity of concrete
If both the capacity of the stiffener and stud is combined both contributions are summed:
The results of these calculations are shown in
table 55 below.
Table 55: Calculation of shear force capacity of stiffener and stud in respectively kN/m and kN
Roof
Floor
Nc
[mm]
Izz
4
[mm ]
6,4 x 10
a
[mm ]
3
12,05 x 10
a
[N/mm]
570
668
392
a
[kN]
3847,5
4510
1117
Sz
Sx
Rs
372
Walls
417
10
351
9,11 x 10
6
20 x 10
10
6
10
6
12,5 x 10
Roof
Floor
Walls
outside
inside
outside
inside
outside
inside
2
322,72
322,72
322,72
322,72
322,72
322,72
2
20,0
20,0
20,0
20,0
20,0
20,0
2
30,0
30,0
30,0
30,0
30,0
30,0
2
fyd
[N/mm ]
fcd
[N/mm ]
fck
5,3 x 10
[N/mm ]
Ecm
[N/mm ]
35000
35000
35000
35000
35000
35000
d,stiff
[mm]
15
15
15
15
15
15
W
[mm ]
56250
56250
56250
56250
56250
56250
a
[mm]
42,6
42,6
42,6
42,6
42,6
42,6
F,stiff
[kN]
852,1
852,1
852,1
852,1
852,1
852,1
d,stud
[mm]
25
25
25
25
25
25
α
-
1,0
1,0
1,0
1,0
1,0
1,0
γ
-
1,25
1,25
1,25
1,25
1,25
1,25
3
Kubilay Bekarlar – Master Thesis
41
August – 2016
F stud shear
[kN]
127
127
127
127
127
127
F stud crushing
[kN]
149
149
149
149
149
149
Now the layout of the stiffeners (150x150x15 mm3) and the studs (35 ɸ - h 100 mm) will be
determined. As stated before the studs and stiffeners should be able to bring over the force of the
steel plates to the concrete. Despite the forces in the steel plates changes over the length of the
element (roof, floor and wall), one layout will be applied for one element. In practice, changing
layouts over an element is not feasible. That is why the governing steel force (max) will be used in
the calculation, denoted in bold
table 55. The layout for the studs and stiffeners will be calculated as follows:
In which:
n is the number of studs welded to the plate
L is the stiffener unit length
The following layout is determined, see Figure 26 and Figure 27.
Figure 26: 3-D illustration of stiffener and stud layout
Figure 27: 3-D illustration of stiffener layout
Kubilay Bekarlar – Master Thesis
42
August – 2016
The unit length which is needed in order to transfer the load from the steel into the concrete is 3,5
m. However there is a boundary condition, which is related to the maximum amount of concrete
that can be poured in one unit. This amount is 10 m3 in one pour.
From the calculation above there can be seen that also the unit volume does not exceed the 10 m 3.
This is calculated for the governing height of the floor slap, which is 1,9 m.
5.4
Uplift and immersion calculations
The floating and immersing processes are essential aspects of immersed tunnels. This means that
the tunnel elements should be designed such that they can float up and be immersed. For this
reason balance equations are used to check whether the floating and immersing conditions hold. If
this tunnel cross section does not hold the balance conditions, then changes of cross section are
inevitable.
The dimension of the span of the element is taken as maximum, which is 27 m. This is the span
which is needed for the reference project in order to cover the transition zone in two spans of 27
m. In the previous section the dimensions of the elements in a scs sandwich tunnel have been
determined, now the uplift and immersion calculations can be made. For this the weight of the
tunnel element has to be determined first. In order to do so the concrete and steel area applied
has to be determined. These calculations are made in table 56 and table 57 below.
Table 56: Determination of concrete area
Concrete
Area Element
b [mm]
h [mm]
2
A [mm ]
Element
Roof
Outer wall 1
b [mm]
h [mm]
2
A [mm ]
Floor
1600
1900
3040000
Outer wall 1
1600
1600
2560000
27000
1900
51300000
Roof 2
27000
1600
43200000
Inner wall 2
1000
1900
1900000
Inner wall 2
1000
1600
1600000
Gallery floor 4
3250
1900
6175000
Gallery roof 4
3250
1600
5200000
Inner wall 3
1000
1900
1900000
Inner wall 3
1000
1600
1600000
27000
1900
51300000
Roof 6
27000
1600
43200000
1600
1900
3040000
Outer wall 4
1600
1600
2560000
Gallery floor 1
3250
200
650000
Floor 2
Floor 6
Outer wall 4
Walls
Outer wall 1
1600
7900
12640000
Inner wall 2
1000
7900
7900000
Inner wall 3
1000
7900
7900000
Outer wall 4
1600
7900
12640000
Total concrete area
Total concrete area
Kubilay Bekarlar – Master Thesis
159735000
159,735
2
mm /m
2
m /m
43
August – 2016
Table 57: Determination of steel area
Steel Area
2
Element
t [mm]
l [mm]
A[mm ]
Outer side floor
35
62450
2185750
Inner side floor
25
57250
1431250
Outer side roof
40
62450
2498000
Inner side roof
25
57250
1431250
Outer side wall outside
30
11400
684000
Inner side wall inside
20
7900
316000
Web plate - ctc 1500
20
3356733
1500
2
Total steel area
11902983
[mm /m]
Total steel area
11,902
[m /m]
2
Because the surfaces have been calculated, the weight can be determined by multiplying the area
with the specific weight. Consequently the total weight of the structure will be calculated. Only the
amount of ballast concrete to be applied after immersion needs to be calculated. Since the total
height of the structure is already determined, the space for ballast concrete can be calculated as
follows:
In which:
hballast is the height of the ballast concrete
htotal is the total inner height of the structure
hfree traffic is the free height which is needed for the traffic
hequipment is the height needed for the installations
hasphalt is the height of the asphalt which will be executed at a slope of 2%
All elements are known in order to make a buoyancy balance calculation. For the floating up
conditions the upward hydrostatic load, should be about 1% larger than the weight of the tunnel
element. For the immersing condition, in order to have a safety margin against floating up the
weight of the element need to be increased further by applying ballast (with water during
immersing later replaced with ballast concrete). This safety margin is about 7,5%. The results of
these calculations are listed in the table 58 and table 59 below.
(
)
Table 58: Floating calculation of SCS sandwich tunnel element
Floating calculation
3
3
[m ]
[kN/m ]
[kN]
[factor]
Concrete
260,31
23,50
6117,17
1,00
Steel
11,90
77,00
916,53
1,00
Ballast
0,00
23,50
0,00
1,00
Kubilay Bekarlar – Master Thesis
44
August – 2016
Hydrostatic load
711,93
10,00
7119,30
1,00
Check
0,99
<1
Table 59: Immersion calculation of SCS sandwich tunnel element
Immersion calculation
3
3
[m ]
[kN/m ]
[kN]
[factor]
Concrete
260,31
23,20
6039,08
1,00
Steel
11,90
77,00
640,38
1,00
Ballast
50,22
23,20
1165,10
1,00
Earth
0,00
7,50
0,00
1,00
Hydrostatic load
711,93
10,35
7368,48
1,00
Check
height
0,93
1,06
>1
From the calculations above there can be concluded that the designed SCS sandwich tunnel
element fulfils the floating and immersion conditions. Also in this case there should be pointed out
that for the immersing conditions a lower concrete specific weight is assumed. This is done to
account for the uncertainties regarding the concrete density and inaccurate concrete thickness
(inaccuracy during filling of the concrete / void forming).
Kubilay Bekarlar – Master Thesis
45
August – 2016
5.5
Drawing of the SCS base case design
Figure 28: Cross section of the SCS sandwich tunnel element
Kubilay Bekarlar – Master Thesis
46
August – 2016
6
BASE CASE SUMMARY
As has been noted, this base case design has several purposes. One purpose is to investigate
whether or not the transition zone of a 2x4 lane to a 2x3 lane immersed tunnel can be executed as
reinforced concrete tunnel part and what are its limits regarding the cross sectional span (in case
the max. reinforcement ratio applied). Another aim of the base case design is that it will be
checked whether or not the SCS sandwich tunnel element can realize a 2x4 lane with safety lanes
on both sides. In other words to check whether or a SCS sandwich tunnel can make a span of 27m.
This way insight will be gathered in the design rules and parameters for the design of a SCS
sandwich and reinforced tunnel. The designed SCS sandwich tunnel will be used for further detailed
analysis in the remainder of this research.
First the base case for a reinforced concrete tunnel was worked out. Initially the loading on the
tunnel was worked out, which resulted in the determination of the design loads. These design loads
were used to determine the design forces, such as the moment, shear force and normal force. First
hand calculation was used, which was checked with a framework software program Matrixframe.
There was concluded that the overall results of the hand calculations and the framework software
program calculation were in accordance with each other. The only difference that was present had
to do with the assumptions that was made for the bedding boundaries. In which the bedding was
assumed to be uniform over the entire length of the floor. However in reality this might not be the
case. This has to do with the fact that scour may occur below the floor element, which will result in
higher loads than assumed with a uniform bedding. In order not to underestimate the design load
on the structure, a hand calculation is used for further design. Since both calculations correspond
well, this is allowed.
Here after the capacity of the reinforced tunnel is determined for the roof, floor and wall element.
First the cross sectional dimensions were determined. Here after the moment capacity check,
normal stress capacity check, shear force capacity check and crack width control was performed for
the roof. For which a reinforcement ratio of 1,2 % in tensile zone and 0,6% in compressive zone
has been applied with a span of 22 m. For this reinforcement ratio and span, the moment capacity
was not exceeded. The normal stress in the cross section was slightly higher than what is allowed.
Shear force capacity with stirrups was not exceeded, however the crack width was larger than the
maximum crack width. For the roof element these checks were repeated for different spans. From
these calculations there was seen that the crack width was the limiting factor for the span. By
changing the reinforcement ratio (1,8% in tensile zone and 0,3% in compression zone) and its
layout the critical span for the crack width was calculated again, since this is the governing span.
This way the critical span for the roof element became 18 to 19 m.
The same steps for the roof element are repeated for the floor element. This time the
reinforcement ratio is 1,59% in tensile zone and 0,26% in the compressive zone. The moment
capacity check, normal stress check, shear force check and the crack width control were performed
for different spans of the element. From these calculations there was again concluded that the
crack width control was the critical factor, since it resulted in the smallest span. This span is 21 m
for the floor element.
Now the outer wall will be checked as well. Here the capacity checks were performed for a span of
the roof and floor of 20 m. This has to do with the fact that the limiting span for the roof is about
19 m and for the floor it is about 21 m. Since the smallest span is the governing span, 19 m should
be taken. In order to have a small safety margin 20 m span is taken as the loading on the
structure, respectively the outer wall.
Kubilay Bekarlar - Master Thesis
- 47 -
August – 2016
After the dimensions of the reinforced concrete tunnel are determined the uplift and immersion
checks were done. The designed tunnel cross section should hold for the buoyancy balance
equations, if not adjustments should be made. From the calculations there was concluded that the
reinforced concrete tunnel is in accordance with the immersion and floating boundary condition.
Just like the reinforced concrete tunnel, also for the SCS sandwich tunnel first the external load per
meter width was determined. With the design loads due to external loading, self-weight etc. the
total design forces acting on the structure will be determined (M, V and N forces). Because the
loading is known, next the dimensions are estimated. These dimensions determined by earlier
experience will be checked later on and adjusted if they don’t fulfill the boundary conditions. The
estimated dimensions for the cross section are the thicknesses of the steel plates, thickness of the
concrete, c.t.c. distance of the diaphragms and the thickness of the diaphragm.
Since the dimensions are determined, the checks can be performed. First the shear capacity check
is performed for different spans of the elements. This is an iterative process and if the design shear
force exceeded the shear force resistance the cross sectional dimensions were adjusted. From the
calculations there was concluded that the shear force capacity, for all spans investigated 15 -27 m,
did not exceed the shear force capacity.
The second check is the moment capacity check. For this step the moment distribution for the
maximum span of 27 m is used. Because the changing moment distribution is of importance for
this analysis, the Matrixframe output will be used rather than the hand calculation. For the chosen
dimensions of the elements and the maximum span of 27 m, there was concluded that each
element fulfilled the capacity condition.
Everything is known to determine the stud connectors and the stiffeners. The dimensions of the
stiffeners and studs applied is respectively 150x150x15 and 35 ɸ - h is 100 mm, with a ctc distance
of 500 mmm. With these dimensions the length of a steel unit is 3,5m. This length is needed to
transfer the forces in the steel shell to the concrete. There is also checked whether the unit volume
meets the executional boundary condition, which states that the volume should be less than 10 m 3.
The last step is again checking whether the floating and immersing conditions are met, if not the
ballast or the structural dimensions needs to be adjusted. From the calculations there can be seen
that the floating and immersion conditions are met (this was also an iterative process).
All things considered, from the results above there can be concluded that even with the maximum
reinforcement ratio applied for a reinforced concrete tunnel, a span of 27 m is not feasible. The
normative check that determines the critical span is the crack width control. In the calculations this
condition was exceeded first. Whereas for the SCS sandwich tunnel no crack width check is
needed. Nor is there a limit for the steel applied, against brittle failure. From the calculations
performed, there is concluded that a span of 27 m with a SCS sandwich element is feasible. The
designed SCS sandwich base case will be used for further analysis.
Kubilay Bekarlar - Master Thesis
- 48 -
August – 2016
FEM Analysis SCS Immersed Tunnel
& Design Optimization
Kubilay Bekarlar - Master Thesis
- 49 -
August – 2016
7
FEA MODEL
7.1
Introduction
In the previous chapters a “Base Case” design was made, for a SCS tunnel. In order to get a good
understanding of the structural response to the loadings a finite element model (FEM) needs to be
used. The finite element analysis (FEA) program that will be used is DIANA. Dimensions of the
earlier designed “Base Case” of the SCS sandwich tunnel will be used for this model. This program
can perform a linear as well as nonlinear structural analysis. Before the actual modelling in DIANA,
the essence of FEM analysis, linear analysis and non-linear analysis was studied in detail. The nonlinear analysis can also be separated in material (physical) nonlinear analysis, geometrical
nonlinear analysis and boundary (contact) nonlinear analysis. These types of analysis are discussed
in detail in Appendix F.
7.2
2-D or 3-D Analysis
In this section there will be explained why there will be chosen for a 2-D or 3-D analysis for the
SCS sandwich tunnel element.
Whether 2-D or 3-D analysis will be performed depends on type of foundation that will be assumed
to be present in the model. In case the foundation is assumed to be well behaving, than 2-D
analysis will suffice. Well behaving foundations are foundations that deliver permanent uniform
support to the structure resting on top of it.
However if the support is assumed to be non-uniform due uneven settlement, then local
concentrated loads are introduced. These concentrated loads result in a complex redistribution of
the internal forces. In that case a 3-D analysis should be preferred in order to see how the forces
are redistributed (which is not possible in 2-D).
In contradictory to reinforced concrete immersed tunnels, SCS immersed tunnels don’t consist of
segments that form one element. SCS immersed tunnels are manufactured as an element of
around 100 m. This means that uneven settlement of the subsoil can indeed lead to large force in
the axial direction of the tunnel. These forces should also be investigated by looking in the axial
direction. However, this can also be done by a FEM analysis or a hand calculation analysis. This is
why for the cross sectional analysis of a SCS element a 2-D structural analysis is sufficient.
7.3
Material model
Finite element programs have different material models in their database that can simulate the
behaviour of the materials applied for a certain loading. In this chapter the chosen material models
are named and the reasons why they are chosen will be explained.
7.3.1
Material model - concrete linear elastic
Concrete: stress strain diagram (one with tension softening), Ec
For the self-compacting concrete class which will be applied to the SCS sandwich element is class
C30. Concrete behaves differently in the elastic and plastic state. In figure 29 below, an idealized
stress strain diagram is given for concrete in the elastic state. The elasticity modulus of concrete
applied for the SCS sandwich element is Ecm 34 000 N/mm2. For the Poisson’s ratio a value ⱱ = 0,3
is applied.
Kubilay Bekarlar - Master Thesis
- 50 -
August – 2016
Figure 29: Idealized elastic behaviour of concrete
7.3.2
Material model - steel linear elastic
Steel class S355 will be used for the model of the SCS sandwich plates, stiffeners and studs. The
steel will also behave differently in its linear and plastic domain. For the linear elastic domain of the
steel, the material behaviour is idealized as shown in figure 30. The elasticity modulus applied for
the linear domain of steel is Es 210 000 N/mm2. Poisson’s ratio ⱱ = 0,2 will be applied.
Figure 30: Idealized elastic behaviour of steel
7.4
Schematization of the SCS sandwich tunnel element
In this section the schematization of the SCS sandwich tunnel will be discussed in detail. One of the
aspects that will be covered first is the idealization of the tunnel structure. This has to do with the
fact that the SCS sandwich element will be simplified in order to reduce the computation time. The
degree of detail of the structure should be justified by the degree of detail that is needed as
output. Another issue is whether or not making use of the symmetry of the structure. To
understand the behaviour of the structure and to get insight in the distribution of the forces,
modelling only a part of the tunnel can suffice. This on the precondition that symmetry axis are
available.
7.4.1
Constraints
Since the model will perform a linear elastic analysis the computation time is limited. Also the
modelling time can be limited by using the mirror function which mirrors the model around the
symmetry axis. That is why the entire cross section will be modelled. Further the normal
displacements should be constrained as well. The bedding has to be constrained in all directions. In
figure 31 below the symmetry axis for the 2D cross section is given. This bedding element will be
constraint in two directions, X and Y.
Kubilay Bekarlar - Master Thesis
- 51 -
August – 2016
Figure 31: Symmetry axis of the SCS sandwich tunnel, base case design
7.4.2
Type of elements
There are several elements which can be used to model the SCS sandwich tunnel element. In this
section the elements that will be applied are discussed and the reason why they are chosen will be
motivated.
SCS elements
For the SCS element a plain strain element will be used. The element that will be applied is the
three node plain strain element– CL9PE. Plain strain elements are preferred because these
elements give good insight in the stress and strain distribution, from which the correct internal
forces will be calculated when intagrated over the height of an element. Another important aspect
of the plain strain element is that they are infinitely long in the axial direction. In figure 32 below
the schematization of a CL9PE element can be observed.
Figure 32: Plain strain element CL9PE
Bedding
The subsoil will be schematized with an interface element. These elements don’t have material nor
physical properties. Only linear and tangential stiffnesses of these elements have to be specified.
Interface element – CL12I is chosen which is a six node interface element. As there can be seen
the position of the nodes correspond with the position of the nodes of the plain strain element, see
figure 33.
Kubilay Bekarlar - Master Thesis
- 52 -
August – 2016
Figure 33: Interface element CL12I
7.4.3
Dimensions of the roof, floor and wall
The global dimensions of the structure that will be modeled in Diana are given in table 60 and table
61 below.
Table 60: Dimenions of the roof, floor and wall element
Roof
Floor
Wall
h [mm] – Total height of the element
1600
1900
1500
b [mm] – Unit width of the element
1500
1500
1500
to [mm] – Thickness steel plate outside
35
35
25
ti [mm] – Thickness steel plate inside
25
20
20
hc [mm] – Height of concrete
1540
1845
1455
tweb [mm] – Thickness of the diaphragm (web)
20
20
10
ctc web [mm] – Centre to centre distance of diaphragm (web)
1500
1500
1500
Table 61: Global dimensions
Dimensions
Width of one tunnel tube
27000 [mm]
Total width of the tunnel
63100 [mm]
Total height of the tunnel
11400 [mm]
Inner height of the tunnel
7900 [mm]
Now the tunnel elements will be schematized. This means that the elements which will be used will
be named and explained why they are chosen. The boundary conditions will be chosen as well as
the loading.
8
LINEAR ELASTIC ANALYSIS SIMPLIFIED MODEL
8.1
Material properties sandwich elements
Composite materials have different modulus of elasticity than the steel and concrete which it
consists of. The elastic modulus is an input value for the simple Diana model which will describe
the linear elastic behaviour of the model in a linear analysis. Since the modulus of elasticity and the
dimensions of the steel and concrete are known the elastic modulus of the SCS elements can be
derived, see figure 34 for a composed cross section.
Kubilay Bekarlar - Master Thesis
- 53 -
August – 2016
Figure 34: Composed cross section of steel and concrete
First of all there has to be stated that a SCS composite material is inhomogeneous. This means
that the composite material has different material properties in each of its axis. For a 2-D analysis
the material properties of the composite material will be determined in the XX direction and the YY
direction. That is why the elasticity modulus for the XX and YY direction will be determined.
The first calculation is the determination of the Exx Ixx and the Eyy Iyy of the overall cross section.
[N mm2]
( )
( )
(
)
[N mm2]
[N]
In which:
Es is the Young’s modulus of steel 2,1 x 105 [N/mm2]
Ec is the Young’s modulus of concrete 3,4 x 104 [N/mm2]
hc is the height of the concrete in the floor 1845 [mm]
hs is the total height of both steel plates of the floor 55 [mm]
b is the unit width 1000 [mm]
A is the surface area
z is the eccentricity of the steel plates towards the centre of gravity of the cross section
approximated by htot/2
Exx Ixx is the overall bending stiffness in the XX direction of the element
Eyy Iyy is the overall bending stiffness in the YY direction of the element
Eyy Ayy is the Young’s modulus times the area of each element
There can be seen that only for one direction the Eyy Ayy is determined, this weak axis will be
neglected. Now the Young’s modulus of the composed element has to be determined for its XX and
YY direction as well as the height. These values are denoted with an asterisk: E*xx , E*yy and h*.
There are three equations available and there are three unknowns, which means that these values
can be solved:
[N/mm2]
[N/mm2]
[N]
Kubilay Bekarlar - Master Thesis
- 54 -
August – 2016
From these calculations the representative values of the Young’s moduli E*xx , E*yy and the height
h* can be determined. These steps are done for the floor, roof and wall element of the SCS tunnel.
The results for each element can be seen in the table 62 and table 63 below.
Table 62: Calculation of the composed modulus of elasticity and height of the floor element
Floor
Inner steel plate
Concrete core
t [mm]
20
b [mm]
1000
2
E [N/mm ]
z [mm]
Outer steel plate
Composed
1845
35
1900
1000
1000
1000
210000
34000
210000
10
922,5
17,5
950
2
A [mm ]
20000
1845000
35000
1900000
4
1,67E+09
1,5375E+11
2,92E+09
1,58E+11
4
1,74E+10
5,23E+11
3,09E+10
5,72E+11
Ixx [mm ]
Iyy [mm ]
EA [N]
4,20E+09
6,27E+10
7,35E+09
7,43E+10
2
3,50E+14
5,23E+15
6,13E+14
6,19E+15
2
3,65E+15
1,78E+16
6,50E+15
2,79E+16
EIxx [N mm ]
EIyy [N mm ]
h*
2124,63
[mm]
Exx*
34961,36
[N/mm ]
Eyy*
34961,36
[N/mm ]
2
2
Only the results of the calculations for the roof and wall element are presented in Table 63. The
detailed overview is presented in Appendix (28.4).
Table 63: Calculation of the composed modulus of elasticity and height of the roof element
Roof
h*
Wall
1829,65
[mm]
h*
1681,77
[mm]
2
Exx*
35034,57
[N/mm ]
2
Eyy*
35034,57
[N/mm ]
Exx*
35503,98
[N/mm ]
Eyy*
35503,98
[N/mm ]
2
2
These values will be used for the definition of the material properties and physical properties of the
SCS sandwich cross section in Diana.
8.2
Determination of the passion ratio of composite material
A composite material has a different passion ratio than the materials which it consists of. This value
can be calculated from the volume fractions of each material relative to the total volume. So the
passion ratio of the SCS element is calculated as follows:
VSCS = VConcrete * Volume fraction concrete + VSteel * Volume fraction steel
For the calculation a spreadsheet program was used. The results can be seen in table 6 below.
Table 64: Calculation of the passion ratio for each composed element
Dimensions
Roof
Floor
Walls
h [mm]
1600
1900
1500
[mm]
b [mm]
1000
1000
1000
[mm]
Kubilay Bekarlar - Master Thesis
- 55 -
August – 2016
8.3
tsc [mm]
25
20
20
[mm]
tst [mm]
35
35
25
[mm]
hc [mm]
1540
1845
1455
[mm]
tweb [mm]
20
20
10
[mm]
Total stiffener Surface - 150x150x15
9000
9000
9000
[mm ]
Total stud surface - 35 Ø - 100
7000
7000
7000
[mm ]
Volume Fraction Steel
0,07
0,06
0,05
Volume Fraction Concrete
0,93
0,94
0,95
Passion ratio Steel
0,30
0,30
0,30
Passion ratio Concrete
0,20
0,20
0,20
Passion ratio SCS
0,21
0,21
0,21
2
2
Determination of the bedding constant
Also the bedding conditions need to be determined. The soil at the location of the reference project
is predominantly sandy. Rules of thumb are used in order to determine the design value of the
bedding constant. The characteristic value for the beddings constant of sand is 50 000 kN/m 3.
Design beddings constant should be in the range of characteristic value multiplied by √2 and
divided by √2.
√
√
Any value within this range can be chosen with regard to the local conditions. For the Diana model
a beddings constant of 60 000 kN/m3 is taken.
The tangential stiffness:
8.4
Main Dimensions being modelled
The dimensions of the tunnel that will be put in Diana are the centre to centre (c.t.c.) distance
between the elements. These main dimensions are visualized in figure 35 below.
Figure 35: Centre line dimensions of the tunnel cross section
Kubilay Bekarlar - Master Thesis
- 56 -
August – 2016
9
MODELLING SIMPLIFIED MODEL IN IDIANA - LINEAR
ELASTIC ANALYSIS
In this chapter the modelling of the simplified model will be explained. A detailed explanation of the
simplified model can be found in Appendix 9.
9.1
Geometry definition
First the geometry will be defined of the concrete tunnel structure as well as the subsoil. The
concrete elements will be schematized with dots and lines. While the subsoil is schematized with an
interface surface element.
9.2
Boundary conditions
After the geometry is defined the boundary conditions also need to be defined. A part of the
interface element is constraint in the Y direction and the lower left corner is constraint in the X, Y
and Z direction, see figure 36.
Figure 36: Cross sectional boundaries
9.3
Meshing
Now the mesh division of each element will be realized. The mesh division of the elements should
be chosen in accordance with the mesh of other elements, figure 37.
Figure 37: Schematization of the geometry division
9.4
Loads
In this stage the loads on the structure are applied including the self-weight, see figure 38.
Kubilay Bekarlar - Master Thesis
- 57 -
August – 2016
Figure 38: Loading on the tunnel cross section
9.5
Material and physical properties
In the final stage the material and physical properties are attached to the structure.
10
RESULTS OF THE SIMPLIFIED LINEAR ELASTIC ANALYSIS
10.1
Moment distribution and deflection
10.1.1
Lc1 – Load case 1
Figure 39: Bending moment due to gravity loading, Max. 0.324E7 Min. – 0.223E7
10.1.2
Lc2 - Load case 2
Figure 40: Load on the structure
Figure 41: Bending moment due to loading on top of the tunnel, Max. 0.121E8 Min. 0.776E7
Kubilay Bekarlar - Master Thesis
- 58 -
August – 2016
10.1.3
Lc3 - Load case 3
Figure 42: Load on the structure
Figure 43: Bending moment due to hydraulic pressure below the floor element, Max. 0.523E-5 Min. -0.65E-5
10.1.4
Lc4 - Load case 4
Figure 44: Load on the structure
Figure 45: Bending moment as a result of loading on the left outer wall, Max. 0.274E7 Min. -0.276E7
Kubilay Bekarlar - Master Thesis
- 59 -
August – 2016
10.1.5
Lc5 - Load case 5
Figure 46: Load on the structure
Figure 47: Bending moment as a result of loading on the right outer wall, Max. 0.218E7 Min. -0.249E7
10.1.6
Lcc - Load case total
Figure 48: Load on the structure
Figure 49: Bending moment as a result of all loads on the tunnel cross section, with interface bedding
Kubilay Bekarlar - Master Thesis
- 60 -
August – 2016
Figure 50: Bending moment as a result of all loads on the tunnel cross section, without interface element
10.1.7
Displacement Lcc – Load case total
Figure 51: Displacement of the structure as a result of total load (extreme scale) Max. 0.409E-2 Min. -0.392E-1
11
VALIDATION OF THE MODEL
11.1
Validation of moment distribution - deflections per load case
In this part the results from the simplified Diana model will be validated by the results of the hand
calculation. This will be performed for the moment and deflection of each load case acting on the
structure.
11.1.1
Load case 1 – self weight of the structure
The results obtained from Diana for the moment and the deflection of the roof element for load
case 1 are given in figure 52 below.
Figure 52 Left: Moment distribution in the roof element Right: Deflection of the roof element due to load case 1
These results will be checked by making use of rules of thumb from mechanics, figure 53.
Kubilay Bekarlar - Master Thesis
- 61 -
August – 2016
Figure 53: Rule of thumb from mechanics
The roof element can be schematized by a beam element which is fully inclined on both sides. The
load on top of it is a distributed load. In order to calculate the moments in the inclination and the
deflection of the mid span the following rules of thumb can be used:
A spreadsheet program has been used to calculate the deflection and moments. The results for
load case 1 are given in table 65 below.
Table 65: Deflection
hand calculation LC1
Deflection hand calculation LC1
q
45,75
L
28,4
E
35503000
h*
b
I
kN/m
m
kN/m
1,83
m
1
m
0,511
m
2
Hand calculation
Deflection
Diana model
0,00427
4
4,27
m
Deflection
0,00675
mm
6,75
m
mm
Table 66: Moment hand calculation and Diana model
Moment hand calculation and Diana model
Hand calculation
Diana model
M1
3075
kNm
M1
1800
kNm
M2
3075
kNm
M2
3200
kNm
Moment Middle
-1538
kNm
Moment Middle
-2000
kNm
Moment Total
4613
kNm
Moment Total
4500
kNm
Now the results from the hand calculation and the Diana model will be compared for the structure
loaded by its self-weight. There can be seen from the results that the deflection from the model is
larger than the deflection calculated by hand calculation, see figure 52 and table 65. This difference
can be explained by the difference in schematization. The hand calculation formula will give good
results is both sides of the beam is fully inclined. However in the model this is not the case. This
results in a slightly different value.
Kubilay Bekarlar - Master Thesis
- 62 -
August – 2016
The moments of the hand calculation and the Diana model also show some differences, this can be
explained by the fact that the roof element acts as a continuous beam. Since the formula is an
inclined beam on both sides, this gives different values for the hand calculation. However the total
moment should be the same. This is indeed the case, see figure 52 and table 66 above.
11.1.2
Load case 2 – vertical loading on top of the structure
The results from the model for the moment and the deflection of the roof element for load case 2
are given in figure 54 below.
Figure 54: Left Moment distribution in the roof element, Right: Deflection of the roof element due to load case 2
Table 67: Calculation of the deflection LC2
Calculation of the deflection LC2
q
172
kN/m
L
28,4
m
E
35503000
h*
b
I
kN/m
1,83
m
1
m
0,511
m
2
Hand calculation
Deflection
Diana model
0,016071
4
16,07
m
Deflection
0,0255
mm
25,5
m
mm
Table 68: Moment hand calculation and Diana model
Moment hand calculation and Diana model
Hand calculation
Diana model
M1
11561
kNm
M1
8000
kNm
M2
11561
kNm
M2
12000
kNm
Moment Middle
-5780
kNm
Mmiddle
-7500
kNm
Moment Total
17341
kNm
Mtot
17500
kNm
For the load case where the structure is loaded by an external force on top, there can be seen that
the results of the hand calculation and the Diana model show differences, see figure 54 and table
67. Just like explained in load case 1, this is due to the assumption of the hand calculation rule
which assumed that both sides are fully inclined. However in the model this is not the case.
The differences in the moments see figure 54 and table 68, can be explained by the fact that the
roof element should be schematized as a continuous beam. The rule of thumb however
schematizes the element as beam which is fully inclined on both sides. The total moment should be
in the same order of magnitude.
Kubilay Bekarlar - Master Thesis
- 63 -
August – 2016
11.1.3
Load case 3 – Vertical hydraulic loading on the bottom of the structure
Figure 55: Moment distribution obtained from Diana for loadcase 3
The moment distribution and deflection of the floor element due to the hydraulic loading obtained
from Diana is given in figure 55. There can be observed from the graphs that the moments and
deflections are very small, which indicates an error value. This can be explained by the fact that
the loading on an element connected with an interface element will result in an error value since it
assumes that the loading is diverged directly into the bedding. The loading on an element
connected with an interface element is schematized in figure 56 below.
Figure 56: Hydraulic loading on an element connected to an interface element
This meant that the model had to be adjusted in order to take the loading on the floor element into
consideration. The interface element on the bottom was removed and 4 supports were installed
instead. Doing so realistic moments and deflections were gathered from the model.
Figure 57 Left: Moment distribution in the floor element Right Deflection of the floor element due to load case 3
Table 69: Calculation of the deflection LC3
Calculation of the deflection LC3
q
273
kN/m
L
28,4
M
E
34961000
h*
2,124
kN/m
2
M
Kubilay Bekarlar - Master Thesis
Hand calculation
- 64 -
Diana model
August – 2016
b
I
1
0,799
M
m
Deflection
0,0166
4
16,6
m
Deflection
mm
0,027
27,0
m
mm
Table 70: Moment hand calculation and Diana model
Moment hand calculation and Diana model
Hand calculation
11.1.4
Diana model
M1
18349
kNm
M1
-10000
kNm
M2
18349
kNm
M2
-18000
kNm
Moment Middle
-9175
kNm
Mmiddle
13000
kNm
Moment Total
27524
kNm
Mtot
27000
kNm
Load case 4 – Loading on the left side of the tunnel element
In figure 59 below the moment distribution and the deflection of the wall element due to the
external loading is given.
The distributed load varying over the height of the tunnel can be analyzed in two steps. It can be
seen as the sum of a constant distributed load and a varying triangular load over the height, see
figure 58.
Figure 58: Rule of thumb from mechanics
Figure 59 Left: Moment distribution in the wall element, Right: Deflection of the wall element due to load case 4
For the displacement of the wall element there can be seen that this is very small, nearly zero see
figure 36. The structure acts like a rigid body for the forces acting on the outer wall. For the hand
Kubilay Bekarlar - Master Thesis
- 65 -
August – 2016
calculation the average distributed load will be taken, to check whether this small deflection can
confirm the results of the model.
The initially used average distributed load is:
(
)
Table 71: Calculation of the deflection LC4
Calculation of the deflection LC4
q
293
kN/m
L
9,65
M
E
35035000
h*
b
I
kN/m
2
1,682
M
Hand calculation
1
M
Deflection
0,396549
m
Diana
0,000476
4
0,476
m
Deflection
mm
<<
m
<<
mm
There can be seen that also the deflection of the hand calculation is very small, not even a half of a
millimetre, see table 71. There can be concluded that both approaches do coincide. For the
moment line however there are some differences. The moment at the bottom is much larger than
the moment at the top of the structure. This can be explained as follows. First there is an
increasing loading towards the bottom. This results in a larger moment at the bottom of the wall.
Secondly the larger floor element and a stiffer connection results in a larger moment at the bottom
side as well.
Table 72: Moment hand calculation and Diana model
Moment hand calculation and Diana model
Hand calculation
11.1.5
Diana model
M1
2274
kNm
M1
2750
kNm
M2
2274
kNm
M2
-200
kNm
Moment Middle
-1137
kNm
Mmiddle
-2100
kNm
Moment Total
3411
kNm
Mtot
3375
kNm
Load case 5 – Loading on the right side of the tunnel element
The same loading is applied again, but this time on the outer wall on the right side. This means
that the results are identical with an opposite sign. The same argumentation of the results as for
load case 4 is also applicable here. The results are given in figure 60 below.
Figure 60 Left: Moment distribution in the wall element, Right: Deflection of the wall element due to load case 4
Kubilay Bekarlar - Master Thesis
- 66 -
August – 2016
Table 73: Calculation of the deflection LC5
Calculation of the deflection LC5
q
293
kN/m
L
9,65
m
E
35035000
h*
b
I
kN/m
1,682
m
1
m
0,396549
m
2
Hand calculation
Deflection
Diana
0,000476
4
0,476
m
Deflection
mm
<<
m
<<
mm
Table 74: Moment hand calculation and Diana model
Moment hand calculation and Diana model
Hand calculation
Diana model
M1
2274
kNm
M1
2750
kNm
M2
2274
kNm
M2
-200
kNm
Moment Middle
-1137
kNm
Mmiddle
-2100
kNm
Moment Total
3411
kNm
Mtot
3375
kNm
10.1.6 - Reaction forces validation
In this section there will be checked whether the loading on the structure coincides with the
reaction forces exerted by the interface on the structure. In figure 61 and figure 62 the reaction
forces of the bedding is give. The response of the bedding for each load case is given in table 75.
In which the total of these forces in the Y-direction should be equal to the total loading in the Ydirection, given in table 76.
Figure 61: Reaction forces of the subsoil, Max. 0.969E5 Min. 0.206E6
As there can be seen in the figure above, also tensile forces are present in the subsoil. This is not
possible, since the sobsoil cannot bear tensile forces. This figure was only obtained to check the
vertical forces balance, whether the forces on the structure are equal to the forces of the subsoil on
the structure. The interface was replaced by 4 supports below the floor element (also see 11.1.3).
So also normal design loads values were present for the floor element.
Kubilay Bekarlar - Master Thesis
- 67 -
August – 2016
Figure 62: Magnitude of the reaction forces over the width of the subsoil
Table 75: Response of the bedding for each load case
Loadset
Total response in X - direction
Total response in Y - direction
LC 1
0
-0.7543E+07 N
LC 2
0
-0.1055E+08 N
LC 3
0
0.1675E+08 N
LC 4
0.2827E+07 N
0
LC 5
-0.2827E+07 N
0
Resultant
0
-0.1343+07 N
The resultant of the reaction force exerted by the bedding on the structure should be equal to the
resultant of the loading on the bedding. This will be checked by summing up the loadings in the Y direction.
Table 76: Hand calculation of the resultant force in the Y - direction
Loadset
Loading Y-direction
Width loading
Total loading in Y - direction
LC 1
-7,543E+06 N
-
-0,7543E+07 N
LC 2
-172000 N
61,35 m
-0,106E+08 N
LC 3
273000 N
61,36 m
0,168E+08 N
LC 4
0
0
LC 5
0
0
Resultant
-0,1344E+07 N
As there can be seen in table 75 and table 76, the total of reaction forces equals the total of
loading on the structure.
Kubilay Bekarlar - Master Thesis
- 68 -
August – 2016
12
ANALYSIS RESULTS FROM THE SIMPLIFIED LINEAR
ELASTIC ANALYSIS
12.1
Axial force distribution - All load cases (Lcc)
In the next stage the axial forces in the elements are determined. This is the axial force as a result
of all load cases (Lcc). There can be observed from figure 63 below that the axial force for the roof
element is -1,35E6 N.
Figure 63: Normal force distribution of the roof element
For the floor element the axial force is determined as well. The value of this the axial force is 1,45E6 N, see figure 64. As there can be seen, this value is larger than the axial force in the roof
element. This is due to the varying distributed load over the depth of the tunnel.
Figure 64: Normal force distribution of the floor element
Now there will be checked whether the total axial forces in the roof and floor element equals the
force acting on the outer wall.
(
)
Kubilay Bekarlar - Master Thesis
- 69 -
August – 2016
There can be seen that the results from Diana coincides with hand calculation. The axial force for
the wall element is about -2,7E6 N, see figure 65 below.
Figure 65: Normal force distribution of the wall element
12.2
Shear force distribution - Lcc
First the shear forces gathered from the FEA model are checked whether the shear force capacity is
exceeded or not. This is done for the roof, floor and wall elements. The shear force distribution
over the roof element is given in figure 66 below. During the base case design stage the shear
force capacity of 4659 kN/m1 was determined. From the results of the FEA model there can be
concluded that the shear force capacity is not exceeded.
Figure 66: Shear force roof element
Kubilay Bekarlar - Master Thesis
- 70 -
August – 2016
The same steps are also performed for the floor element. In figure 67 below the shear force
distribution for the floor element is presented. The shear force capacity calculated for the floor
element is 5581 kN/m1. There can be seen that also the shear force in the floor element does not
exceed the shear capacity.
Figure 67: Shear force in the floor element
In figure 68 below the shear force acting on the outer wall is given. The shear force capacity
determined for the outer wall is 2594 kN/m1. From this figure there can be seen that the capacity
is not exceeded.
Figure 68: Shear force in the wall element
12.3
Moment distribution Lcc
Also the moment distribution over the tunnel elements are also checked whether the moment
determined with the FEA model does not exceed the moment capacity. First the moment
development in the roof element is determined, see figure 69. The value of the moment in the roof
element is compared with the moment capacity of the roof element. As determined in the base
case design stage the moment capacity in the inclination and mid span, these values are
respectively 17197 kNm/m1 and 12667 kNm/m1. There can be concluded that the moment capacity
is not exceeded.
Kubilay Bekarlar - Master Thesis
- 71 -
August – 2016
Figure 69: Moment distribution of the roof element
The same check is done for the floor element. In figure 70 below the moment distribution for the
floor element is given. Previously determined value for the moment capacity of the floor element is
20209 kNm/m1 and 12086 kNm/m1 respectively for the inclination and mid span. With these results
there can again be concluded that the moment capacity is not exceeded.
Figure 70: Moment distribution of the floor element
The moment development is the outer walls is given in figure 71. The value for the moment
capacity of the outer wall is 9537 kNm/m1 and 11670 kNm/m1, respectively for the inclination and
mid span.
Figure 71: Moment distribution of the wall element
12.4
Primary stress distribution Lcc
In figure 72 below the primary stress distribution is given for the model with an interface element
which represents the bedding. There can be seen that the stresses in the floor element are low
compared with the roof element. This again has to do with the fact that the loads on the floor are
directly diverted to the supports. Since the floor elements are connected with interface elements.
Kubilay Bekarlar - Master Thesis
- 72 -
August – 2016
Figure 72: primary stress distribution in the global x – direction over the structure as a result of the total
loading
In order to solve this problem the tunnel is schematized without using an interface element, but
rather straight forward with three supports constrained in Y – direction and one in X- and Ydirection. The resulting stress distribution is illustrated in figure 73 below. There can be seen that
the largest positive stresses are there where the roof elements and the walls meet. The largest
negative stresses on the other side are at the mid span of the roof element. For the floor element
there can be seen that the largest positive stresses are at the center of the floor element. The
largest negative stresses on the other hand are at the parts of the floor close to the connection
with the walls.
Figure 73: Primary stress distribution in the global x – direction over the structure as a result of Lcc constraint
on top (without an interface element)
12.5
Principal stress distribution
The principal stress is the maximum and minimum value of the normal stress at a specific point on
a structural element. At the orientation in which the principal stresses occur the shear stresses are
zero. The principal stresses are used because it gives a more realistic display of the stress
distribution and direction. This is why Diana is asked to calculate the principal stresses from the
primary stresses. In figure 74, the principal stresses for the tunnel cross section is given.
Figure 74: Principal stress distribution in the global x – direction over the structure as a result of Lcc constraint
on top (without an interface element)
12.6
Analysis of moment and shear capacity (fully connected
composite)
For the analysis of the SCS sandwich element there can be assumed that the steel plates and
concrete either act independent, fully connected or partially connected. For this analysis the steel
and concrete parts are assumed to be fully connected. In other words the connection will be
infinitely stiff. This means that these elements will not slip relative to each other. As a result the
Kubilay Bekarlar - Master Thesis
- 73 -
August – 2016
strain diagram over the cross section of the element will be linear. The stress distribution over the
cross section of a composite material is not linear. Since the modulus of elasticity of steel and
concrete are different. This explains the big jumps in the stress distribution over the cross section.
A part of the stress distribution curve is zero, this is concrete tensile region. The stress is zero
because the concrete is assumed to be cracked and does not contribute to the tensile strength of
the structure. The strain and stress distribution diagram over the cross section is given in figure 75
below.
Figure 75: Strain and stress distribution over the cross section of the SCS sandwich element
In the next step the moment capacity of each element will be compared with the new design
moments. The new unity check will be compared with the unity check of the base case design. The
moment capacity and the unity check are given in table 77 and table 78.
Table 77: Earlier determined moment capacity
Bending capacity
Roof
Floor
Walls
outside
inside
outside
inside
outside
inside
Nsc, rd [kN]
12102
16943
9682
16943
9682
12102
Nst, rd [kN]
16943
12102
16943
9682
12102
9682
Ncu,rd[kN]
4841
-4841
7261
-7261
2420
-2420
x [mm]
308
308
369
369
291
291
Mpl,rd/m [kNm/m]
17197
12667
20209
12086
11670
9537
Table 78: Moment capacity of the base case
Bending capacity
Roof
Floor
Walls
outside
inside
outside
inside
outside
inside
Med [kNm/m]
15247,4
10607,5
16247,4
11607,5
8029,1
0
Mpl,rd/m [kNm/m]
17197
12667
20209
12086
11670
9537
Unity Check
0,887
0,837
0,804
0,961
0,688
0
If the results in table 78 above are compared with the earlier calculated unity checks in table 79,
there can be seen that the unity check decreases.
Table 79: Moment capacity due to simplified linear elastic analysis
Roof
Floor
Wall
Out
In
Out
In
Out
In
M design [kNm]
14000
10000
15000
11000
9800
0
M capacity [kNm]
17197
12667
20209
12086
11670
9537
Kubilay Bekarlar - Master Thesis
- 74 -
August – 2016
Unity check
0,81
0,79
0,74
0,91
0,84
0
There can be concluded that the design moments of each element and for each section of the
element, is smaller than the moment capacity of the element. In table 80 below the same steps are
taken for the shear force capacity.
Table 80: Shear capacity check
Roof
Floor
Wall
V design [kN]
3300
3400
1500
V capacity [kN]
4659
5581
2594
Unity check
0,71
0,61
0,58
From these results there can be concluded that also the shear capacity of the elements are not
exceeded.
13
LINEAR ELASTIC ANALYSIS DETAILED MODEL
13.1
Schematization of detailed SCS sandwich tunnel model
In this part there will be explained how the detailed model will be schematized. For the simple
model the SCS sandwich element was schematized as a line element with a representative modulus
of elasticity and a height of the element. In that case the cross section acts as one material instead
of three layers of two different materials.
However with this detailed model the SCS sandwich tunnel element will be modelled as it is
designed in reality. This means that the steel parts for the inner side and outer side of the roof,
floor and wall element have a specified thickness. The same holds for the diaphragms that connect
the inner and outer steel plates. In figure 76, below the different elements of the tunnel are given.
Figure 76: Tunnel cross section with different elements, with each their distinct dimensions (thicknesses).
Next the Diana elements used and their configuration will be discussed in detail. The steel inner,
outer and the diaphragm parts will be modelled by using the plain strain element CL9PE. This is a
three node plain strain element. This shell element is chosen for the steel since it has a small
height compared with its length, just like the steel plates applied. Another point is that the plain
strain elements plain strain elements also have an infinite length in the axial direction. These
elements give a good stress and strain distribution from where the internal forces can be calculated
by integrating over the height. The three node pain strain element is illustrated in figure 77 below.
Kubilay Bekarlar - Master Thesis
- 75 -
August – 2016
Figure 77: Three node plain strain element CL9PE
The concrete inner core of a SCS sandwich cell is modelled with the CQ16E element, which is an
eight node plain strain element. This element is square shaped and can be applied for all kind of
analysis including linear, nonlinear and cracking. Also this element has a length which is infinitely
long in its axial direction. This element is illustrated in figure 78.
Figure 78: Eight node plain strain element CQ16E
The stiffeners and studs which connect the steel and concrete should also be modelled. However
they won’t be modelled physically, rather by making use of interface elements. For these interface
elements a certain stiffness will be entered. The stiffness resembles the degree of connection
between these two elements. In this case a high k value will be entered for the connection of the
steel and concrete, because steel and concrete are initially assumed to be fully connected. In figure
79 below the applied interface element CL12I is schematized.
Figure 79: Interface element CL12I
As illustrated in figure 80 below, the steel plates are on all four sides of the concrete element
CQ16E. Since the steel and concrete elements cannot be connected directly, four interface
elements are applied on each side of the concrete square. This is the layout as it will be modelled
in Diana. The dots in figure 80 are not the modelled points but the nodes of each element. These
cell elements are repeated with different dimensions for the roof, floor and wall elements.
Kubilay Bekarlar - Master Thesis
- 76 -
August – 2016
Figure 80: Layout of two SCS sandwich cells
13.2
Input IDIANA – Detailed linear elastic analysis
13.2.1
Geometry
In this section there will be explained how the detailed model is constructed. First there will be
started by entering the geometry of the tunnel cross section. Below in table 81 and table 82 the
geometry entered in the model is tabulated.
Table 81: Dimensions tunnel to be modelled
Dimensions
Width of one tunnel tube
27000 [mm]
Total width of the tunnel
63100 [mm]
Total height of the tunnel
11400 [mm]
Inner height of the tunnel
7900 [mm]
Table 82: Dimensions tunnel to be modelled
Roof
Floor
Wall
h [mm] – Total height of the element
1600
1900
1500
b [mm] – Unit width of the element
1500
1500
1500
ctc web [mm] – Center to center distance of diaphragm (web)
1500
1500
1500
The tunnel geometry as it is modelled is given in figure 81. As there can be seen the entire cross
section is modelled in detail, where all connections are physically modelled except for the stiffeners
and studs, as stated before for this interface is used.
Kubilay Bekarlar - Master Thesis
- 77 -
August – 2016
Figure 81: Tunnel geometry
13.2.2
Boundary constraints
The tunnel cross section is supported at four points below the floor element at places where the
walls are connected with the floor. In the simplified model first interface elements where used,
however there was seen that for the floor element the interface resulted in a reduced moment. It
would mean that the floor element would be under dimensioned. That is why there is chosen for a
point supports. The location of the supports is given in figure 82.
Figure 82: Boundary constraints detailed model
13.2.3
Meshing
Picking a proper mesh is important for the model. Proper in the sense that the mesh division is
large enough to give an accurate result and that the mesh division is not too large to increase the
calculation time without much contribution to improve the results. Taking this into consideration,
the steel plates and concrete core are subdivided into 10. This also means that the interfaces
between these elements have to be divided into 10. As for the vertical division of the interface
element Diana provides a default value of 1 division. In figure 83 the divisions of a single SCS
sandwich cell is illustrated.
Figure 83: Meshing division of the lines
After the geometry is divided the meshing is generated for the cross section, figure 84 below.
Kubilay Bekarlar - Master Thesis
- 78 -
August – 2016
Figure 84: Mesh of the SCS cross section
13.2.4
Loads
Permanent loads
The loading on the tunnel cross section is the same as for the simplified model. Here also selfweight, soil and hydraulic loading has been taken into consideration. In figure 85 the loads on the
tunnel are illustrated.
Figure 85: Loading on the tunnel cross section
13.2.5
Variable loading
Sea level rise
The sea level rise acts as a variable loading on the tunnel structure. For the Arabian Gulf which is
the region that was chosen for the base case design the sea level rise in the Arabian Gulf is 2,27
mm/year (A. Alothman and M. E. Ayhan 1). A service life time for the tunnel of 100 – 120 years,
this corresponds with 27 cm. This is a rather low value, which will not have a significant impact on
the overall distribution of internal forces. In other words the variable lading due to the sea level
rise will be neglected.
Traffic load
The Load due to road traffic is determined according to Eurocode 1NEN-En 1991. In figure 86
below the layout of the traffic load on the structure is given. There will be investigated whether the
design moment due to traffic loading is still smaller than the moment capacity. From the
configuration of the variable traffic load is that this loading will reduce the value of the design load,
because it works in the opposite direction of the governing permanent loading. That is why this
1
Sea level rise within the west of Arabian Gulf using tide gauge and continuous GPS measurements: A.
Kubilay Bekarlar - Master Thesis
- 79 -
August – 2016
load will not be governing for the design, as well as for the optimization of the tunnel.
Figure 86: Design load due to traffic according to Eurocode 1
This loading from the Eurocode is schematized in Diana as illustrated in figure 87 below.
Figure 87: Distributed traffic load (upper), point loads due to traffic (lower)
For the moment distribution obtained due to traffic loading, a reduction of the bending moment
distribution can be observed. This because the loading on the tunnel cross section works
favourable, that is why this loading is not taken into consideration for further design.
13.2.6
Accidental loading
Sunken ship load
In a very extreme case a ship can sink upon a tunnel element. This will result in an additional
loading on the structure. The optimized structure should still be able to resist this loading upon the
already present permanent loading. However the situation of the base case, no big ships enter the
bay, only small private yachts which has a limited impact on the overall moment and shear force
distribution.
Kubilay Bekarlar - Master Thesis
- 80 -
August – 2016
Explosion and fire in one tunnel section
Another accidental loading is the explosion of an object with one of the tunnel sections. This very
short loading should be resisted by the structure as well. The loading due to an explosion is
approximated by a distributed load of 100 kN/m2. In figure 88 the schematization of the load due
to explosion is given. The permanent load acts in the opposite direction compared with the load
due to explosion, this will only reduce the governing design moment. That is why this accidental
load will not taken into account for the design optimization. With an explosion, it will also be likely
that a fire will break out. To prevent the fire from reaching the steel plate of a SCS tunnel a fire
protective layer is placed on the steel plate. However loading due to an explosion and/or fire inside
a SCS tunnel should be research thoroughly (see recommendations 22.2).
Figure 88: Distributed load due to explosion in one part of the tunnel cross section
13.3
Material and physical properties
As stated before the connection between the steel and the concrete is achieved by interface
elements. The degree of connection is determined by the stiffness constants entered in Diana.
There is assumed that the stiffness of the connection is very large, this because the steel and
concrete elements are initially assumed to be fully connected. That is why a very large stiffness
value is entered into Diana. A value of 3e+13 N/m3 is entered for the linear and tangential stiffness
of the interfaces, see table 83 for the material properties.
Table 83: Material properties
Elasticity / Linear stiffness
Concrete
3,4e+10 [N/m ]
Steel
2,1e+11[N/m ]
Interface
Passion ratio
2
Tangential stiffness
0,2
2
0,3
3
3
3,0e+13 [N/m ]
3,0e+13 [N/m ]
The physical properties are also defined in this section, where the values below table 84 are
entered in Diana.
Table 84: Thickness steel plates applied
Roof
Floor
Wall
to [mm] – Thickness steel plate outside
35
35
25
ti [mm] – Thickness steel plate inside
25
20
20
hc [mm] – Height of concrete
1540
1845
1455
tweb [mm] – Thickness of the diaphragm (web)
20
20
10
Kubilay Bekarlar - Master Thesis
- 81 -
August – 2016
13.4
Composed elements
As stated before the cross section consists of three layers. If the analysis of the model would be
run now, the moments and force distribution of each element would be calculated individually. In
order to get the forces and moments over the total structure, the stresses of the individual
elements need to be integrated. There is a tool in Diana that composes the three layers as one and
calculates the total moment over the cross section. This is the composed element CL3CM, figure
89. There are a few things that need to be adjusted to the geometry. A line in the center of the
roof, floor and wall element should be made. The composed element CL3CM properties will be
assigned to this line. Here after a thickness will be assigned to this line such that all three layers of
the roof, floor and wall fall within this range. Composed element in the tunnel cross section is given
in figure 90.
Figure 89: Composed element CL3CM
Figure 90: Position of the composed element (blue) in the cross section
14
LINEAR ELASTIC ANALYSIS OF DETAILED MODEL
14.1
Comparison of the simplified and detailed model (fully connected
SCS)
In this section the results of the detailed Diana model will be compared with the results obtained
with the hand calculation and simplified Diana model. This is done to verify the model. In case
there is difference in value, there will be explained why that is the case. As there can be seen in
the title, the detailed SCS sandwich model is schematized as fully connected elements. This is done
by increasing the linear and tangential stiffness of the connection between the steel and concrete
to a high value. By doing so, the simplified and the detailed model can be compared better since
the simplified model was also constructed with the assumption of fully connected elements.
14.1.1
Load case 1 – self weight of the structure
The results obtained from Diana for the moment and the deflection of the roof element for load
case 1 are given in figure 91 below. There can be seen that there is a kink in the left part of the
moment line. This is the part within the wall and the nicely curved part is the moment development
in the span of the cross section.
Kubilay Bekarlar - Master Thesis
- 82 -
August – 2016
Figure 91: Left Moment distribution in the roof element, Right: Deflection of the roof element due to load case 1
Next step will be the comparison of the results obtained with the detailed Diana model with the
hand calculation and the simplified model. In table 85 below the deflections are tabulated for the
three cases mentioned. There can be seen from the results of the detailed model that the
deflection for load case 1, is close to values obtained by hand calculation and the simplified model.
Table 85: Deflection roof LC1
Deflection roof LC1
Hand calculation
Deflection
Diana simplified model
0,00427
4,27
m
Deflection
Diana detailed model
0,00675
mm
6,75
m
Deflection
0,0053
mm
5,30
m
mm
The results for moment distribution of the roof element for load case 1 are given in table 86 below.
There can be seen that the moment distribution for the hand calculation, simplified model and the
detailed model differ. The difference between the simplified and detailed model can be explained by
the fact that the simplified model takes the center to center (c.t.c) distance of the cross section,
where the detailed model takes the actual dimensions. The c.t.c. span of the simplified model is
28,4 m whereas the real span is 27,0 m. Since this value is squared for the calculation of the
moment, it has a noticeable impact on the overall moment distribution. The difference should be in
the range of
, which is around 11%. If the results are compared by taking this into
account the difference can be justified.
Table 86: Moment hand calculation and Diana model
Moment hand calculation and Diana model
Hand calculation
14.1.2
Diana simplified model
Diana detailed model
M1
3075
kNm
M1
1800
kNm
M1
1500
kNm
M2
3075
kNm
M2
3200
kNm
M2
2300
kNm
Moment mid
-1538
kNm
Moment mid
-2000
kNm
Moment mid
-1700
kNm
Moment tot
4613
kNm
Moment tot
4500
kNm
Moment tot
3600
kNm
Load case 2 – vertical loading on top of the structure
For load case 2 the same steps are repeated for the roof elements. The results for the deflection
and the moment distribution can be seen in figure 92. Again the kink is due to the connection of
the roof and wall.
Kubilay Bekarlar - Master Thesis
- 83 -
August – 2016
Figure 92: Left Moment distribution in the roof element Right: Deflection of the roof element due to load case 2
First the deflection of the hand calculation, simplified model and the detailed model are compared.
From the results presented in table 87 there can be concluded that the deflection obtained by the
detailed model is close to the deflection of the simplified model, as well as the hand calculation.
Table 87: Deflection roof LC2
Deflection roof LC2
Hand calculation
Deflection
Diana simplified model
0,0161
16,1
m
Deflection
Diana detailed model
0,0255
mm
25,5
m
Deflection
0,0250
mm
25,0
m
mm
The moment distribution for all three methods is tabulated in table 88. There can be seen that the
moments of the detailed model are little smaller than the moments gathered with the simplified
model. Again this can be explained by the fact that the simplified model uses the c.t.c distance,
while the detailed model uses the actual dimensions. The difference in approach accounts for a
moment difference of 11%. Taking this into account there can be concluded that the results of the
detailed model are correct.
Table 88: Moment hand calculation and Diana model
Moment hand calculation and Diana model
Hand calculation
14.1.3
Diana simplified model
Diana detailed model
M1
11561
kNm
M1
8000
kNm
M1
5800
kNm
M2
11561
kNm
M2
12000
kNm
M2
9800
kNm
Moment mid
-5780
kNm
Moment mid
-7500
kNm
Moment mid
-7500
kNm
Moment tot
17341
kNm
Moment tot
17500
kNm
Moment tot
15300
kNm
Load case 3 – Vertical hydraulic loading on the bottom of the structure
The results of the deflection and moment distribution for the floor element are given in figure 93.
Kubilay Bekarlar - Master Thesis
- 84 -
August – 2016
Figure 93 Left: Moment distribution in the floor element Right Deflection of the floor element due to load case 3
The results of the deflection in the floor element are given in table 89. There can be seen that the
deflection of the detailed model is close to the deflection of the simplified model and the hand
calculation.
Table 89:
Deflection floor LC3
Deflection floor LC3
Hand calculation
Diana simplified model
Deflection
0,0166
16,6
m
Deflection
Diana detailed model
0,027
mm
27,0
m
Deflection
0,0245
mm
24,5
m
mm
Like in load case 1 and 2, the moment distribution of the detailed model for load case 3 is also
smaller. This is also due to the c.t.c. approach of the simplified model.
Table 90: Moment hand calculation and Diana model
Moment hand calculation and Diana model
Hand calculation
14.1.4
Diana simplified model
Diana detailed model
M1
18349
kNm
M1
-10000
kNm
M1
-5500
kNm
M2
18349
kNm
M2
-18000
kNm
M2
-17300
kNm
Moment mid
-9175
kNm
Moment mid
13000
kNm
Moment mid
13200
kNm
Moment tot
27524
kNm
Moment tot
27000
kNm
Moment tot
24600
kNm
Load case 4 – Loading on the left side of the tunnel element
In figure 94 below the moment distribution and deflection are shown for the left side wall for load
case 4.
Kubilay Bekarlar - Master Thesis
- 85 -
August – 2016
Figure 94: Left: Moment distribution in the wall element Right: Deflection of the wall element due to load case 4
From the results in table 91, there can be seen that the deflection of the side wall is 6,0 mm. This
value is considerably larger than the deflection calculated with the hand calculation as well as the
simplified model.
Table 91: Deflection wall LC4
Deflection wall LC4
Hand calculation
Deflection
Diana simplified model
0,000476
0,476
m
Diana detailed model
Deflection
mm
<<
m
<<
mm
Deflection
0,006
6,0
m
mm
The moment distribution also has a different shape. The total moment that should be active over
the height of the wall is there, but the moments at the intersection are different.
Table 92: Moment hand calculation and Diana model
Moment hand calculation and Diana model
Hand calculation
14.1.5
Diana simplified model
Diana detailed model
M1
2274
kNm
M1
2750
kNm
M1
0
kNm
M2
2274
kNm
M2
-200
kNm
M2
0
kNm
Moment mid
-1137
kNm
Moment mid
-2100
kNm
Moment mid
2900
kNm
Moment tot
3411
kNm
Moment tot
3375
kNm
Moment tot
2900
kNm
Load case 5 – Loading on the right side of the tunnel element
The results for load case 5 are presented in figure 95.
Figure 95: Left: Moment distribution in the wall element Right: Deflection of the wall element due to load case 5
Kubilay Bekarlar - Master Thesis
- 86 -
August – 2016
Just as in load case 4, also here the deflection is larger than the deflection of the hand calculation
and the simplified model. Results of the deflections for this load case are given in table 93. The
moment distribution is given in table 94. The total moment is close to the hand calculation and the
simplified model.
Table 93: Deflection wall LC5
Deflection wall LC5
Hand calculation
Diana simplified model
Deflection
0,000476
0,476
m
Deflection
mm
Diana detailed model
<<
m
<<
mm
Deflection
0,004
m
4,0
mm
Table 94: Moment hand calculation and Diana model
Moment hand calculation and Diana model
Hand calculation
Diana simplified model
Diana detailed model
M1
2274
kNm
M1
2750
kNm
M1
1100
kNm
M2
2274
kNm
M2
-200
kNm
M2
0
kNm
Moment mid
-1137
kNm
Moment mid
-2100
kNm
Moment mid
-2300
kNm
Moment tot
3411
kNm
Moment tot
3375
kNm
Moment tot
2850
kNm
14.2
Axial, moment, shear force distribution and deflection
14.2.1
Axial force distribution – All load cases (Lcc)
Now the axial force distribution in the roof, floor and wall elements are investigated as a result of
all load cases, figure 96.
Figure 96: Axial force distribution in the tunnel
First the axial force in the roof element will be checked. The axial force in the roof has a value of
1600 kN, see figure 97.
Kubilay Bekarlar - Master Thesis
- 87 -
August – 2016
Figure 97: Axial force in the roof element – Lcc
The axial force in the floor element has a value of 1900 kN, see figure 98.
Figure 98: Axial force in the floor element – Lcc
The axial force in the wall element is around 3400 kN. This can be seen in figure 99.
Figure 99: Axial force in the wall element – Lcc
14.2.2
Moment distribution Lcc
For the next step the bending moment distribution is obtained as a result of all load cases. The
shape of the total moment combination is presented in figure 100.
Kubilay Bekarlar - Master Thesis
- 88 -
August – 2016
Figure 100: Bending moment distribution as a result of all load cases - Lcc
The total bending moment distribution above is illustrated in more detail in the figures below. First
the total bending moment in the roof element is discussed. There can be seen in figure 101 that
the maximum bending moment in the roof element is at the intersection with the inner wall. The
moment here has a value of 12 000 kNm. On the left hand side a kink is observed, this is the
moment development at the intersection of the roof and the wall.
Figure 101: Bending moment distribution roof - Lcc
For the floor element the bending moment development is shown in figure 102. The governing
moment is again at the intersection of the floor and the inner wall. At this spot the maximum
moment has a value of 13 000 kNm.
Figure 102: Bending moment distribution floor - Lcc
The moment distribution in the wall is given in figure 103. There can be seen that the maximum
bending moment in the wall is 10 000 kNm.
Kubilay Bekarlar - Master Thesis
- 89 -
August – 2016
Figure 103: Bending moment distribution wall - Lcc
14.2.3
Shear force distribution Lcc
In figure 104 below the total shear force distribution over the cross section of the tunnel is given.
Figure 104: Shear force distribution due to all load cases - Lcc
The shear force distribution in the roof element is given in figure 105. There can be seen that the
maximum shear force occurring in the roof element is 3100 kN.
Figure 105: Shear force distribution in the roof element - Lcc
The shear force distribution the floor element is presented in figure 106, which has a maximum
value of 3400 kN.
Kubilay Bekarlar - Master Thesis
- 90 -
August – 2016
Figure 106: Shear force distribution in the floor element - Lcc
In figure 107 below the shear force distribution in the wall element is presented. The shear force in
the wall element has a maximum value of 1200 kN.
Figure 107: Shear force distribution in the wall element - Lcc
14.2.4
Deflection as a result of all load cases
The vertical deflection as a result of all load cases is illustrated in figure 108. As there can be seen
the deflection is presented on a larger scale in order to make the deflection more visible. The
maximum deflection of the roof element is about 32 mm, whereas the deflection of the floor
element is 25 mm. Also the horizontal deflection of the wall elements is presented in figure 109,
there can be seen that the maximum horizontal deflection is about 7 mm.
Figure 108: Vertical deflection due to all load cases, Max 0,251E-1 Min -0,317E-1 (extreme scale)
Kubilay Bekarlar - Master Thesis
- 91 -
August – 2016
Figure 109: Horizontal deflection due to all load cases, Max 0,2E-2 Min -0,693E-2 (extreme scale)
14.3
Analysis of the stress distribution
14.3.1
Analysis of stress in concrete core
The stress distribution for the concrete inner core is given in figure 110 below. There has to be
emphasized that this is the stress distribution for the case when the SCS sandwich elements are
fully connected. In other words, the connection between steel and concrete has a high value for its
stiffness. To account for the high stiffness a value of 3,0 e+13 N/m3 was entered in Diana. This
resulted in the stress distribution over the cross section given below.
First the concrete tensile stresses will be checked. In the previous calculations there was assumed
that the concrete parts exposed to tensile forces were already cracked and no tensile force was
acting in the concrete. There can be checked whether this approach is justified. In figure 110 the
tensile forces in the concrete is given from orange all the way to red. The maximum tensile stress
occurring in concrete is about 12 N/mm2. However the design value of the concrete tensile stress is
1,35 N/mm2. It means indeed that the concrete tensile part is cracked and will not be able to resist
tensile forces anymore.
For the concrete compressive stresses are given from the colour range of green till blue. The
maximum compressive stress occurring in the cross section is nearly 22 N/mm 2. In the initial
design the characteristic concrete compressive stress is 30 N/mm2. The design value of the
concrete compressive force is 20 N/mm2. From the results presented in the figures below there can
be concluded due to the governing loading cracks might occur in the concrete compression zone.
Again there should be emphasized that this is true with the precondition that the steel and concrete
are fully connected.
Figure 110: Stress distribution in the concrete core, horizontal elements
In figure 111, the stress distribution over the vertical elements is given. More or less the same can
be said for the wall elements. The concrete parts in tensile will be cracked anyway, so they will not
resist the tensile forces. As for the compressive stresses, some cracks might occur in the concrete
compressive zone. A concrete with a higher compressive strength will resolve this problem.
Kubilay Bekarlar - Master Thesis
- 92 -
August – 2016
Figure 111: Stress distribution in the concrete core, vertical elements
14.3.2
Analysis of stress in steel
The stress distribution over the steel plates is given in figure 112 and figure 113 below. Again the
tensile and compressive stresses are respectively given with orange/red and green/blue. There can
be seen that the maximum tensile stress in steel is 124 N/mm2 and the maximum compressive
stress is 143 N/mm2. Both stresses are smaller than the design yield stress of the steel applied,
which is 323 N/mm2. There can be concluded that at no place of the cross section the yielding
stress of the steel will be exceeded.
Figure 112: Stress distribution in steel plates, horizontal elements
Figure 113: Stress distribution in steel plates, vertical elements
14.3.3
Analysis of moment and shear capacity of a detailed fully connected composite element
Also for the force distribution of the detailed model the moment and shear capacity will be checked.
Since a large value for the stiffness of the connection is applied, this model can be assumed as fully
connected. In other words the connection will be very stiff. This means that the slip between the
concrete and steel plates will be small. As a result the strain diagram over the cross section of the
element will be linear. The stress distribution over the cross section of a composite material is not
linear, due to the difference in the E modulus. Concrete in tensile is assumed to be cracked and
does not contribute to the tensile strength of the structure. The strain and stress distribution
diagram over the cross section is given in figure 114 below.
Kubilay Bekarlar - Master Thesis
- 93 -
August – 2016
Figure 114: Strain and stress distribution over the cross section of the SCS sandwich element
Also for the detailed model the moment and shear capacity check will be done. The force
distribution over the cross section is given in figure 115.
Figure 115: Force distribution over the cross section of the SCS sandwich element
Now the detailed design moments are compared with the moment capacity of each element. The
results are presented in table 95.
Table 95: Detailed model
Roof
Floor
Wall
Out
In
Out
In
Out
In
M design [kNm]
12000
9500
13000
11000
9800
0
M capacity [kNm]
17197
12667
20209
12086
11670
9537
Unity check
0,69
0,75
0,64
0,91
0,84
0
Table 96: Simplified model
Roof
Floor
Wall
Out
In
Out
In
Out
In
M design [kNm]
14000
10000
15000
11000
9800
0
M capacity [kNm]
17197
12667
20209
12086
11670
9537
Unity check
0,81
0,79
0,74
0,91
0,84
0
There can be concluded that the design moments of each element and for each section of the
element, is smaller than the moment capacity of the element. In table 96 below the results of the
moment capacity check are presented for the simplified model. There can be seen that with the
detailed FEM model the unity check for the roof element is reduced from around 80% to around
Kubilay Bekarlar - Master Thesis
- 94 -
August – 2016
72%. For the floor element the reduction of the unity check reduced from 83% to 77%. For the
wall element the unity check has remained the same.
The new unity check for the shear capacity, as a result of the detailed FEM analysis is given in table
97 below.
Table 97: Detailed model
Roof
Floor
Wall
V design [kN]
3100
3400
1200
V capacity [kN]
4659
5581
2594
Unity check
0,67
0,61
0,46
Roof
Floor
Wall
V design [kN]
3300
3400
1500
V capacity [kN]
4659
5581
2594
Unity check
0,71
0,61
0,58
Table 98: Simplified model
From these results there can be concluded that also the shear capacity of the elements are not
exceeded. Comparing the unity checks for the shear force capacity of the detailed model with the
simplified model (see table 98), there can be seen that the unity check for the detailed model is
slightly smaller for the detailed model. The unity check for the roof element has gone from 71% to
67%, for the floor element it remained the same, where for the wall element the unity check
reduced from 58% to 46%.
15
PARTIALLY CONNECTED SCS SANDWICH MODEL
In this section the model results will be analysed in case the stiffness between the elements is not
infinitely large, but close to a value that is representative to a stud connection. Therefor first the
linear and tangential stiffness of a stud connection has to be determined.
15.1
Determination of the linear and tangential stiffness of the
interfaces
As there was emphasized in the preliminary study of this research project, the ultimate strength of
SCS composite sandwich elements depends on the strength and ductility of the shear connection.
When the load-slip diagram of a stud is studied in more detail there can be noted that up to 0,5
Fmax, the stud behaves linear elastic. If the loading is increased further nonlinear slip will be
observed. This is the horizontal plateau shape in the load-slip diagram given in figure 116 and
eventually the stud fails at 95% of the ultimate force. In order to evaluate the performance of the
composite elements, determining the true shear stiffness is important. Two different approaches
have been used to determine the shear stiffness of the stud connection. One is the method used by
Gelfi, Giuriani and the other by D.J. Oehlers, M.A. Bradford.
Kubilay Bekarlar - Master Thesis
- 95 -
August – 2016
Figure 116: Force slip diagram, International Journal of Composite Materials (2012)
15.1.1
Approach 1 - Gelfi and Giuriani (1987)
The analysis has been performed for designs with different stiffness values for the connection
between the steel and concrete. There was observed that the stiffness value had impact on the
overall force and moment distribution of the cross section. So in order to model a SCS sandwich
connection as realistic as possible the stiffness of the connection need to be investigated in more
detail. A stud embedded in concrete can be observed in figure 117.
Figure 117: Stud connected to a steel plate embedded in concrete
In order to determine the shear stiffness of a SCS connection, the behaviour of the studs needs to
be studied in more detail. In the initial loading phase the stud resists the loading and retains its
shape, see figure 118 on the left side. When the loading increases further the stud cannot retain its
shape anymore and deforms, denoted with s of slip figure 118 right side. This slip value is needed
in order to determine the shear stiffness of the connection.
Figure 118: Deformation of a stud
Kubilay Bekarlar - Master Thesis
- 96 -
August – 2016
The shear acts as a distributed load over the height of the stud. In order to determine the slip of
the stud, the distributed shear force is schematized as a point load acting on the head of the stud.
As the force acts on the stud, the concrete which surround the stud prevents the stud from bending
to one side. In other words the concrete acts as a distributed spring that resists the bending of the
stud, see figure 119.
Figure 119: Schematization of a stud as a spring system
The slip can be determined as follows. First the moment of inertia of the stud element needs to be
determined. With the moment of inertia and modulus of elasticity of the stud and the stiffness of
concrete, the value
α can be determined. First the stiffness of concrete should be determined. Gelfi
and Giuriani (1987) proposed a relationship between the modulus of elasticity of concrete and the
stiffness.
In which:
β is a function of stud diameter and stud spacing, approximated with
Next step is the determination of the moment of inertia of a stud. The diameter of the studs
applied is 35 mm and the height is 100 mm.
Now everything is known in order to determine
√
α. This can be calculated as follows:
√
In which the Es is the modulus of elasticity of the steel studs 2,1 * 10 5 N/mm2.
Here after the angle of slip as a result of a concentrated load can be determined. With the angle of
slip the total slip can be determined by multiplying the angle with the height of the studs.
Kubilay Bekarlar - Master Thesis
- 97 -
August – 2016
In which h is the height of the stud, 100 mm.
Finally the shear stiffness of the stud connection can be calculated.
With the shear stiffness determined in more detail, a better understanding of the structural
behaviour can be obtained.
15.1.2
Approach 2 - D.J. Oehlers, M.A. Bradford (1995)
D.J. Oehlers, M.A. Bradford have drafted a formula with which the shear stiffness of the studs can
be calculated. This formula is given below.
(
)
In which:
K is the shear stiffness of the stud connection
Fmax is the ultimate load that a stud can bear
d is the stud diameter mm
α is a constant value that ranges from 0,08 – 0,16 – 0,24
fc is the compressive yield stress of concrete
(
)
There can be seen that the shear stiffness of the studs differ a factor 3. The value that will be
chosen for the stiffness of the connection should be within this range.
15.2
Detailed analysis of the stress distribution in concrete core
Previously the distribution of the internal forces was obtained for the case where the SCS sandwich
elements are fully connected. This way a better comparison could be made between the detailed
and simplified model, since in both the elements were assumed to be fully connected.
However for an even better approximation of the distribution of the internal forces, the shear
stiffness of the studs should be applied. This value was determined in the previous section by two
different approaches. With the newly determined stiffness the internal forces are determined again.
In this section the stress distribution for the governing load cases will be analysed. The shear
stiffness applied for a single cell of a SCS box is given in figure 120 below.
Figure 120: Configuration of the applied stiffness for a single SCS cell
Kubilay Bekarlar - Master Thesis
- 98 -
August – 2016
Stress distribution over the concrete core layer is given in figure 121 below. In this figure three
critical spots can be identified for the roof and floor element. On the left hand side the connection
with the outer wall, in the middle of the span and at the connection with the inner wall. These
spots are critical since there are higher stresses at these locations than the rest of the cross
section. In the section below these spots will be discussed in more detail.
Figure 121: Stress distribution over concrete cross section
15.2.1
Stress and strain distribution in the roof
Connection roof and outer wall
Stress distribution at the point of the connection with the outer wall and the roof is given in figure
122. As there can be seen two stress concentration spots can be identified. In which the
orange/red is the tensile stress and green/blue the compressive stress. A closer look is first taken
at the upper tensile spot. Since the concrete tensile strength is low, tensile cracks will appear in the
concrete tensile section. As there can be recalled from the previous sections, this was also taken
into account for the capacity calculations in which the concrete tensile force was neglected. From
the perspective of durability there can be stated that the cracks in the tensile section are not a
problem since the concrete is in a confined space enclosed by steel. Intrusion of water or minerals
in concrete will not take place. In figure 122 also the strain distribution can be observed. Also for
the tensile zone there can be concluded that the tensile strain of concrete is exceeded. On the
other side the compressive stresses locally exceed the design compressive stress of concrete,
which is fcd 20 N/mm2. As a result of this local concrete plasticity and crushing of concrete might
occur in the lower part of the concrete. From the strain distribution of the cross section there can
be seen that indeed the highest strains are at the intersection of the roof with the wall. As a result
of the tensile and compressive cracks in concrete the slip between the steel and concrete
connection will increase, this will eventually lead to a reduction of the shear stiffness of the
connection.
Kubilay Bekarlar - Master Thesis
- 99 -
August – 2016
Figure 122: Stress (left) and strain (right) distribution of roof – outer wall connection
Mid span roof
For the mid span of the roof element there can be seen that on the upper side there are high
compressive stresses and the lower side tensile stresses. Again the tensile stresses and strain at
the bottom of the concrete exceed the low value of the concrete tensile strength. This will result in
tensile cracks at the lower part of the concrete. These tensile cracks were also expected to occur.
At the upper part of the concrete core the compressive stress is high, however the compressive
design stress is not exceeded. The applied concrete class C30, with a characteristic compressive
stress value of 30 N/mm2 and a compressive design stress value of 20 N/mm2. In figure 123
below, at the upper side of the concrete there can be seen that the compressive stress reaches as
value of 17 N/mm2. Due to this no cracks / crushing will occur in the compressive zone as well. As
there can be seen in the strain distribution over the cross section, the highest compressive strain
happen at the top of the roof element and the highest tensile strain happened at the lower part.
Figure 123: Stress (upper) and strain (lower) distribution of roof mid span
Connection roof with the inner wall
The location where the roof element connects with the inner wall also stress concentration points
can be observed, see figure 124. The tensile stresses at the upper side of the concrete core show
that the concrete tensile strength is exceeded. In other words tensile cracks will appear at this part
of the concrete. On the other side high compressive stresses can be observed at the connection of
the roof with the inner wall. The compressive stresses here exceed the concrete design stress and
nearly reach the characteristic concrete compressive stress. There can be concluded that the
concrete in these cells will be in a plastic state and local crushing of concrete will occur in the
Kubilay Bekarlar - Master Thesis
- 100 -
August – 2016
compressive zone. This stress distribution is confirmed by the strain distribution over the cross
section at the intersection as well, see figure 98 (lower picture).
Figure 124: Stress (upper) and strain (lower) distribution of connection roof – inner wall
15.2.2
Stress distribution in the floor
Connection floor and outer wall
Stress and strain distribution of the connection between the floor and the outer wall is given in
figure 125. From the stress and strain distribution of the corner cells there can be seen that the
concrete will crack in the concrete tensile zone. At the upper side of the concrete core a high
compressive stress and strain zone can be identified. Here the design concrete compressive stress
is exceeded, which means that locally concrete plasticity and crushing of concrete will occur in the
concrete compressive zone.
Figure 125: Stress (left) and strain (right) distribution of floor – outer wall connection
Floor mid span
The stress and strain distribution at the mid span of the floor element is given in figure 126. As
Kubilay Bekarlar - Master Thesis
- 101 -
August – 2016
there can be seen the concrete tensile stress and strain exceeds the design value. As a result the
concrete is cracked in the tensile section. On the bottom side of the floor element an increasing
compressive stress and strain can be identified. This stress is high but it does not exceed the
design value of the concrete compressive stress. As a result no cracks / crushing will appear in the
concrete compressive zone.
Figure 126: Stress (upper) and strain (lower) distribution of floor mid span
Connection floor with the inner wall
figure 127 below the stress and strain distribution of the location where the floor is connected with
the inner wall is given. The tensile section given in orange/brown, shows that the concrete tensile
strength is exceeded here as well. It means that tensile cracks will occur at the lower part of the
concrete core. During the calculations of the cross section this was also assumed to happen, since
the concrete tensile strength is low. However what was not taken into account are the cracks that
will occur at the concrete compressive section. Since there are high stresses and strain in the
concrete compressive zone that will exceed the design value of the concrete compressive strength.
Kubilay Bekarlar - Master Thesis
- 102 -
August – 2016
Figure 127: Stress (upper) and strain (lower) distribution of connection floor – inner wall
15.2.3
Stress distribution in the walls
The vertical stress and strain distribution in the walls will be analysed in this part. First the outer
wall will be investigated, see figure 128 (left). There can be seen that tensile stresses and strain
are present at the outer side and the compressive stresses in the inner side. From this figure there
can be seen that the concrete tensile stresses exceeds the concrete tensile strength, which denotes
that concrete in these parts are cracked. As for the part that is exposed to compressive stresses
there can be noted that the stress approaches the design value and at some places exceeds it. This
is the case in the top and bottom cells of the outer wall. As a result concrete will be in the plastic
state and crushing might occur, only locally. For the inner walls there can be stated that the stress
in these elements are smaller. Some cracks will occur due to exceedance of the concrete tensile
stresses, but the design concrete compressive stresses will not be exceeded. This can be observed
in figure 128 (right) below.
Figure 128: Stress (left) and strain (right) distribution of the outer and inner wall
Kubilay Bekarlar - Master Thesis
- 103 -
August – 2016
15.2.4
Stress distribution in steel parts
In this part the stress and strain distribution of the steel plates are discussed. There will be focused
on the positions of high stresses and strains and there will be checked whether the steel will yield
due to exceedance of its tensile /compressive strength. The stress and strain distribution of the
steel is given respectively in figure 129 and figure 130 below. As expected, the high tensile and
compressive zones are at the same positions as discussed in the section of concrete stresses and
strain.
From the distribution of the tensile stresses and strain in the steel there can be concluded that at
no position in the steel structure the elastic tensile / compressive stresses and strain will be
exceeded. Since the maximum tensile and compressive stresses respectively are 124 N/mm2 and
143 N/mm2. This is below the applied design yield strength of steel 322,7 N/mm2.
Figure 129: Stress distribution of the steel
Figure 130: Strain distribution of the steel
15.3
Principal vector stress analysis of concrete core
The principal stresses are the components of the stress tensor when the basis is changed in such a
way that the shear stress components become zero. Yielding occurs when the largest principal
stress exceeds the yield strength. The principal stress analysis is in particularly useful for brittle
material, like the concrete core.
With the principal stress analysis a more accurate analysis of the concrete inner core has been
made. The described distribution of the earlier stress analysis does coincide with the principal
stress analysis, but this time with more detail and accuracy. For the roof – inner wall connection
there can be seen that the tensile principal stresses at the upper side of the concrete core show
that the concrete tensile strength is exceeded, figure 131. In other words tensile cracks will appear
at this part of the concrete. On the other side also locally high compressive principal stresses can
be observed. From the results of this analysis there was obtained that the highest compressive
Kubilay Bekarlar - Master Thesis
- 104 -
August – 2016
stress is 29 N/mm2. This means that cracks will go to the plastic state and local crushing of
concrete will occur, at the position illustrated in dark blue below. There can also be observed that
the vectors are oblique due to the high shear forces at the connection with the inner walls.
Figure 131: Roof – inner wall connection
For the roof element at mid span there can be seen that vectors are horizontal due to the low shear
forces, see figure 132. At the lower side of the mid span the concrete tensile strength is exceeded,
which will cause cracks in the concrete. At the upper side of the roof element the concrete
compressive stress is not exceeded. This indeed coincides also with the earlier stress analysis.
Figure 132: Roof mid span
Again there can be observed that the principal stress vectors at the connection with the outer roof
are oblique due to the large shear forces. On the upper side of the connection with the outer wall
there can be seen that the tensile strength of the concrete is exceeded. This means that cracks will
occur in the concrete at this position figure 133. On the other hand there can be observed that
there are two positions of compressive stress concentration. The principal stresses here locally do
exceed the concrete compressive strength. This will result in local concrete plastic state and
crushing of the concrete.
Figure 133: Roof – outer wall connection
Kubilay Bekarlar - Master Thesis
- 105 -
August – 2016
For the floor – inner wall connection there can be seen that the principal stresses are oblique,
figure 134. In the lower part of this connection the concrete tensile strength is exceeded, which will
cause tensile cracks. For the upper part of this connection there can be observed that on three
positions the concrete compressive strength is exceeded. This will cause local concrete plasticity
and crushing of concrete.
Figure 134: Floor – inner wall connection
Again the principal stress vectors at the mid span are horizontal due to small shear forces, see
figure 135. As a result of exceedance of the tensile strength of concrete cracks will occur at the
upper side of this element at the mid span. While the compressive principal stresses don’t exceed
the design compressive strength of concrete. This means that no cracks will occur at the lower part
of this element.
Figure 135: Floor mid span
For the connection of the floor element with the outer wall there can be seen that the tensile
principal stress exceeds the concrete tensile strength so cracks will occur. While the concrete
compressive strength will only be locally exceeded, at one point. This position is denoted in dark
blue, see figure 136.
Figure 136: Floor – outer wall connection
Kubilay Bekarlar - Master Thesis
- 106 -
August – 2016
15.4
Conclusions of the stress analysis
As there was seen at some spots the design concrete compressive stress is exceeded and the
characteristic compressive stress value is approached. These spots can be seen in the cells where
the roof and floor elements are connected with the inner and outer walls. The cracks in the tensile
zone of the concrete are permissible because the concrete is in a confined space. As for the local
crushing and cracking in the compressive zone, they will be compressed by the compressive force
which will prevent the cracks from growing further. On the few places where the yielding strength
is exceeded the internal forces will be redistributed. The cracks however may have impact on the
degree of connection between the steel and concrete. Due to the cracks the shear stiffness of the
steel and concrete connection can decrease. This may have impact on the overall stiffness of the
structure. From the durability point of view these cracks have no impact on the durability of the
structure since the concrete is situated in a confined space. On the other side the exceedance of
the stress is only locally, which will result in a redistribution of forces.
16
ULTIMATE MOMENT CAPACITY INTERACTION AXIAL
FORCE – MOMENT
16.1
Interaction axial force and bending moment
The results of the detailed SCS model were first verified with the simplified model and the hand
calculation. From these results there can be concluded that the detailed model is correct. One of
the biggest advantages of such detailed model is that it gives a detailed insight in the distribution
of the internal forces. It means that the design forces are determined more accurately and the
uncertainties are less, which means that the structure can be designed more optimal.
High water and soil pressures acting on the structure result in large axial forces in the elements.
Taking these axial forces into consideration, new moment capacities can be determined that are
higher since large axial forces result in an increase of the concrete compressive force, consequently
also the moment capacity. In this section there will be checked whether the design can be
optimized after gathering detailed insight in the internal force distribution. In order to do so first
the additional moment capacity will be determined for each element due to the large axial loading.
For the elements where large axial forces and moments are present, an interaction diagram should
be made in order to determine the ultimate moment capacity for a certain axial force. This will be
done for the roof, floor and wall element.
16.1.1
Roof element – Outside part (inclination)
For the first element the steps for the interaction diagram will be discussed for each step. Since the
interaction diagram is an iterative process there is chosen for a four point M – N interaction
diagram which will give the required insight in the development of the moment capacity.
Point A
For this point the bending moment is zero and the roof is exposed to pure axial loading.
(
(
))
(
)
Point B
The axial loading for this point is zero, where the roof is exposed to pure bending moment, see
figure 137.
Kubilay Bekarlar - Master Thesis
- 107 -
August – 2016
Figure 137: Forces working on a cross section for pure bending moment
Point C
Compared with point B, for the determination of point C the neutral axis is mirrored relative to the
central axis of the cross section. The extra compressive stresses in the concrete don’t contribute to
the moment since those are symmetric around the central axis. This means that the Mrd,C = Mrd, B.
However the extra compressive force adds to the axial force, see figure 138.
(
)
Figure 138: Forces working on a cross section with bending moment and axial loading
Point D
For point D the neutral axis coincides with the central line of the cross section. The stresses in the
steel plates do contribute to the normal force due to the difference in thickness, they could be left
out of the equation if they were equally thick, see figure 139. On the other hand all stresses
contribute to the internal moment.
Figure 139: Forces working on the cross section when the neutral axis coincides with the central line
Kubilay Bekarlar - Master Thesis
- 108 -
August – 2016
This way the values (4 points) for the interaction diagram of the roof element has been obtained.
Now the diagram can be plotted, see figure 140.
Figure 140: Interaction diagram N – M for the roof element at the inclination
New moment capacity with the axial force acting on the element: 17196,7 + 326,6 = 17523,3 kNm
The steps above are repeated for each element for the inclination and the mid span, values and
diagrams can be observed below.
16.1.2
Roof element – Mid span
Table 99: Roof element per meter width - Mid span
Roof element per meter width - Mid span
Point A
Point B
Point C
Point D
Mrd
0
kNm
Mrd
12667
kNm
Mrd
12667
kNm
Mrd
21122
kNm
Nrd
50164
kN
Nrd
0
kN
Nrd
25340
kN
Nrd
12173
kN
x
308
mm
x - new
1292
mm
Figure 141: Interaction diagram N – M for the roof element at mid span
Kubilay Bekarlar - Master Thesis
- 109 -
August – 2016
New moment capacity with the axial force acting on the element: 12667 + 1076,5 = 13743,7 kNm
16.1.3
Floor element – Outside part (inclination)
Table 100: Floor element per meter width - Mid span
Floor element per meter width - Mid span
Point A
Point B
Point C
Point D
Mrd
0
kNm
Mrd
20209
kNm
Mrd
20209
kNm
Mrd
25110
kNm
Nrd
54650
kN
Nrd
0
kN
Nrd
29920
kN
Nrd
23290
kN
x
369
mm
x - new
1531
mm
Figure 142: Interaction diagram N – M for the floor element at inclination
New moment capacity: 20209 + 400 = 20609 kNm
16.1.4
Floor element – Mid span
Table 101: Floor element per meter width - Mid span
Floor element per meter width - Mid span
Point A
Point B
Point C
Point D
Mrd
0
kNm
Mrd
12086
kNm
Mrd
12086
kNm
Mrd
25110
kNm
Nrd
54650
kN
Nrd
0
kN
Nrd
30220
kN
Nrd
13609
kN
x
369
mm
x - new
1531
mm
Kubilay Bekarlar - Master Thesis
- 110 -
August – 2016
Figure 143: Interaction diagram N – M for the floor element at mid span
New moment capacity: 12086 + 1682 = 13768 kNm
16.1.5
Wall element - Outside part (inclination)
Table 102: Floor element per meter width - Mid span
Floor element per meter width - Mid span
Point A
Point B
Point C
Point D
Mrd
0
kNm
Mrd
11669
kNm
Mrd
11669
kNm
Mrd
16019
kNm
Nrd
43622
kN
Nrd
0
kN
Nrd
23680
kN
Nrd
16164
kN
x
291
mm
x - new
1209
mm
Figure 144: Interaction diagram N – M for the wall element at inclination
New moment capacity: 11669 + 915 = 12584 kNm
Kubilay Bekarlar - Master Thesis
- 111 -
August – 2016
16.1.6
Wall element – Mid span
Table 103: Floor element per meter width - Mid span
Floor element per meter width - Mid span
Point A
Point B
Point C
Point D
Mrd
0
kNm
Mrd
9537
kNm
Mrd
9537
kNm
Mrd
16019
kNm
Nrd
43622
kN
Nrd
0
kN
Nrd
23780
kN
Nrd
12937
kN
x
291
mm
x - new
1209
mm
New moment capacity: 9537 + 1704 = 11241 kNm
Figure 145: Interaction diagram N – M for the wall element at mid span
17
OPTIMIZATION OF THE DESIGN USING DETAILED
LINEAR STRUCTURAL ANALYSIS
17.1
Optimization due to detailed analysis of the internal forces
In the previous section the new moment capacity is determined as a result of the interaction
between the bending moment and the axial force. There can be seen from the interaction diagrams
for each element that the moment capacity increases with an increasing axial force up to a certain
level. After exceeding this level the moment capacity decreases again, which can be observed as a
kink in the interaction diagram. The new design moment for each element is given in table 104
below.
Table 104: Design moment, new moment capacity and unity check
Roof
Floor
Wall
Out
In
Out
In
Out
In
N [kN]
1550
1550
1900
1900
3400
3400
M design [kNm]
12000
9500
13000
11000
10000
7500
M new capacity [kNm]
17523
13744
20609
13768
12584
11241
Unity check
0,68
0,69
0,63
0,79
0,79
0,67
Kubilay Bekarlar - Master Thesis
- 112 -
August – 2016
In this table above there can be seen that with the detailed model and interaction between
moment and axial loading, the moment capacity check is reduced. The values for the unity checks
are around 70%, this means that the tunnel has a considerable rest capacity. This is why there will
be checked whether the design can be more optimized for the moment capacity. The results in
table 105 give the new determined steel thicknesses, the overall height of the element and the
corresponding moment capacity.
Table 105: New determined steel thickness
Roof
Floor
Wall
Out
In
Out
In
Out
In
tsc new [mm]
20
25
20
25
20
20
tst new [mm]
25
20
25
20
20
20
h new [mm]
1600
1600
1900
1900
1500
1500
Nsc [kN]
6455
8068
6455
8068
6455
6455
Nst [kN]
8068
6455
8068
6455
6455
6455
N [kN]
1550
1550
1900
1900
3400
3400
Ncu [kN]
1614
1614
1614
1614
0
0
x [mm]
311
311
371
371
292
292
M cap new [kNm]
12916
10996
15530
13218
10794
10794
As there can be seen the results give a reduction of the steel used. This resulted in a higher value
of the unity check which now is around 0,85 - 0,9, see table 106. Which is a more optimal value for
the unity check, than the previously determined value around 0,7, see table 104. In other words by
getting to know the distribution of the internal forces more accurately the SCS tunnel structure can
be designed more optimal.
Table 106: Unity check of the moment capacity for the new steel thicknesses
Roof
Floor
Wall
Out
In
Out
In
Out
In
N [kN]
1550
1550
1900
1900
3400
3400
M design [kNm]
12000
9500
13000
11000
10000
7500
M capacity [kNm]
12916
10996
15530
13218
10794
10794
Unity check
0,93
0,86
0,84
0,83
0,93
0,69
This is the optimization step taken for the moment capacity check. The same can be done for the
shear capacity. This will be governing for the concrete core and the steel diaphragms that connect
the steel plates with each other. In table 107 below the new shear capacity per meter width of the
cross section for each element is given.
Kubilay Bekarlar - Master Thesis
- 113 -
August – 2016
Table 107: Calculations of the shear capacity for the new steel dimensions
Dimensions
Roof
Floor
Walls
outside
inside
outside
inside
outside
inside
h [mm]
1600
1600
1900
1900
1500
1500
b [mm]
1500
1500
1500
1500
1500
1500
hc [mm]
1455
1455
1655
1655
1460
1460
tweb [mm]
15
15
15
15
10
10
ctc web [mm]
1500
1500
1500
1500
1500
1500
τrd,c,min [N/mm ]
0,54
0,54
0,54
0,54
0,54
0,54
Vrd,c [kN]
1180
1180
1342
1342
1184
1184
hs,web [mm]
1455
1455
1655
1655
1460
1460
Av,s [mm ]
21825
21825
24825
24825
14600
14600
Vrd,s [kN]
4067
4067
4626
4626
2720
2720
Vrd,c+s [kN]
5247
5247
5968
5968
3904
3904
Vrd new [kN/m1]
3498
3498
3979
3979
2603
2603
2
2
If the new shear capacities of the elements are compared with the previously determined shear
capacities there can be concluded that the new shear capacities are smaller. Since the thickness of
the diaphragm denoted as tweb in table 107 above has been reduced. The thickness of the
diaphragms in the roof and floor was 20 mm, has become 15 mm. Design shear force has been
determined in detail with the detailed analysis, which leaves the shear capacity check to be
performed. The results can be observed in table 108.
Table 108: Unity check of the shear capacity
Roof
Floor
Wall
Out
In
Out
In
Out
In
V design [kN]
3100
3100
3400
3400
1200
1200
Vrd new [kN/m1]
3498
3498
3979
3979
2603
2603
Unity check
0,89
0,89
0,85
0,85
0,46
0,46
The unity check for the shear force previously was around a value of 0,6. This means that the
structure had a rest capacity which is considerable high. In other words the design was not
optimized. After the internal forces are known in detail with the help of the detailed linear analysis,
the optimization step could be made. As there can be seen in table 108, the unity check has now
gone up to 0,85 – 0,90. This is a more optimal value for a design.
Since the tunnel cross section has now been optimized for the moment and shear capacity checks,
now the total quantity of steel can be determined per meter in the axial direction of the tunnel.
These optimized values may not look significant at the first sight however they will be significant
since these values are only done for one meter in the axial direction of the tunnel. Considering that
immersed tunnel projects range from several hundred meters to several kilometres, it means that
this type of optimization will be highly important.
In table 109 below on the left side, the amount of steel applied for the tunnel designed by making
use of framework program Matrixframe and hand calculations, denoted as old. On the right side the
new determined dimensions of the steel plates are given by making use of a detailed FEM analysis.
Kubilay Bekarlar - Master Thesis
- 114 -
August – 2016
There can be concluded that the total amount of steel applied for the design using the detail
analysis is reduced significantly. Where in the previous design the applied steel in the cross section
was 11,96 m2, has now reduced to 9,45 m2. This is a reduction of the steel applied with 21 %. In
absolute values, this is a reduction of 2,51 m3 per meter in the axial direction. The optimization
which leads to reduction of the steel applied with 21% is a significant improvement, since the steel
is an expensive material and is one of the major expenses of a SCS tunnel project because it is
applied on a large scale.
Table 109: Steel area in the old situation (left) and new situation (right)
Steel Area
Old
New
2
2
t [mm]
l [mm]
A[mm ]
t [mm]
l [mm]
A[mm ]
Outer side floor
35
63050
2206750
25
63050
1576250
Inner side floor
20
57250
1145000
20
57250
1145000
Outer side roof
35
63050
2206750
25
63050
1576250
Inner side roof
25
57250
1431250
20
57250
1145000
Outer side outer wall
25
11400
570000
20
11400
456000
Inner side inner wall
20
7900
316000
20
7900
316000
Outer side inner wall
20
7900
316000
20
7900
316000
Inner side inner wall
20
7900
316000
20
7900
316000
Web plate - ctc 1500
20
3450100
15
Total steel area
2604750
2
11957850
[mm ]
11,96
[m ]
2
2
9451250
[mm ]
9,45
[m ]
2
The amount of concrete applied in a SCS immersed tunnel is not further optimized because that
amount is needed for the immersion and floating balance. In other words, if the amount of
concrete in the SCS structure is reduced, than it has to be applied as ballast concrete in the cross
section. Another reason is that the thickness of the concrete has impact on the moment capacity
since the internal level arm of the forces in the steel become larger which correspondents with a
higher moment capacity. This is the reason why no further optimization of the amount of concrete
will take place.
In the preliminary study of this research project there was made clear that there should be a
balance between immersion and floating of the tunnel element. This means that with the new
dimensions of the steel plates, checks need to be performed whether the tunnel element still fulfils
the floating and immersion conditions. The results for the floating and immersion conditions are
given in table 110 below.
Table 110: Immersion and floating balance calculations
Immersion calculation
Old
3
New
3
3
3
Total areas
[m ]
[kN/m ]
[kN]
[factor]
[m ]
[kN/m ]
[kN]
[factor]
Concrete
257,9
23,2
5984
1
267,2
23,2
6198
1
Steel
11,95
77
643
1
9,45
77
508
1
Ballast
50,2
23,2
1165,1
1
50,2
23,2
1165,1
1
Earth
0
7,5
0
1
0
7,5
0
1
Hydrostatic load
718,8
10,35
7439,3
1
718,8
10,35
7439,3
1
Kubilay Bekarlar - Master Thesis
- 115 -
August – 2016
Check
1,06
>1
Check
1,06
>1
Floating calculation
3
3
3
3
Total areas
[m ]
[kN/m ]
[kN]
[factor]
[m ]
[kN/m ]
[kN]
[factor]
Concrete
257,9
23,5
6061
1
267,2
23,5
6277,9
1
Steel
11,95
77
920
1
9,45
77
727,7
1
Ballast
0
23,5
0
1
0
23,5
0
1
Hydrostatic load
711,5
10
7115
1
718,8
10
7187,7
1
Check
0,98
<1
Check
0,98
<1
From these results there can be concluded that the new SCS tunnel cross section fulfils the floating
and immersion conditions.
Kubilay Bekarlar - Master Thesis
- 116 -
August – 2016
Design and cost comparison of tunnel
variants
Kubilay Bekarlar - Master Thesis
- 117 -
August – 2016
18
TRANSVERSE PRESTRESSED (POST TENSIONED)
REINFORCED CONCRETE TUNNEL
18.1
Roof element
During the study of the base case design there was concluded that a large span of 27m is not
feasible for a reinforced concrete tunnel element for which the maximum reinforcement ratio is
applied. The limit for the maximum span is around 19 m. This has to do with the fact that the crack
width of concrete exceeds the maximum allowable crack width. In order to make a valid
comparison between a SCS sandwich tunnel and a reinforced concrete tunnel for a large span of
about 27m, there has to be investigated which measures have to be taken for the reinforced
concrete tunnel in order to make a span of 27m. The crack width can be reduced by increasing the
axial force in the roof and floor element. This can be realized by applying prestressed tendons in
the transverse direction of the tunnel. As it is known the longitudinal prestressed cables are cut
after the immersion of the tunnel element. But the transverse tendons will remain in place after
immersion. Aspects of attention are the protection of the prestressed tendons from the marine
environment. This because the loss of a tendon can have great impact on the prestressed members
since their ability to sustain load relies on the tensile strength on the tendons2. Also the friction of
the concrete with the tendon will be reduced due to the attack of the tendon. This is the reason
why the application of transverse prestressing of tunnel elements is not that common.
First the moment distribution of the statically indeterminate system will be determined for the
axial, prestress and variable loading. A computer program will be used to determine the moment
line distribution, see figure 146, figure 147 and figure 148.
Figure 146: Roof self-weight
2
Corrosion protection and steel concrete bond improvement of prestressing strand. M. Anderson, M. Oliva, M.
Tejedor. December 2012.
Kubilay Bekarlar - Master Thesis
- 118 -
August – 2016
Figure 147: Roof variable
Figure 148: Roof total
The tendon layout and force should be chosen such that the tensile strength of concrete should not
be exceeded at t = 0. On the other hand the prestressing force should be high enough to prevent
too high stresses tensile stresses in t = ∞. The layout of the tendon is given in figure 149 and table
111 below.
Figure 149: Layout of the prestressed tendon
Table 111: Dimensions of the roof and tendon
Dimensions roof and tendon
Height
1,6
m
Width
1,0
m
Ac
1,6
m
2
4
I
0,34
m
z
0,8
m
W
0,427
m
3
Kubilay Bekarlar - Master Thesis
L1 - length big span
28,4
m
f1 drape
0,615
m
R1 – radius 1
163,9
m
L2 – length short span
4,7
m
f2 - drape
0,07
m
R2 – radius 2
39,8
m
- 119 -
August – 2016
The radius of the tendon should have a minimum value of 15 – 20 m. From the tendon profile the
radius can be calculated as follows:
. In figure 150, the layout including the radius of the
tendon profile is give.
Figure 150: Prestressed tendon layout and the radius of the tendon profile
Now the distributed loading due to prestressed tendon can be calculated.
. The results
are given in table 112 below.
Table 112: Loading and the specifications concrete and tendon
Loading and specifications
qp1 – prestress loading big span
7,32
kN/m
fck
35
N/mm
2
qp2 – prestress loading small span
30,19
kN/m
fcd
23,33
N/mm
2
Self-weight
47,5
kN/m
Es
210000
N/mm
2
External loading long term
140
kN/m
Ec
34000
N/mm
2
Pm0 – initial prestress force
1200
kN
Ep
195000
N/mm
2
fct
1,44
N/mm
2
As
2880
mm
2
The moment line distribution due to the prestress loading of an initial prestress force Pm0 of 1200
kN is given in figure 151.
Figure 151: Roof prestress loading
Kubilay Bekarlar - Master Thesis
- 120 -
August – 2016
The next step is the determination of the minimum and maximum tensile forces for the roof
element. At t = 0 the prestressing force is at its maximum (no losses). The first calculation is done
for point A, which is at the mid span of the roof element. For the working prestressing force Pm∞,
there is assumed that Pm∞ = 0,85 Pm0, loss of 15%.
Point A
t=0
Bottom
Top
Point A
t=∞
Bottom
Top
Now the governing prestressing force can be determined from the results presented above. The
prestressing force should be in the range 17941 kN ≥ Pm0 ≤ 59516 kN. The results for position A
and B (where the roof connects with the inner wall) gathered with a spreadsheet program are
presented in table 113 and table 114.
Table 113: Results of the prestress calculation in point A
Roof - Point A
t=0 Self weight
t=0
Ma
2431
kNm
Bottom
Pm0
≥
3077
kN
Mb
3406
kNm
Top
Pm0
≤
59516
kN
t=0 Prestress
t=∞
Ma
378
kNm
Bottom
Pm0
≥
17941
kN
Mb
512
kNm
Top
Pm0
≤
168707
kN
t = ∞ Variable loading
Kubilay Bekarlar - Master Thesis
- 121 -
August – 2016
Ma
7167
kNm
Mb
10040
kNm
Table 114: Results of the prestress calculation in point B
Roof - Point B
t=0 Self weight
t=0
Ma
2431
kNm
Bottom
Pm0
≤
25128
kN
Mb
3406
kNm
Top
Pm0
≥
4026
kN
Ma
378
kNm
Bottom
Pm0
≤
101009
kN
Mb
512
kNm
Top
Pm0
≥
21273
kN
t=0 Prestress
t=∞
t = ∞Variable loading
Ma
7167
kNm
Mb
10040
kNm
For spot B the prestressing force should be in the range 21273kN ≥ Pm0 ≤ 25128 kN.
In the next stage the number of strands will be calculated. Since the prestressing force in point B is
governing, this load will be used for further design of the prestressed tendon. The minimum
prestressing force is known, which means that the required prestress tendon area can be
determined, table 115.
Table 115: Results of the required tendon area and the amount of strands to be applied
Steel type Y1860S7
fpk
1860
N/mm
2
Pm0
21773
kN
σ pm0
1395
N/mm
3
Ap
15607,89
mm
Characteristic diameter
15,2
mm
n strands in tendon
109,7
n
2 tendons
55 strands
Cross section of steel
139
mm
2
2
Figure 152: Position of the tendon in the concrete cross section
Kubilay Bekarlar - Master Thesis
- 122 -
August – 2016
From these calculations there can be observed that two tendons of 55 strands Y1860S7 has to be
applied. The 55 strand tendon anchor is illustrated in table 115.
Figure 153: Data and layout of a 55 strand tendon of Y1860S7
18.2
3
Floor element
The hydraulic loading of the floor element works in the opposite direction of the loading on the roof
element. If a curved tendon profile would be applied, than the large prestressed loading and the
loading due to self-weight will act in the same direction. This means that in the initial situation, t=0
both loads will cause tensile stresses in the concrete tensile zone. Since there is no opposing load
in the initial stage t=0, the concrete will eventually be cracked. This is the reason why an axial
tendon will be applied, rather than a curved tendon profile. There will be examined whether to
apply a centrically or an eccentrically prestressing tendon. The advantage of an eccentrically
prestressing tendon is that there is also a moment introduced, which works favourable.
For the floor element first the moment distribution due to self-weight and external hydraulic
loading will be determined. This is again needed for the determination of the maximum and
minimum prestress force value. The dimensions of the floor element are given in table 116.
Table 116: Dimensions of the roof and the loading
Dimensions roof and loading
Height
1,9
m
Self-weight
47,5
kN/m
Width
1,0
m
External loading long term
240
kN/m
Eccentricity - e
0,25
m
Ac
1,9
m
2
4
I
0,57
m
z
0,8
m
W
0,6
m
3
The moment line distribution of the floor due to dead load and hydraulic loading is given
respectively in figure 154 and figure 155 below.
3
Data and picture from Freyssinet Prestressing, April 2010
Kubilay Bekarlar - Master Thesis
- 123 -
August – 2016
Figure 154: Moment line distribution of the floor due to dead load
Figure 155: Moment distribution of the floor due to hydraulic loading
Now the boundaries of the applied prestressing force are determined. There are two governing
locations where the checks should be done. Position A at the mid span of the floor element and
position B at the intersection of the floor element with the inner wall. Checks will be done for t=0
and t=∞. For the working prestressing force Pm∞, there is assumed that Pm∞ = 0,85 Pm0, loss of
15%.
The check will be done for A and B simultaneously with a spread sheet program in order to
determine the force and eccentricity which results in the smallest prestressing force. This is an
iterative process. Again the tensile strength of concrete should not be exceeded.
Eccentricity, e = -0,06 m (below the neutral axis)
Pm0 = 41500 kN, the calculation of this prestress force is not presented here, rather in Appendix
(28.5).
Kubilay Bekarlar - Master Thesis
- 124 -
August – 2016
In figure 156 below a possible position of the tendon in the floor element is given.
Figure 156: Possible position of the tendon in the floor element
As stated before the tendon is placed slightly eccentrically (figure 157), which requires the smallest
prestressing force. Now the minimum required amount of prestressing steel can be calculated. For
the prestressing steel Y1860S7 with a σp0 of 1395 N/mm2 will be applied. The area prestressing
steel is calculated as follows:
Figure 157: Final position of the tendon
The number of strands that have to be applied for the cross section is determined as follows, table
117. The position of the tendon in the concrete cross section is given in figure 158.
Table 117: Results of the required tendon area and the amount of strands to be applied
Steel type Y1860S7
fpk
1860
N/mm
2
Pm0
41500
kN
3
Ap
29749
mm
n strands in tendon
214
N
4 tendons
55 strands
σ pm0
1395
N/mm
Characteristic diameter
15,2
mm
Cross section of steel
139
mm
Kubilay Bekarlar - Master Thesis
2
- 125 -
2
August – 2016
Figure 158: Position of the tendon in the concrete cross section
Figure 159: Curved and eccentrically prestressed tendon layout for the roof and floor element
Conclusion prestressed (post tensioned) immersed tunnel
From the new design of a concrete tunnel element there can be concluded that a span of 27 m is
not feasible with prestressed (post tensioned) roof and floor elements. In the initial reinforced
concrete tunnel design there was seen that the crack width was the limiting factor. By adding
prestressed tendons no cracks will occur. However the prestress tendons to be applied have a
dimension of 510 mm by 420 mm. This makes it impossible to fit several of 55 strands of Y1860S7
tendons per meter width of the cross section.
If those tendons were able to fit the cross section, there was seen that the moment and shear
force capacity is also smaller than the design moment and shear force in ULS. On the other side
there was seen from the analysis that large axial forces were present. In order to bear these large
axial forces, high strength concrete is required.
From this analysis there is seen that a transversely prestressed reinforced concrete tunnel is not a
feasible solution for a tunnel with a large span in the transverse direction.
Kubilay Bekarlar - Master Thesis
- 126 -
August – 2016
19
STEEL SHELL TUNNEL
19.1
Variant 1
In this section there will be investigated if a span of 27 m is feasible for a steel shell tunnel. If a
span of 27 m is not feasible with a normal steel shell tunnel, there should be investigated which
measures there need to be taken in order to fulfil the condition for a large span.
But first the steel shell tunnel element will be described in little more detail. As the name of the
steel shell tunnel says so, the tunnel consists of a steel shell on the outer side. This is also the first
part of the tunnel that will be constructed, see figure 160. After the steel shell has been
constructed the reinforced concrete inner section will be constructed. Some roof elements of a steel
shell tunnel are designed as a reinforced concrete part without a steel shell on the outer side.
However this would be no different for the length of the span from that of a reinforced concrete
tunnel element as was seen for the base case design.
Figure 160: Construction of the steel shell of a steel shell tunnel element.
In order to see the difference between the steel shell and a reinforced concrete tunnel element,
also the roof element is designed as a steel shell element. Doing so the boundary condition that the
concrete cover has to be 75 mm can be ignored, since the concrete is not exposed to marine
conditions. The reinforced concrete part is exposed to normal humid conditions.
In table 118 below the environmental class and material properties are given.
Table 118: Environmental class and the material properties
Environmental class
XC1 / XS2
fcd =
30,0
N/mm²
εc;3 =
1,75
‰
Concrete class
C35/45
fyd =
434,78
N/mm²
εu;3 =
3,5
‰
Reinforcement steel
B500B
Es =
200000
N/mm²
εud =
45
‰
wmax
19.1.1
0,3 mm
Floor element
First the floor element is designed. The dimensions of the floor element and the design forces in
ULS and SLS are given in table 119 below.
Table 119: Dimensions of the floor element and the loading on the floor element
Dimensions and loading
Width
1000
Kubilay Bekarlar - Master Thesis
mm
- 127 -
August – 2016
Height
ULS
SLS
1900
mm
Md
16620
kNm/m
Nd
-2040
kN/m
Vd
3078
kN/m
Nd,vd
-2040
kN/m
Mrep
12976
kNm/m
Nrep
-1774
kN/m
Tensile zone
As stated before, the steel shell tunnel has a steel shell on the outer side of the tunnel element and
reinforced concrete on the inner side. In table 120 the amount of reinforcement applied on the
inner side of the tunnel.
Table 120: Amount of steel applied on the inner side
Layer
1st layer
2nd layer
3rd layer
Amount
Diameter
10,00
Ø
10,00
Ø
10,00
Ø
Position
40 mm
distance layers
50 mm
distance layers
50 mm
40 mm
40 mm
Total
Area
1773,0 [mm]
12566
[mm²]
1683,0 [mm]
12566
[mm²]
1593,0 [mm]
12566
[mm²]
37699
[mm²]
1683,0 [mm]
Compressive zone
In table 121 the thickness of the steel plate and the total steel area per meter width is given.
Further in table 122 the amount of stirrups applied is given.
Table 121: Dimension of the steel plate
Thickness plate
Steel shell
Area
30
[mm]
30000
[mm²]
Table 122: Amount of stirrups applied
Stirrups
1st
Ø
16
mm -
150
mm
2
pcs
Asw;1
2,68
mm²/mm
Asw,tot
2,68
mm²/mm
Normal stress check
The first check is whether the normal stresses in the cross section does or does not exceed the
normal stress capacity of the cross section. From the result in table 123 there can be stated that
the maximum capacity of the cross section is not exceeded by the design force.
Kubilay Bekarlar - Master Thesis
- 128 -
August – 2016
Table 123: Normal stress check
Normal stresses
Calculation of stresses
σc;top
fcd
-28,7
N/mm²
-30
N/mm²
Unity check 0,96
Moment capacity check
Now the moment capacity check is performed. In table 124, the compression zone height in ULS is
given along the strains in the cross section. Furthermore the strain and force distribution in ULS
over the cross section can be seen in figure 161.
Table 124: Results of strains calculation
Calculation of strains
xu
237,41
e'c;u
mm
-3,5
‰
es1
22,63
‰
es2
21,31
‰
es3
19,98
‰
es4
-3,48
‰
Figure 161: Strain distribution and force distribution in ULS of the cross section
Since the forces in the cross section are known, now the moment capacity of the cross section can
be calculated. The results are given in table 125.
Table 125: Moment capacity calculation of the cross section and the unity check
Calculation of forces
Calculation of internal equilibrium
Effective depths
N'cd;1
-5341,94
kN
MN'cd;1
-493,22
kNm
Ns1
5463,63
kN
MNs1
9687,03
kNm
ds1
1773
mm
Ns2
5463,63
kN
MNs2
9195,30
kNm
ds2
1683
mm
Kubilay Bekarlar - Master Thesis
- 129 -
August – 2016
Ns3
5463,63
kN
MNs3
8703,57
kNm
ds3
1593
mm
Ns4
-13089
kN
MNs4
-13,08
kNm
ds4
1
mm
Nd
2040
kN
MNd
1938
kNm
ds5
22,25
mm
Total
0
kN
MRd
29017,61 kNm
Unity check 0,58
Shear capacity check
The shear capacity check for the situation with and without shear reinforcement is given in table
126 below.
Table 126: Results of the shear forces calculation in combination with normal forces
Shear forces in combination with normal forces
Acting forces
Bearing capacity cross section without stirrups
VEd
3078
kN
CRd,c
0,12
Nd,Vd
-2040
kN
k
1,34
ρl
0,02
Bearing capacity cross section with stirrups
k1
0,15
cot θ = 2,14
scp
1,074
N/mm²
VRd,c
1420
kN
Unity check
2,17
θ
25
°
a
90
°
VRd,s
3876
kN
VRd,max
7151
kN
Unity check
0,79
Crack width control
Finally the crack width control will be performed for the steel shell tunnel. The results of the
calculation can be seen in table 127.
Table 127: Results of the crack width calculation
Calculation of crack width
εsm - εcr
0,914751
‰
s1
100
mm
s1,max
555
mm
407,2538
mm
ae
5,555556
-
sr,max
ρp,eff
0,069491
-
k1
0,8
-
mm
k2
0,5
-
mm²
k3
3,4
-
0,425
-
heff
542,5
Ac,eff
542500
fct,eff
3,795447
N/mm²
k4
ξ1
1
-
φeq
40
kt
0,4
-
kx
1
wk
Kubilay Bekarlar - Master Thesis
0,372536
- 130 -
mm
mm
August – 2016
wmax
0,3
mm
Unity Check 1,24
From the calculations there can be seen that the steel shell tunnel element does not fulfil the
condition of crack width control. Several steps were taken in order to fulfil this condition. By
increasing the reinforcement ratio the crack width becomes smaller, doing so the maximum
reinforcement ratio is exceeded. The reinforcement needed is 3%, which is too high and not
permitted in order to prevent brittle failure.
Another aspect that influences the crack width is the diameter of the reinforcing steel. By
increasing their number and decreasing the diameter, there was tried to fulfil the crack width
condition. However there was seen that still the crack width condition was not met.
A concrete cover of 91 mm is applied, which is the 75 mm cover and the additional 16 mm of the
stirrup diameter. This is a boundary condition demanded by the client (reference project). If the
cover would be reduced to 60 mm the crack width control check would fulfil the precondition. The
steel plates for a steel shell are applied on the outer side of the floor and wall elements. As stated
before, the roof element which is normally executed as a reinforced concrete element will also be
designed with a steel plate on the outer side. This way the concrete side is only exposed to the
inner environment. This also means that the client would drop the demand of a 91 mm cover on
the reinforcing steel.
Table 128: Exposure class related to environmental conditions in accordance with EN 206-1 (table 4.1)
2 Corrosion induced by carbonation
XC1
Dry or permanently wet Concrete inside buildings with low air humidity. Concrete
permanently submerged in water
XC2
Wet, rarely dry
Concrete surfaces subject to long-term water contact.
Many foundations
XC3
Moderate humidity
Concrete inside buildings with moderate or high air
humidity. External concrete shelter from rain
XC4
Cyclic wet and dry
Concrete surfaces subject to water contact, not with exposure
class XC2
Table 129: Values of minimum cover Cmin, dur requirements with regard to durability for reinforcement steel in
accordance with EN 10080 (Table 4.4N)
Environmental requirement for Cmin,dur [mm]
Exposure class according to table 4.1
Structural
X0
XC1
XC2/XC3 XC4
class
S5
15
20
30
35
S6
20
25
35
40
XD1/XS1
XD2/XS2
XD3/XS3
40
45
45
50
50
55
Now the new concrete cover can be determined. The new thickness of the concrete cover is 35 mm +
16 mm = 51 mm this will be rounded up to 60 mm. Now the crack width check is performed again
and the result is given in table 130 below.
Kubilay Bekarlar - Master Thesis
- 131 -
August – 2016
Table 130: Results of crack width calculation
Calculation of crack width
εsm - εcr
0,930643
‰
s1
100
mm
ae
5,882353
-
s1,max
400
mm
ρp,eff
0,081073
-
sr,max
287,8747
mm
heff
465
mm
k1
0,8
-
Ac,eff
465000
mm²
k2
0,5
-
fct,eff
3,209962
N/mm²
k3
3,4
-
ξ1
1
-
k4
0,425
-
kt
0,4
-
φeq
40
mm
kx
1
-
wk
0,267909
mm
wmax
0,3
mm
Unity Check 0,89
Now the same calculation steps are performed for the roof element.
19.1.2
Roof element
The same steps as been performed above for the floor element are now performed for the roof
element.
Table 131: The dimensions and the forces acting on the roof element
Dimensions and forces
C50/60
B500B
Width
1000
mm
Height
1800
mm
Md
16342
kNm
Nd
-1295
kN
ULS
Vd
3027
kN
-1295
kN
Mrep
13316
kNm
Nrep
-1126
kN
Nd,vd
SLS
Table 132: Layout and amount of the reinforcement
Tensile zone

1st layer
12
Ø
40

2nd layer
9
Ø
mm
distance between layers: 50
40
mm
Kubilay Bekarlar - Master Thesis
- 132 -
ds;i
As;i
[mm]
[mm²]
1713
15079,64
1623
11309,73
mm
August – 2016
distance between layers: 50
3rd layer
10
Ø
32
mm
mm
Totals
1537
8042,477
1642,328
34431,86
Table 133: Thickness and area of the steel plate applied
Compressive zone
Thickness plate
Area
Steel shell
30
30000
[mm]
[mm²]
Table 134: Amount of stirrups applied
Stirrups
1st
Ø 16
mm -
150
mm
2
pcs
Asw;1 =
2,68
mm²/mm
Figure 162: Strain distribution and force distribution in ULS of the cross section
Table 135: Overview of the results of the unity checks
Unity Checks
MSd
16419,7
kNm
MRd
25580,52
kNm
VEd
3027
kN
VRd,c
1273
kN
VRd,s
3695
kN
VRd,max
6816
kN
wk
0,276031
mm
wmax
0,3
mm
σc;top
-30,9824
N/mm²
fcd
-33,3333
N/mm²
Kubilay Bekarlar - Master Thesis
xu
uc= 0,64
127,5484
mm
ε'bu
-3,5
‰
εs1
43,50569
‰
uc= 2,38 Stirrups required
uc= 0,82
Θ
25
°
Α
90
°
x
581,4342
mm
σs;1
250,9991
N/mm²
uc= 0,92
uc= 0,93
- 133 -
August – 2016
Now the floating and immersion check will be done, see Table 136 and Table 137.
Table 136: Results of the immersion calculation
Immersion calculation
Total areas
Concrete
Steel
Ballast
Earth
Hydrostatic load
3
[m ]
3
[kN/m ]
[kN]
[factor]
285,44
23,20
6622,09
1,00
6,01
77,00
462,47
1,00
61,02
23,20
1415,66
1,00
0,00
7,50
0,00
1,00
760,49
10,35
7871,02
1,00
[kN]
[factor]
height
1,13
Check
1,08
>1
Check
0,94
<1
Table 137: Results of the floating calculation
Floating calculation
Total areas
Concrete
3
[m ]
3
[kN/m ]
285,44
23,50
6707,72
1,00
Steel
6,01
77,00
462,47
1,00
Ballast
0,00
23,50
0,00
1,00
760,49
10,00
7604,85
1,00
Hydrostatic load
By increasing the height of the roof element the crack width condition is met. The new height of
the roof element is 1,8 m instead of 1,6 m. This however has impact on the immersion and floating
conditions. Due to this change the floating and immersion conditions are initially not met. Which
means that the cross sectional dimensions has to be adjusted. In order to fulfill the floating and
immersion conditions the amount of air in the tunnel cross section has to be increased. This also
means that the height of the tunnel will be increased. The inner height of the tunnel increased from
7,9 m to 8,4 m. Doing so the total height of the tunnel has become 12,1 m.
There can be seen that by adjusting the tunnel dimensions to the new conditions the floating and
immersion conditions are fulfilled again. However there should be taken into account that more
ballast has to be applied to fulfill the condition. The weight of ballast concrete/water that has to be
applied for the new condition is 1416 kN. This means that during the immersion process 142 m 3
ballast water has to be applied. It accounts to 71 m3 water in each side of the tunnel. This can be
realized by a ballast tank of 6 x 6 x 2 m. The designed steel shell tunnel element is illustrated in
figure 163 and figure 164.
Kubilay Bekarlar - Master Thesis
- 134 -
August – 2016
Figure 163: Drawing of the cross section of a steel shell tunnel element (half of the cross section until the
symmetry axis)
Figure 164: Detail of a steel shell tunnel, floor element
19.1.3
Amount of materials applied variant 1
Now the amount of materials applied for the steel shell tunnel will be quantified. First the length
over which the shear reinforcement has to be applied will be calculated. These results are given in
table 138 and figure 165 below.
Table 138: Length over which stirrups will be applied
Length of stirrup
Roof
Floor
Shear capacity without stirrups
1273
kN
Design shear force
3027
kN
Length over which stirrups needed
7,8
m
Shear capacity without stirrups
1420
kN
Design shear force
3078
kN
Length over which stirrups needed
7,3
m
Kubilay Bekarlar - Master Thesis
- 135 -
August – 2016
Figure 165: Illustration of the length over which stirrups will be applied
Since the length over which the stirrups are needed is known, now the amount of stirrups to be
applied can be calculated. The quantity and the specifications of the stirrups applied for each
element is given in table 139.
Table 139: Amount of stirrups applied
Amount of stirrups applied
Roof
Length over which stirrups needed
Ø 16 – 150
Floor
2 pcs
h roof
1800 mm
Volume per stirrup
1125936 mm
Amount of stirrups applied
208
Total stirrup area
0,234 m
Length over which stirrups needed
7,3 m
Ø 16 – 150
Walls
7,8 m
3
2 pcs
h floor
1900 mm
Volume per stirrup
1166159 mm
Amount of stirrups applied
208
Total stirrup area
0,233 m
Length over which stirrups needed
1,6 m
Ø 16 – 150
3
3
2 pcs
b wall
1500 mm
Volume per stirrup
1005309 mm
Kubilay Bekarlar - Master Thesis
3
- 136 -
3
August – 2016
Amount of stirrups applied
22
Total stirrup area
0,044 m
Total amount stirrup reinforcement /m
0,52 m
3
3
After the amount of stirrups is determined the amount of tensile reinforcement will be determined.
The amount and specifications of the tensile reinforcement is given in table 140 below.
Table 140: Amount of tensile reinforcement applied
Amount of tensile reinforcement applied
Floor
Tensile reinforcement
10 - Ø 40 x 3
Total area 37699 mm
2
Total reinforcement volume 2,04 m
Roof
3
Tensile reinforcement
12 - Ø 40
9 - Ø 40
10 - Ø 32
Total area 34432 mm
2
Total reinforcement volume 1,86 m
Walls
4 - Ø 32
Total area 3217 mm
3
2
Total reinforcement volume 0,35 m
3
3
Total amount tensile reinforcement /m
Total reinforcement volume 4,25 m /m
The amount of steel plate applied is given in table 141.
Table 141: Amount of steel plate applied
Amount of steel plate applied
Thickness
Volume
Roof
30 mm
1,89 m
3
Floor
30 mm
1,89 m
3
Walls
30 mm
0,48 m
3
3
Total amount of steel plate applied/m
4,25 m /m
The quantity of concrete applied to this tunnel is given in table 142.
Table 142: Amount of concrete applied
Amount of concrete applied
Thickness
Volume
Roof
1900 mm
119,7 m
3
Floor
1800 mm
113,4 m
3
Walls
1500 mm
45,82 m
3
Kubilay Bekarlar - Master Thesis
- 137 -
August – 2016
3
Total amount of concrete applied /m
278,92 m /m
The dimensions and the quantity of the stiffeners applied are given in table 143 below.
Table 143: Amount of steel stiffeners applied
Amount of steel stiffeners applied
h×l×t
Volume
Roof
100 × 60 × 30 mm
0,40 m
3
Floor
100 × 60 × 30 mm
0,40 m
3
Walls
100 × 60 × 30 mm
0,135 m
3
3
Total amount of steel stiffeners applied /m
0,935 m /m
Finally the amount of studs applied per meter is given in table 144.
Table 144: Amount of shear studs applied
Amount of shear
studs applied
Roof
Diameter
Height
Min. ctc
Max. ctc
Height stud
head
12 mm
Volume
1440 mm
Diameter
stud head
45 mm
30 mm
360 mm
45 mm
0,41 m
3
Floor
30 mm
360 mm
45 mm
1440 mm
45 mm
12 mm
0,41 m
3
Walls
32 mm
384 mm
48 mm
1536 mm
48 mm
12,8 mm
0,214 m
3
Total amount of shear studs applied /m
19.2
3
1,04 m /m
Variant 2
As there was seen in the previous variant of the steel shell tunnel with a maximum reinforcement
ratio of close to 2% the height of the roof element had to be adjusted. Which also meant that the
cross sectional dimensions of the tunnel element had to be adjusted. In order to fulfill the
immersion condition more ballast has to be added.
19.2.1
Roof element
Another option for the design of a steel shell tunnel is by applying a steel cover on the inner side,
this way the crack width is not the limiting factor anymore. Doing so the cross sectional dimensions
don’t have to be adjusted and the applied reinforcement can be reduced. In other words the
moment, shear or normal force capacity will be governing. In table 145 below the design loads for
the roof element is given.
Table 145: Dimension and design loads on the roof element
Dimensions and forces
C60/75
B500B
ULS
Width
1000
mm
Height
1600
mm
16342
kNm
Md
Kubilay Bekarlar - Master Thesis
- 138 -
August – 2016
SLS
Nd
-1295
kN
Vd
3027
kN
Nd,vd
-1295
kN
Mrep
13316
kNm
Nrep
-1126
kN
The amount of reinforcement, steel thickness and stirrups applied is given in table 146, table 147
and table 148 below.
Table 146: Amount and position of the tensile reinforcement
Tensile reinforcement
1st layer
11
Ø
32
mm
distance between layers:
2nd layer
10
Ø
32
10
Ø
32
mm
50
mm
mm
distance between layers:
3rd layer
50
mm
Totals
ds;i
As;i
[mm]
[mm²]
1517
8847
1427
8042,4
1345
8042,4
1437,6
24932
Table 147: Amount of steel shell applied
Compressive zone
Thickness plate
Area
Steel shell
30
30000
[mm]
[mm²]
Table 148: Amount of stirrups applied
Stirrups
1st
 16
mm -
95
mm
4
pcs
Asw;1 =
8,47
mm²/mm
Now the checks for the roof element can be performed and the results are given in table 149.
Table 149: Overview of the results of the unity checks
Unity Checks
MSd
16411,07
kNm
MRd
16585
kNm
uc= 0,99
VEd
3027
kN
Stirrups required
VRd,c
1289
kN
uc= 2,35
VRd,s
4775,912
kN
11800
kN
VRd,max
wk
wmax
0,47
mm
0,3
mm
Kubilay Bekarlar - Master Thesis
uc= 0,64
uc= 1,57
- 139 -
August – 2016
αc;top
-39,1109
N/mm²
-40
N/mm²
fcd
uc= 0,98
Steel plates are placed on the inner side, which makes the crack width check irrelevant. This way
the crack width control is not the limiting factor anymore, since the concrete is not exposed to
external environment. Where the reinforcement ratio of the previous case was close to 2,0% in the
roof element, this value has now been reduced to 1,55% and the thickness of the roof element still
remains 1,6 m. Eventually the final analysis will reveal which variant is more feasible from the
material / cost point of view.
19.2.2
Floor element
The same calculations will be performed for the floor element of the steel shell tunnel variant 2. In
table 150 the design loads for the floor element can be observed.
Table 150: Dimension and design loads of the floor element
Dimensions and forces
C45/55
B500B
ULS
SLS
Width
1000
mm
Height
1900
mm
Md
16620
kNm
Nd
-2040
kN
Vd
3077
kN
Nd,vd
-2040
kN
Mrep
12976
kNm
Nrep
-1774
kN
The amount of reinforcement, thickness steel plate and the stirrups is given in table 151, table 152
and table 153.
Table 151: Amount and position of the tensile reinforcement
Tensile reinforcement
1st layer
9
Ø
2nd layer
9
Ø
3rd layer
9
Ø
32
mm
32
mm
32
mm
distance between layers:
50
distance between layers:
50
ds;i
As;i
[mm]
[mm²]
1817
7238
1735
7238
1653
7238
1735
21715
mm
mm
Totals
Table 152: Amount of steel shell applied
Compressive zone
Thickness plate
Area
Steel shell
30
30000
Kubilay Bekarlar - Master Thesis
[mm]
- 140 -
[mm²]
August – 2016
Table 153: Amount of stirrups applied
Stirrups
1st
 16
mm -
95
mm
4
pcs
Asw;1 =
8,47
mm²/mm
Now the checks are performed for the floor element and the results can be observed in table 154.
Table 154: Overview of the results of the unity checks
Unity Checks
MSd
16749
kNm
MRd
18284
kNm
uc= 0,92
VEd
3077
kN
Stirrups required
VRd,c
1348
kN
uc= 2,28
VRd,s
5748
kN
11524
kN
VRd,max
wk
0,42
mm
wmax
0,30
mm
αc;top
-28,7
N/mm²
-30
N/mm²
fcd
uc= 0,54
uc= 1,41
uc= 0,96
From the results of the checks there can be seen that all checks fulfill the boundary condition
except the crack width check. Since this variant is a steel shell with steel plates covering the
concrete surface the crack width check is not the limiting aspect anymore. In other words the
concrete layer is not exposed to the environment anymore. This means that all relevant checks
fulfill the boundary conditions.
Figure 166: Drawing of the cross section of a steel shell tunnel element (half of the cross section until the
symmetry axis)
Kubilay Bekarlar - Master Thesis
- 141 -
August – 2016
Figure 167: Detail of a steel shell tunnel, floor element
19.2.3
Amount of materials applied variant 2
The amount of stirrups and its specifications are denoted for each element in the table 155.
Table 155: Amount of stirrups applied
Amount of stirrups applied
Roof
Length over which stirrups needed
Ø 16 – 150
Floor
2 pcs
Amount of stirrups applied
208
Total stirrup area
0,234 m
Length over which stirrups needed
7,3 m
Ø 16 – 150
Walls
7,8 m
2 pcs
Amount of stirrups applied
208
Total stirrup area
0,233 m
Length over which stirrups needed
1,6 m
Ø 16 – 150
3
3
2 pcs
Amount of stirrups applied
22
Total stirrup area
0,044 m
Total amount stirrup reinforcement /m
0,52 m
3
3
The amount of tensile reinforcement per element is given in table 156 below.
Table 156: Amount of tensile reinforcement applied
Amount of tensile reinforcement applied
Floor
Tensile reinforcement
9 - Ø 32 x 3
Total area 21715 mm
2
Total reinforcement volume 1,36 m
Roof
3
Tensile reinforcement
11 - Ø 32
10 - Ø 32
10 - Ø 32
Total area 34432 mm
2
Total reinforcement volume 1,57 m
Walls
4 - Ø 32
Kubilay Bekarlar - Master Thesis
Total area 3217 mm
- 142 -
3
2
August – 2016
Total reinforcement volume 0,35 m
3
3
Total amount tensile reinforcement /m
Total reinforcement volume 3,25 m /m
The amount of steel plate applied for variant 2 is given in table 157.
Table 157: Amount of steel plate applied
Amount of steel plate applied
Thickness
Volume
Roof
30 mm + 10 mm
2,52 m
3
Floor
30 mm + 10 mm
2,52 m
3
Walls
30 mm + 10 mm
0,48 m
3
3
Total amount of steel plate applied/m
5,52 m /m
The calculated amount of concrete to be applied in this tunnel is given in table 158.
Table 158: Amount of concrete applied
Amount of concrete applied
Thickness
Volume
Roof
1900 mm
119,7 m
3
Floor
1600 mm
100,8 m
3
Walls
1500 mm
45,82 m
3
3
Total amount of concrete applied /m
266,32 m /m
The dimensions of the stiffeners and the amount is given in table 159 below.
Table 159: Amount of steel stiffeners applied
Amount of steel stiffeners applied
h×l×t
Volume
Roof
100 × 60 × 30 mm and 100 × 60 × 15 mm
0,61 m
3
Floor
100 × 60 × 30 mm and 100 × 60 × 15 mm
0,61 m
3
Walls
100 × 60 × 30 mm and 100 × 60 × 15 mm
0,28 m
3
3
Total amount of steel stiffeners applied /m
1,50 m /m
Now the dimensions and the amount of studs are calculated. The results are given in table 160.
Table 160: Amount of shear studs applied
Amount of shear
studs applied
Roof – Inside
Diameter
Height
Min. ctc
Max. ctc
15 mm
180 mm
22,5mm
Roof - Outside
30 mm
360 mm
Floor – Inside
15 mm
Floor - Outside
30 mm
Kubilay Bekarlar - Master Thesis
Height stud
head
6 mm
Volume
720 mm
Diameter
stud head
22,5 mm
0,05 m
3
45 mm
1440 mm
45 mm
12 mm
0,41 m
3
180 mm
22,5mm
720 mm
22,5 mm
6 mm
0,05 m
3
360 mm
45 mm
1440 mm
45 mm
12 mm
0,41 m
3
- 143 -
August – 2016
Walls – Inside
15 mm
180 mm
22,5mm
720 mm
22,5 mm
6 mm
0,04 m
3
Walls - Outside
30 mm
360 mm
45 mm
1440 mm
45 mm
12 mm
0,14 m
3
3
Total amount of shear
studs applied /m
19.3
1,1 m /m
Critical span steel shell tunnel
Since there will be a comparison of the steel shell tunnel with the SCS sandwich tunnel, it is also
important to know what the critical span is for the steel shell tunnel. In the tables below the
calculation for the critical span for a steel shell tunnel is given. The unity checks for a span of 28 m
are given in table 161 and for 29 m
table 162.
Table 161: Unity checks of a steel shell tunnel for a span of 28 m
Unity Checks
MSd
18002
kNm
MRd
29568
kNm
uc= 0,61
VEd
3192
kN
Stirrups required
VRd,c
15574
kN
uc= 2,05
VRd,s
7712
kN
VRd,max
9454
kN
wk
0,28
mm
wmax
0,30
mm
αc;top
-28,7
N/mm²
-30
N/mm²
fcd
uc= 0,41
uc= 0,95
uc= 0,96
Table 162: Unity checks of a steel shell tunnel for a span of 29 m
Unity Checks
MSd
19302
kNm
MRd
29568
kNm
uc= 0,65
VEd
3306
kN
Stirrups required
VRd,c
1557
kN
uc= 2,12
VRd,s
7712
kN
VRd,max
9454
kN
wk
0,31
mm
wmax
0,30
mm
Kubilay Bekarlar - Master Thesis
uc= 0,43
uc= 1,03
- 144 -
August – 2016
αc;top
-32,94
N/mm²
fcd
-33,33
N/mm²
uc= 0,99
From these calculations there is seen that the critical span for a steel shell tunnel is 28 m. There
can be seen that the normal, shear and moment capacity is higher than the design forces applied
on the structure. However the crack width for a span of 29 meters becomes larger than the
permissible 0,30 mm. So now also for the inner environment the crack width is the limiting factor.
This evaluation is important because will be essential in the comparison of the types of tunnels for
a large span in the cross direction.
20
SCS SANDWICH
The SCS sandwich tunnel that was designed in the earlier stage of this research and analysed with
a FEM program, will now be expressed in the quantity of the materials used. Doing so the amount
of steel used for the plates of the SCS tunnel is given in table 163.
Table 163: Amount of steel plate applied
Amount of steel plate applied
Thickness
Volume of steel applied
Roof outside
25 mm
1,575 m
Roof inside
20 mm
1,26 m
Floor outside
25 mm
1,575 m
Floor inside
20 mm
1,26 m
3
Walls outside
20 mm
0,63 m
3
Walls inside
20 mm
0,63 m
3
Diaphragm
15 mm
2,69 m
3
Perpendicular diaphragm
15 mm
1,17 m
3
3
3
3
3
Total amount of steel plate applied/m
10,79 m /m
Hereafter the amount of self-compacting concrete is calculated, from which the results are given in
table 164.
Table 164: Amount of concrete applied
Amount of concrete applied
Thickness
Volume
Roof
1600 mm
100,8 m
3
Floor
1900 mm
119,7 m
3
Walls
1500 mm
45,82 m
3
3
Total amount of concrete applied /m
266,32 m /m
The amount and dimensions of the stiffeners is given in table 165 below.
Table 165: Amount of steel stiffeners applied
Amount of steel stiffeners applied
h×l×t
Volume
Roof – Outside
100 × 60 × 25 mm
0,34 m
3
Roof – Inside
100 × 60 × 20 mm
0,27 m
3
Kubilay Bekarlar - Master Thesis
- 145 -
August – 2016
Floor – Outside
100 × 60 × 25 mm
0,34 m
3
Floor – Inside
100 × 60 × 20 mm
0,27 m
3
Walls - Outside
100 × 60 × 20 mm
0,09 m
3
Walls - Inside
100 × 60 × 20 mm
0,19 m
3
3
Total amount of steel stiffeners applied /m
1,50 m /m
Finally the designed dimensions and quantity of the applied studs is given in table 166.
Table 166: Amount of shear studs applied
Amount of shear
studs applied
Roof - Outside
Diameter
Height
Max. ctc
360 mm
Min.
ctc
45 mm
Height stud
head
12 mm
Volume
1440 mm
Diameter
stud head
45 mm
30 mm
0,35 m
3
Roof – Inside
25 mm
300 mm
38 mm
1200 mm
38 mm
10 mm
0,24 m
3
Floor - Outside
30 mm
360 mm
45 mm
1440 mm
45 mm
12 mm
0,35 m
3
Floor – Inside
25 mm
300 mm
38 mm
1200 mm
38 mm
10 mm
0,24 m
3
Walls - Outside
25 mm
300 mm
38 mm
1200 mm
38 mm
10 mm
0,08 m
3
Walls – Inside
25 mm
300 mm
38 mm
1200 mm
38 mm
10 mm
0,17 m
3
3
Total amount of shear
studs applied /m
1,43 m /m
21
COMPARE THE COSTS OF VARIANTS
21.1
Comparing the material quantities
In order to compare the tunnel variants, the amount of materials to be applied for each variant is
summed in table 167 below.
Table 167: Comparing the tunnel variants for the amount of materials used per m1
Prestressed
Tunnel
Steel Shell
variant 1
Steel Shell
variant 2
Not feasible
Stirrups
0,52
m /m
Tensile
reinforcement
4,25
m /m
Steel plate
4,25
m /m
Stiffeners
0,94
m /m
Kubilay Bekarlar - Master Thesis
SCS Sandwich
Tunnel
3
Stirrups
0,52
m /m
3
Tensile
reinforcement
3,25
m /m
3
Steel plate
5,52
m /m
3
Stiffeners
1,50
m /m
- 146 -
3
3
3
Steel plate
10,8
m /m
3
Stiffeners
1,50
m /m
August – 2016
3
3
3
Studs
1,10
m /m
3
Concrete
266
m /m
Studs
1,04
m /m
Concrete
278,9
m /m
3
Studs
1,43
m /m
3
3
Concrete
266
m /m
3
As there was concluded in the previous section about the transversely prestressed concrete tunnel,
this method is not a feasible solution for large span tunnels. This is why the materials are not
further quantified. Comparing the amount of materials applied for the two steel shell tunnel
variants there can be observed that amount of stirrups applied for both variants is the same. As for
the tensile reinforcement there can be seen that more is applied for variant 1. On the other hand
the amount of steel plates applied for variant 2 is larger. This has to do with the fact that steel
plates are also placed in the inner side of the steel shell tunnel. Further there can be seen that the
amount of stiffeners applied for variant 2 is larger, this also has to do with the fact that steel plates
are also placed on the inner side of the tunnel. Since steel plates on the inner side also need to be
stiffened, which explains the difference in values. The same holds for the steel studs to be applied,
in which variant 2 requires more. Also due to the steel plates on the inner side which need to be
connected with the concrete inner core by studs. Further, the amount of concrete to be applied for
variant 1 is slightly larger because the dimensions of the elements are slightly larger.
Comparing the quantity of materials applied for the steel shell tunnel with the SCS tunnel, the
following can be seen. First of all no stirrups and tensile reinforcement is needed for the SCS
tunnel. The amount of steel plates applied for the SCS is larger than for the steel shell variant 1
and 2. This due to the fact that for a SCS tunnel steel plates are applied on both sides of the
concrete and in between there are diaphragm’s placed. That is why the steel plates applied to the
SCS tunnel are about twice as high as the steel shell tunnel.
The amount of stiffeners applied to the SCS tunnel is the same as for the steel shell tunnel variant
2. On the other side there can be observed that the amount of stiffeners to be applied for the steel
shell tunnel variant 1 is less than steel shell variant 2 and the SCS tunnel.
From the quantity of studs applied to the tunnels there can be seen that the volume of studs for
the SCS tunnel is the highest. Same as stated above the reason for this larger amount is that steel
plates are on both sides of the concrete and both plates need to be connected with the concrete.
The same holds for the steel shell tunnel variant 2. Since the overall thickness of the steel plates is
less, this results in less stud volume to be applied for the steel shell tunnel variant 2 in comparison
with the SCS tunnel. For the steel shell tunnel variant 1 there can be seen that the volume of studs
to be applied is the least of the three variants. This is explainable by the fact that the steel is
applied at only one side of the concrete, where the inner side is made out of reinforced concrete.
Finally the concrete quantity will be discussed. There can be seen that the amount is nearly same
for all variants. Only for variant 1 the concrete to be applied is slightly more. This is because of the
extra concrete to be applied as a cover on the reinforcing steel.
21.2
Comparing the costs
In order to make a costs comparison the material quantities need to be multiplied with the unit
prices4, see table 168. These unit prices include labour costs.
4
Data obtained from construction costs specialist at Royal Haskoning DHV, February 2016
Kubilay Bekarlar - Master Thesis
- 147 -
August – 2016
Table 168: Unit price per material
Unit prices per material
Unit Price / kg
Unit Price / m3 or m2
Steel plates
2,50
Euro/kg
19500,00
Euro/m3
Reinforcing Steel
1,10
Euro/kg
8580,00
Euro/m3
Steel Studs
3,00
Euro/kg
23400,00
Euro/m3
Prestressing Steel
5,50
Euro/kg
42900,00
Euro/m3
125,00
Euro/m3
125,00
Euro/m3
20,00
Euro/m2
20,00
Euro/m2
Formwork Walls
75,00
Euro/m2
75,00
Euro/m2
Formwork Roof
150,00
Euro/m2
150,00
Euro/m2
Concrete
Formwork Floor
Since the material quantities and the unit prices are determined, now the total price for each type
of tunnel per meter width can be calculated. With these costs per tunnel variant, the tunnel
variants can be compared with each other. These costs include the costs for labour as well.
As stated before the prestressed immersed tunnel is not a feasible solution, which is why that
variant was not further elaborated. There was seen that the steel shell tunnel variant 1 was a
feasible solution for a large span tunnel of 27m. The results for the costs calculation of this variant
can be observed in table 169.
Table 169: Results of the cost calculation of the steel shell tunnel variant 1
Costs Floor Element incl labour
Stirrups
Costs Roof Element incl labour
Costs Walls incl labour
2007,7
Euro
Stirrups
2007,7
Euro
Stirrups
Tensile reinforcement
17503,2
Euro
Steel plates
51597,0
Euro
Stiffeners
10920,0
Studs
Tensile reinf
15958,8
Euro
Steel plates
51597,0
Euro
Euro
Stiffeners
10920,0
Euro
15990,0
Euro
Studs
15990,0
Concrete
14742,0
Euro
Concrete
Formwork
11358,0
Euro
Formwork
Sum
124117,9
Total
377,5
Euro
Tensile reinf
3003,0
Euro
Steel plates
13104,0
Euro
Stiffeners
3685,5
Euro
Euro
Studs
8346,0
Euro
15561,0
Euro
Concrete
6873,0
Euro
35967,0
Euro
Formwork
7110,0
Euro
148001,5
42499,0
315 000,0 Euro/m tunnel
From these results there can be seen that the costs of the steel shell tunnel variant 1 is 315 000
euros per meter length.
There was also seen that the steel shell tunnel variant 2 was a feasible solution for a large span of
the tunnel for 27m. The results of the cost calculation can be seen in table 170 below.
Table 170: Results of the cost calculation of the steel shell tunnel variant 2
Costs Roof Element incl labour
Costs Floor Element incl labour
Costs Walls incl labour
Stirrups
Tensile
reinforcement
Stirrups
Tensile
reinf
2007,7
Euro
11668,8
Euro
Kubilay Bekarlar - Master Thesis
2007,7
Euro
Stirrups
13470,6
Euro
Tensile reinf
- 148 -
377,5
Euro
3003,0
Euro
August – 2016
Steel plates
68796,0
Euro
Stiffeners
16653,0
Euro
Steel
plates
Stiffeners
Studs
17940,0
Euro
Concrete
15561,0
Euro
Formwork
30288,0
Euro
Sum
162914,5
Total
351 000
68796,0
Euro
Steel plates
13104,0
Euro
16653,0
Euro
Stiffeners
7644,0
Euro
Studs
17940,0
Concrete
13104,0
Euro
Studs
7020,0
Euro
Euro
Concrete
5956,6
Euro
Formwork
11989,0
Euro
Formwork
7110,0
Euro
143960,3
44215,1
Euro/m tunnel
These results show that the costs for the steel shell tunnel variant 2 is 351 000 euros. This value is
higher than value for the costs of variant 1.
Finally the results of the cost calculation for the SCS tunnel is given in table 171.
Table 171: Results of the cost calculation of the SCS tunnel
Costs Roof Element incl labour
Costs Floor Element incl labour
Costs Walls incl labour
Steel plates
112476
Euro
Steel plates
Stiffeners
16653
Euro
Studs
23010
Concrete
11088
Sum
163227,0
Total
421 000
112476
Euro
Steel plates
Stiffeners
16653
Euro
Euro
Studs
23010
Euro
Concrete
13167
165306,0
69615
Euro
Stiffeners
7644
Euro
Euro
Studs
9750
Euro
Euro
Concrete
5040
Euro
92049,2
Euro/m tunnel
From these results there can be seen that the costs for the SCS tunnel per meter length is the
highest with 421 000 euros.
Kubilay Bekarlar - Master Thesis
- 149 -
August – 2016
Conclusion & Recommendations
Kubilay Bekarlar - Master Thesis
- 150 -
August – 2016
22
CONCLUSION AND RECOMMENDATIONS
22.1
Conclusions
In this chapter the most important conclusions drawn from the performed research are described.
In the second part some recommendations are given to provide a direction for further research on
this topic.
Design of a reinforced concrete, SCS sandwich immersed tunnel and determining the
critical span:
In order to determine the critical span for a reinforced concrete tunnel and a SCS tunnel a base
case design was made. For the reinforced concrete tunnel there was seen that with the maximum
reinforcement ratio applied, the maximum span for the roof element is around 18-19m. While for
the floor element this critical span is 21 m. There was seen that for the reinforced concrete tunnel
not the moment-, shear- or normal force capacity was the determining factor, but the crack width
was. This meant that the reinforced concrete tunnel was not able to make the desired span of 27m
meters (reference project).
However for the SCS tunnel the crack width is no limiting factor since the concrete remains inside
the steel casing and is not exposed to the environment. As well as the amount of steel applied for
the SCS tunnel does not have a maximum steel ratio that might be applied, which holds for the
reinforced concrete tunnel. With these characteristics for a SCS tunnel, there was seen that a span
of 27m is feasible.
Schematization and modelling of a SCS sandwich elements in a FEM program:
The schematization of the SCS tunnel was started with a simplified model first. For the simplified
model the SCS shape was idealized to a line element in order to reduce the computation time. So
for the roof, floor and wall element a three node plain strain element CL9PE is applied. The choice
for this element is applied since it gives good insight in the stress and strain distribution. From
these stresses and strains the internal forces can be calculated by integrating over the length of
the element. Another aspect for choosing this element was that it is infinitely long in the axial
direction. The subsoil was schematized with the interface element CL12I. Finally the bedding was
constraint in two directions, X and Y. This model was validated by hand calculations. There was
seen that the simplified model coincides with the hand calculations, which meant that the model is
correct.
After the simplified model was validated, a detailed model was made. This model was made as the
SCS is designed in reality. This means that the steel parts for the inner side and outer side of the
roof, floor and wall element have a specified thickness. The same holds for the diaphragms that
connect the inner and outer steel plates. The steel inner, outer and the diaphragm parts will be
modelled by using the plain strain element CL9PE. This is a three node plain strain element. This
shell element is chosen for the steel since it has a small height compared with its length, just like
the steel plates applied. Another point is that the plain strain elements also have an infinite length
in the axial direction. These elements give a good stress and strain distribution from which the
internal forces can be calculated.
The concrete inner core of a SCS sandwich cell is modelled with the CQ16E element, which is an
eight node plain strain element. This element is square shaped and can be applied for all kind of
analysis including linear, nonlinear and cracking. Also this element has a length which is infinitely
long in its axial direction.
The stiffeners and studs which connect the steel and concrete aren’t modelled physically, rather by
making use of interface elements. For these interface elements a stiffness is given. The stiffness
resembles the degree of connection between these two elements. The applied interface element is
CL12I.
Kubilay Bekarlar - Master Thesis
- 151 -
August – 2016
Detailed analysis of the internal forces (stresses) over the SCS sandwich tunnel element
(Tracing the stress concentration in the structure)
Stress distribution in concrete core
For the stress distribution over the concrete core layer three critical spots were identified for the
roof and floor element. On the left hand side the connection with the outer wall, in the middle of
the span and at the connection with the inner wall. These spots are critical since there are higher
stresses at these locations than the rest of the cross section. When looked at these locations in
more detail, there was seen for the roof, floor and wall elements have stress / strain concentration
points. Since the concrete tensile strength is low, so this was exceeded and tensile cracks appeared
in the concrete tensile section. From the perspective of durability there can be stated that the
cracks in the tensile section is not a problem because the concrete is in a confined space enclosed
by steel. Intrusion of water or minerals in concrete will not take place.
There was also seen that the design concrete compressive stress is exceeded locally and the
characteristic compressive stress value is approached. These spots can be seen in the cells where
the roof and floor elements are connected with the inner and outer walls. As a result of this the
concrete will be locally in the plastic state and local concrete crushing might occur. On the few
places where the yielding strength is exceeded the internal forces will be redistributed. The cracks
however may have impact on the degree of connection between the steel and concrete. Due to the
cracks the shear stiffness of the steel and concrete connection can decrease. This may have impact
on the overall stiffness of the structure. From the durability point of view these cracks have no
impact on the durability of the structure since the concrete is situated in a confined space. On the
other side the exceedance of the stress is only locally, which will result in a redistribution of forces.
Stress distribution in steel parts
From the stress / strain analysis of the steel elements, there was seen that the high tensile and
compressive zones are at the same positions as discussed in the section of concrete stresses and
strain. From the distribution of the stresses and strain in the steel there was be concluded that at
no position in the steel structure the elastic tensile / compressive stresses and strain was
exceeded.
Optimization of the SCS sandwich tunnel design with a detailed FEM analysis:
From the detailed model accurate insight in the distribution of the internal forces was obtained. In
other words, the design forces were determined more accurately and the uncertainties were less,
which meant that the design of the structure was further optimized.
Also the high water and soil pressures acting on the structure result in large axial forces in the
elements. Taking these axial forces into consideration, new moment capacities can be determined
that are higher since large axial forces result in an increase of the concrete compressive force,
consequently also the moment capacity. For these elements where large axial forces and moments
are present, interaction diagrams were made in order to determine the ultimate moment capacity
for a certain axial force. This was done for the roof, floor and wall element.
From the detailed analysis of the internal forces (FEM) and also the taking into consideration the
large axial forces by using the interaction diagram, the design was optimized. The unity checks for
the moment capacity that used to be around 70%, was raised to 85-90%. The same was also done
for the shear capacity, which used to be around 60%, was also raised to 85-90%.
There was seen that the total amount of steel applied for the design using the detail analysis is
reduced significantly. Where in the previous design the applied steel in the cross section was 11,96
m2, has now reduced to 9,45 m2. This is a reduction of the steel applied with 21 %. In absolute
values, this is a reduction of 2,51 m3 per meter in the axial direction. The optimization which leads
to reduction of the steel applied with 21% is a significant improvement. These optimized values
may not look significant at the first sight however they will be significant since these values are
only done for one meter in the axial direction of the tunnel. Considering that immersed tunnel
Kubilay Bekarlar - Master Thesis
- 152 -
August – 2016
projects range from several hundred meters to several kilometres, it means that this type of
optimization will be highly important. Since the steel is an expensive material and hence one of the
major expenses of a SCS tunnel project because it is applied on a large scale.
The amount of concrete applied in a SCS immersed tunnel was not further optimized because that
amount was needed for the immersion and floating balance. In other words, if the amount of
concrete in the SCS structure is reduced, than it has to be applied as ballast concrete in the cross
section. Another reason is that the thickness of the concrete has impact on the moment capacity
since the internal level arm of the forces in the steel become larger which correspondents with a
higher moment capacity. This is the reason why no further optimization of the amount of concrete
will take place.
Analysis whether a prestressed (post tensioned) reinforced concrete tunnel and a steel
shell tunnel is a feasible solution for a tunnel with a large span in the cross direction:
From the new design of a concrete tunnel element there can be concluded that a span of 27 m is
not feasible with prestressed roof and floor elements. In the initial reinforced concrete tunnel
design there was seen that the crack width was the limiting factor. By adding prestressed tendons
the crack width becomes small enough. However the prestress tendons to be applied have a
dimension of 510 mm by 420 mm. This makes it impossible to fit several of 55 strands of Y1860S7
tendons per meter width of the cross section.
If those tendons were able to fit the cross section, there was seen that the moment and shear
force capacity is also larger than the design moment and shear force in ULS. On the other side
there was seen from the analysis that large axial forces were present. In order to bear these large
axial forces, high strength concrete is required. From this analysis there is seen that a transversely
prestressed reinforced concrete tunnel is not a feasible solution for a tunnel with a large span in
the transverse direction.
For the steel shell tunnel two variants were researched. One normal steel shell tunnel with steel
shell on the outer side and reinforced concrete on the inner side. The second variant also has a
steel shell on the outer side and a steel cover plate on the inner side, which will seal the concrete
from the inner environment of the tunnel. For the first steel shell variant, the new exposure class
for the concrete is moderate humid. This leads to a reduction of the concrete cover to 60 mm.
There was seen for the first variant that all checks were fulfilled including the crack width. For the
second variant on the other side the crack width is not relevant, since the concrete is sealed on the
inner side with a steel plate and there is the steel shell on the outer side. This means that the other
checks are relevant such as, moment-, shear- and normal force capacity. All these checks also
fulfilled the conditions. Which lead to the conclusion that both steel shell variants are feasible
solutions for tunnels with large spans in the cross direction up to 27 m.
Comparison of a SCS immersed tunnel with other types of tunnels, for large spans in
terms of cost and materials:
In order to make a cost comparison for the variants, first the amount of material required per
meter length for each variant was determined. From the amount of materials, the costs per variant
was determined, including labour.
Since the presetressed reinforced concrete tunnel is not a feasible solution, it is not in this
comparison. On the other side there was seen that the steel shell tunnel variant 1 was a feasible
solution for a large span tunnel (27 m). From the costs analysis there was seen that steel shell
tunnel variant 1 would cost 315 000 euros per meter length. This is the costs including labour.
Also the steel shell tunnel variant 2 was a feasible solution for a large span of 27 m. This variant
was slightly more expensive then variant 1. The costs for this tunnel per meter length is 351 000
euros. The same analysis was performed for the SCS tunnel. This variant is with 421 000 euros per
meter length, more expensive than the other two steel shell tunnel variants.
Kubilay Bekarlar - Master Thesis
- 153 -
August – 2016
Is a SCS sandwich immersed tunnel the most ideal solution for tunnels with large span in
the cross direction? (Main research question)
In terms of costs a reinforced concrete tunnel is the most ideal solution for tunnels with a span up
to 18 / 19 m. This is also the limiting span for a reinforced concrete tunnel. Also a transversely
prestressed (post tensioned) reinforced tunnel was investigated in detail, however the conclusion
was drawn that it is not a feasible option. On the other had a span of 18 / 19 m is not considered a
large span for the cross section.
For the reference project (Sharq Crossing) which initiated this research project a large span was
desired of around 27 m. With this research project there was seen that a large span up to 27 m is
feasible with a SCS sandwich tunnel as well as a steel shell tunnel. However in terms of costs a
SCS tunnel is not the most ideal solution for a tunnel with a large span which is around 27m. From
the costs analysis there was seen that the SCS tunnel is around 34% more expensive than steel
shell variant 1 and 20% more expensive than the steel shell tunnel variant 2. In other words, for a
tunnel span in the cross direction of between 19 till 28 m a steel shell tunnel is the most ideal
solution in terms of costs. The amount of costs that can be reduced is significant. The higher costs
for a SCS sandwich tunnel have to do with the fact that more steel is applied. However a detailed
FEM analysis needs to be performed for a steel shell tunnel for a large span. This way insight will
be gathered how the steel shell will respond to loading due to a large span.
However choosing for a SCS sandwich tunnel a span shorter than 29 m, has also several
advantages. One advantage is that the shear force capacity and moment capacity of a SCS tunnel
is larger than a steel shell tunnel. This advantage can be important for changing boundary
conditions or accidental loading on the tunnel structure. One can think of an explosion, sunken ship
on top of the tunnel or extra loading due to sedimentation on top of the tunnel or erosion below the
tunnel floor. Another aspect worth mentioning separately is the loading on the structure due to
earthquake. If the construction area is in a region where the risks for earthquakes are significant,
then the SCS sandwich is the most ideal solution. This is the case for the reference project the
Sharq Crossing (Qatar), risks for an earthquake in that part of the Arabian Peninsula is significant 5.
Since the design lifetime of a tunnel is up to 100 years, conditions and loadings may change. In
that case a SCS tunnel might be an ideal solution.
Another aspect is the safety. As stated before a SCS tunnel is a stronger and more rigid structure
then other tunnel types. Since in a SCS tunnel more steel has been applied, a higher rest capacity
is present and the structure will behave more ductile if the ultimate strength would be exceeded.
This is in particular important for the safety of the people making use of the tunnel. Which is less
the case for structures that show failure closer to brittle failure.
Another conclusion is that the SCS sandwich tunnel becomes the most ideal solution for a span 28
m or larger. Since for spans larger than 28 m the SCS tunnel is the only feasible solution. This has
to do with the fact that at a span of 29 m the steel shell tunnel does not hold the crack width
condition for the inner environment. While for a SCS tunnel the crack width is not a limiting
condition. The points mentioned above are summarized in table 172.
Table 172: Overview of ideal solution for a certain span in the cross direction
Length of span
Reinforced Concrete Tunnel
Steel Shell Tunnel
Steel Concrete Steel Sandwich Tunnel
< 19 m
Most ideal solution
Not ideal
Not ideal
19 – 28 m
Not feasible
Ideal solution
Ideal solution
>28 m
Not feasible
Not feasible
Only feasible solution
5
Earthquake hazard zonation of Eastern Arabia: Jamal A. Abdalla and Al-Homoud 2004
Kubilay Bekarlar - Master Thesis
- 154 -
August – 2016
22.2
Recommendations
The effect of the uneven soil settlement on the design optimization of a SCS tunnel.
The effect of uneven soil settlement on the design is important for further research because it
might have impact on the detailed design of a SCS sandwich tunnel. A reinforced concrete tunnel
consists of segments which form an element. These segments are prestressed with prestress
cables during the transport to its final location. After immersed on its final location the prestress
cables are cut off, which enables the tunnel segments to adjust to the subsoil. This will prevent the
creation of large spans beneath the floor element. As for a SCS tunnel, this tunnel consists of one
big element, without any segments. In other words, scour underneath the structure may introduce
extra loading on the structure. Studying this phenomenon and describing the impact on the
detailed design of a SCS tunnel is a research on its own.
Nonlinear analysis
For this thesis only linear elastic material behaviour is assumed. By using the nonlinear analysis
more insight will be gathered regarding the development of the cracks as well as the failure
mechanisms. This way more information will be gathered about the ductile behaviour of a SCS
tunnel due to extreme loading.
Detailed analysis of structural response of a SCS tunnel to loading due to explosion or
fire.
In this research loading due to an explosion inside the tunnel was briefly analysed with the FEM
program. There was seen that the structure did not collapse due to this load. However there are
more things included such as fire. There are certain things that should be investigated as the
response of the steel and concrete sandwich structure to heat inside the tunnel. Also the fire
protection is an important aspect regarding this topic.
Research whether a fibre reinforced concrete tunnel a feasible solution is for a tunnel
with a large span in the transverse direction.
There was concluded with this research that a reinforced concrete tunnel has its limits regarding a
large span. The limiting condition was the crack width. However fibre reinforced concrete has
several advantages like reducing the crack width and improving the structural strength, compared
with normal concrete. After the feasibility study also a comparison in costs should be made in order
to compare it with the other tunnel types.
Detailed FEM Analysis of a steel shell tunnel for large spans
After this research among other aspects, also detailed insight in the structural response of a SCS
tunnel has been gathered. The same needs to be done for a steel shell tunnel to see how it will
respond to loading on a large span. Stress / strain concentration points needs to be identified and
analysed.
Kubilay Bekarlar - Master Thesis
- 155 -
August – 2016
Appendix
Kubilay Bekarlar - Master Thesis
- 156 -
August – 2016
23
LITERATURE
Book: Immersed Tunnels
Authors: Richard Lunniss, Jonathan Baber
Lecture notes: Bored and Immersed Tunnels – TU Delft
Author: Dr. Ir. K. J. Bakker
Lecture slides: Concrete Science and Technology
Author: Prof. Dr. Ir. K. van Breugel
Report: Double skin composite construction for submerged tube tunnels – Phase3, 1997
Author: European Commission for Technical Steel Research
Report: “Stalen en composiet staalbeton tunnelconstructies – Staalbeton sandwichelementen, Deel
2: Modelvorming en rekenregels” English: “Steel and composite steel concrete tunnel constructions
– Steel concrete sandwich elements” – 2000
Author: Centrum Ondergronds Bouwen
Paper: Immersed Tunnels in Japan: Recent Technological Trends - 2002
Authors: Keiichi Akimoto, Youichi Hashidate, Hitoshi Kitayama, Kentaro Kumagai
Paper: Development of sandwich structure submerged tunnel tube production method
Authors: Hideo Kimura, Hiroo Moritaka, Ichio Kojima
Paper: Self-compacting concrete - 2003
Authors: Hajime Okamura, Masahiro Ouchi
Paper: The challenges involved in concrete works of Marmaray immersed tunnel with a service life
of 100 years - 2009
Authors: Ahmet Gokce, Fumio Koyama, Masahiko Tsuchiya, Turgut Gencoglu
Paper: “Finite element analysis of steel concrete steel sandwich beams” – 2007
Author: N. Foundoukos, J.C. Chapman
Paper: Behaviour of composite segment for shield tunnel – 2010
Authors: Wenjun Zhang, Atsushi Koizumi
Kubilay Bekarlar - Master Thesis
- 157 -
August – 2016
24
APPENDIX A
Immersed Tunnels General
24.1
Introduction
One of the options to cross a waterway is by an immersed tunnel. As the name says these tunnel
elements can be transported over great distances and be immersed at its final location. Immersed
tunnels consist of a large pre-cast concrete or concrete-filled steel tunnel elements fabricated in
the dry and installed under water. At the moment there are about 180 immersed tunnels built ever
since 1893. Compared with the other types of tunnel this number is rather low. This also means
that this technique is still in its infancy.
An immersed tunnel can be preferred over a bridge, bored tunnel or a cut and cover tunnel due to
its several advantages. The disadvantage of a bridge is that it limits the air draft of the ships
passing under the bridge. A solution would be a moveable bridge, but still this has some
disadvantages as waiting times and limited cross section to pass under. Bored tunnels on the other
side are not possible to execute in soft alluvial sandy soils. Since the bored tunnels need a cover
layer of about one time the tunnel diameter (to prevent uplift), the bored tunnels are normally
more expensive. Also with very deep tunnels bored tunnels are not the most economical solution.
The biggest disadvantage of a cut and cover technique is that the waterway will be reduced to half
of its capacity. At some frequently used waterway this is not a preferred choice.
Another advantage is that immersed tunnel elements are fabricated in convenient lengths on
shipways, in dry docks or in improvised floodable basins where they can be floated out. Bulkheads
are needed to create a watertight tunnel element which can be floated. Immersed tunnel elements
are usually floated to the site using their buoyant state. However, sometimes additional external
buoyancy tanks attached to the elements would be used if necessary. They are then towed to their
final location where the tunnel elements will be lowered into their location after adding either
temporary water ballast or tremie concrete. After the tunnel is immersed into a trench and joined
to previously placed tunnel elements, foundation works will be completed and the trench around
the immersed tunnel is backfilled and the water bed reinstated.
The countries where the immersed tunnels are constructed more often are the US, the Netherlands
and Japan. There is a significant difference between the immersed tunnels constructed in these
countries. In the US the immersed tunnels are constructed more often with a single or double steel
shell. As for the Netherlands the traditional tunnel is built out of reinforced concrete segments. In
Japan reinforced concrete, steel plate or steel concrete steel composite (sandwich) tunnels are
constructed more often. This type of tunnel will be described in more detail below with the
emphasis on steel concrete steel immersed tunnel elements.
24.2
Types of tunnels
24.2.1
Single shell immersed tunnel
The single shell immersed tunnels consists of a stiffened outer shell. This steel shell is stiffened in
the longitudinal and transverse direction. It is normally manufactured by using 10 mm thick steel
plate. The steel shell provides strength and water tightness. On the inner side of the steel shell a
reinforced concrete lining is placed. This reinforced concrete acts compositely with the steel and the
inner lining is about 700 mm thick, figure a- 1. The steel shell which is exposed to the marine
environment is most commonly protected by a cathodic protection system.
Kubilay Bekarlar - Master Thesis
- 158 -
August – 2016
A big advantage of the steel shell tunnels is that the steel shell can be built in small facility or a
shipping yard. Nearly all countries have these types of shipyards where the shells can be
constructed. Another advantage is that the concrete can be casted in a steel shell while it is afloat.
For this, the tunnel element will be towed to a jetty, where the concrete will be cast. The small
draft of a steel shell makes it possible to execute an immersed tunnel in shallow waters. This would
certainly not be the case with reinforced concrete immersed tunnels where the draft is large.
In order to give the steel shell resistances against deforming, stiffeners are attached in the
longitudinal and transverse directions. The shear studs which are connected on the inner side of
the steel shell connect the steel with concrete. This way the steel and concrete will act compositely.
Figure A- 1: Left: single shell tunnel and right: construction of a single shell
To prevent extreme loading on the single steel shell tunnel during launching of the tunnel from a
slipway, these tunnels are launched sideways. This way the internal stresses will be minimized.
Otherwise the tunnel elements would have to be designed more robustly. Before launching, the
reinforcement for the inner concrete lining is placed together with other internal equipment and a
certain amount of keel concrete is also placed to increase the draft of the element and to give it
stability while afloat. Bulkheads are applied at the ends which prevents the water from entering the
tunnel element. This way the element can be transported over water to its final position.
24.2.2
Double steel shell immersed tunnel
This tunnel consists of two steel shell layers, one on the inner side and the other on the external.
Compared with a single steel shell, the inner shell is thinner (about 8 mm). These steel shells
provide strength and water tightness. External diaphragms are added at intervals between the
inner and external steel shell, also known as a form plate. On the inner side of the steel shell
reinforced concrete lining is placed. This lining will act compositely with the steel shell. Around the
inner shell there is an outer shell also known as form plate. This outer plate is slightly thinner than
the inner plate, about 6 mm. The space between the two shells is filled with concrete, which acts as
ballast and also protects the inner steel shell against corrosion. In figure a- 2 there is a cross
section of a double shell immersed tunnel element.
The construction method is similar to that of a single steel section. Fabrication of the steel shell is
done from a series of modules then assembled on a slipway and launched. It is then towed to an
outfitting site and the concrete is placed while the element is afloat.
Kubilay Bekarlar - Master Thesis
- 159 -
August – 2016
Figure A- 2: Double shell immersed tunnel element
24.2.3
Concrete immersed tunnels
The reinforced concrete immersed tunnel is predominantly used in the European countries, in
particular the Netherlands. The main driving reason for this is that the steel prices in Europe are
relatively high. Because of the fact that the Dutch waterways are not that deep, rectangular shaped
reinforced concrete elements were constructed. An advantage of the rectangular shape is that it
matches the rectangular traffic envelope belter. Some rough dimensions of a concrete immersed
tunnel are about 1 m for the floor and roof and the inner and outer wall all the way from 0,3m to
0,7m.
An important aspect is the foundation of the immersed tunnel. The foundation should provide
uniform bedding for the tunnel element. If this is not the case, high local stresses will be
generated. In order to prevent this some techniques were provided such as sand jetting and sand
flow. Sand jetting where a water sand mixture was jetted under the tunnel had the disadvantage
that the jetting plant was an obstacle in the waterway. Sand flow happens through pipes casted in
the tunnel element. In this case the water sand mixture flows slowly under the tunnel without
obstructing the waterway.
Tunnel elements used to be built as 100 m long monolithic reinforced concrete structures, figure a3. The disadvantage of these types of long concrete structures is that due to thermal shrinkage
cracking can occur. As a result water could leak into the tunnel. In order to prevent thermal
cracking, engineers in the Netherlands divided element of over 100 m into several smaller
segments of 20 – 25 m. An element is not cast in one pour, first the base is cast where after the
walls and roof are cast. The temperature development during the second cast is controlled closely
and measures are taken if necessary to prevent significant thermal differences between the base
and wall slabs. By cooling concrete during curing cracking could be prevented and the need for a
waterproof membrane was eliminated. Omission of a waterproofing layer results in a reduction of
construction time and money. On the other hand, the individual segments have to be connected by
prestressing to form a continuous element while being towed towards its final location. After the
concrete elements are immersed the prestress tendons are cut off.
Figure A- 3: Cross section reinforced concrete tunnel
Even though water tight concrete was produced by segmenting the concrete tunnel element, the
weakness was that more joints were introduced. The joints are potential sources of leakage. In
order to make the segment joints watertight, a continuous water stop is placed in the joint. These
Kubilay Bekarlar - Master Thesis
- 160 -
August – 2016
water stops were developed so that grout could be injected around the ends so that any porosity in
the concrete near the tips of the water stop could be sealed.
24.2.4
Monolithic concrete tunnel element
As stated before the concrete tunnel element can either be executed as a segmental or as a
monolithic tunnel element. The monolithic tunnel element is made as a continuous structure.
Reinforced concrete tunnels constructed before 1960 -1970 were constructed as monolithic
elements. As stated before, the cracking is the main cause of problem for a monolithic structure.
To prevent this thermal control measures are taken as well as a waterproof layer is placed on top
of it. For a monolithic concrete tunnel, this is considered to provide the best long-term solution for
water tightness and hence durability. Reinforcing steel is used to account for the tensile stresses in
the slabs and walls. A typical dimension of a monolithic tunnel element is about 100 m to 200 m
long. The base, walls, and roof are all rigidly connected together with the reinforcement throughout
the section and across the construction joints.
The monolithically constructed tunnel elements provide great flexibility for the designer, since it
can provide variation in the height width of the tunnel cross section as well as in the length
direction. This is useful if the width varies or an emergency lane has to be provided. At the joints
between the monolithic elements shear keys are provided where the shear is transferred and which
also makes sure that the elements remain in alignment.
Since the tunnel element is exposed to fresh or saline water it needs to be protected against
corrosion as well. This is usually done by applying a bituminous coating or a protective epoxy layer.
Even this may not be enough to protect the tunnel for a life time of 100 years. The extra security is
provided by cathodic protection.
Cathodic protection for the steelwork provides this additional security. This can either be a
sacrificial anode protection system or an impressed current cathodic protection system. The
sacrificial anode system, which usually consists of zinc anodes fixed to the outside of the steel
membrane, is designed to make up the difference between the expected life of the protective
coating and the design life of the tunnel, with an additional allowance made for a possible
percentage of defects in the coating. An impressed current system can be installed at the outset, or
provision can be made to retrofit one later if subsequent monitoring of the steelwork corrosion
shows that it is needed. Another way to protect the tunnel element is by applying some additional
thickness to the steel membrane. This way the steel membrane will still have the required
thickness at the end of the design life of the tunnel. A newly applied technique is the plastic
membrane instead of steel. This is a more cost efficient solution than the steel membrane.
The monolithic immersed tunnel could also be designed as a prestressed monolithic element. The
advantage of this is that the amount of longitudinal reinforcement would be reduced. Also
sometimes transverse prestress is considered. When the span in the cross section increases due to
requirements, then the reinforced concrete sections become uneconomic. A disadvantage however
is that the anchorages of the prestress tendons are positioned on the outside of the tunnel element
and should be protected well against the environment.
24.2.5
Segmental concrete tunnel
The segmental concrete tunnel was developed from the monolithic tunnel in order to omit the
waterproofing layer on the structure. As stated before the main cause of leakage in a monolithic
tunnel element is due to thermal cracks created by thermal differences, between the freshly poured
concrete on the already hardened concrete. These cracks create a path for water to go from the
Kubilay Bekarlar - Master Thesis
- 161 -
August – 2016
outside towards the inside of the tunnel. Measures are taken to reduce the cracks in a monolithic
tunnel element but nevertheless completely crack free element cannot be guaranteed.
To encounter the crack problem with the monolithic element, the segmental tunnel element was
introduced by the Dutch engineers. They limited the tunnel size to segments of 22 – 25 m this way
crack free tunnel segments could be manufactured. The segment was cast roughly in two sessions,
first the base was casted where after the walls and roofs were. A typical segment joint detail can
be observed in figure a- 4.
Figure A- 4: Segment joint – detail segmental concrete tunnel
The temperature of the second pour is carefully controlled to prevent the concrete from cracking as
it cools. As for the tensile stresses, this is kept below the developing tensile strength of concrete. A
way to achieve it is by a concrete mix design, controlling of temperature and insulating of the
formwork. All these controlled the temperature gradient in the boundary of the existing and fresh
concrete. External insulation was applied to the shutters to prevent the concrete from cooling too
quickly. These measures control the development of the stresses in concrete such that it does not
exceed the tensile strength of the poured concrete. Through these techniques it possible to cast a
crack free cross section. A watertight external membrane becomes unnecessary.
As stated before a tunnel element consists of several segments. These segments are connected
with joints where after they are clamped together with longitudinal prestress, such that they
behave as a single homogeneous tunnel element for transporting and placing. Prestressing cables
are cut after the element has been placed into its final location.
24.2.6
SCS sandwich composite immersed tunnel
Steel concrete steel composite sandwich construction is a relatively new application in the
immersed tunnel engineering. This technique is mostly used in Japan. Roughly stated it is
constructed from steel plates connected by shear plates and diaphragms. In between the steel
plates self-compacting concrete is poured. The unreinforced concrete gives the structure stiffness
and connects the steel plates with each other. This results in concrete acting compositely with the
steel. The steel concrete connection is provided by steel studs welded on the steel plates. These
steel studs also account for the longitudinal shear stress between the concrete and steel plates,
figure a- 5. Placing this concrete and ensuring sufficient compaction and complete filling of the void
between the plates, is one of the main challenges of this method. This is why self-compacting
concrete is applied rather than conventional concrete which it is not possible to compact in a
confined space. Due to the ideal configuration of the steel and concrete parts of a SCS sandwich
tunnel slabs, these slabs will be designed more slender. However the envelope of free space for the
traffic will remain the same as for a reinforced concrete tunnel for example. So a lighter structure
with the same upward force can cause a balance problem. If the mass of the tunnel element is not
in the structural section as part of the load carrying members, it has to be applied elsewhere as
internal ballast or on the roof.
Kubilay Bekarlar - Master Thesis
- 162 -
August – 2016
Figure A- 5: Steel concrete steel sandwich element with shear studs
A major advantage of the SCS sandwich tunnel element is that it behaves ductile when the
ultimate capacity is exceeded. The structure will show large deflections rather than a brittle failure.
In case of dynamic loading this property of a SCS composite sandwich tunnel makes it favourable,
dynamic loading such as explosion or earthquake.
As stated before, the studs that connect the steel with the concrete also accounts for the shear
force between the steel and concrete. To be effective at resisting shear, these studs have to extend
through the full depth of the section and must be anchored in the compression zone. Another
function of the shear studs is to prevent the steel plate in the compression zone from buckling. The
spacing between the studs can be reduced to prevent the steel plate to buckle.
The composite tunnel is an elegant solution to a structural problem. Since the steel and the
concrete are used efficiently a strong and light element is created. A lighter tunnel element has a
shallower draught which enhanced the application of it delta regions with shallow waters. There can
also be opted for the casting of concrete close to the location of the tunnel. Then first the steel
shell will be constructed and this will be towed to the final tunnel location.
Two layers of steel create a double watertight layer which is an important advantage of this type of
tunnel, because preventing water leakage into the tunnel is critical. Another advantage is that this
design does not need formwork to cast the concrete in. This has to do with the fact that the steel
shells are used as permanent formwork and it will cut down the costs for extra materials and
labour. In figure a- 6 below, there is a 3 dimensional schematization of a SCS sandwich tunnel.
Figure A- 6: Schematization of a SCS sandwich tunnel element
Another major advantage of a SCS sandwich tunnel compared with reinforced concrete tunnel is
that the SCS tunnel doesn’t has an upper / lower limit of reinforcement ratio unlike the reinforced
concrete tunnel. The reinforcement ratio limit of 2% for reinforced concrete structures is against
Kubilay Bekarlar - Master Thesis
- 163 -
August – 2016
brittle failure, concrete cracking at smaller deflection and difficult concrete casting around the steel.
These aspects don’t hold for SCS structures since the steel is on the outer side of the element and
it can be thicker if needed. That is why there is no upper steel ratio limit.
As stated before, the SCS sandwich tunnel element is not easy to execute. Especially casting of the
concrete is challenging. The self-compacting concrete is poured into the steel casing by using
nozzles or tremie-pipe either in the top or bottom steel plate. Pouring the concrete through the
bottom plate with a nozzle makes it able for the self-compacting concrete reaches the voids better.
Air holes are placed in the corners of the steel shell where the trapped air can get out and the
voids can be filled. Vibrating elements are placed on top of the steel shell which helps to release
the trapped air. Ensuring a complete fill is essential for a good bond between the steel studs and
the concrete.
Fires inside a SCS sandwich tunnels is of bigger concern than for other types of tunnels. This has to
with the high heat absorption of steel. Because of the fact that the steel is on the outer side of the
structure it is more vulnerable for heat development inside the tunnel. In case of a reinforced
concrete tunnel this is a smaller problem since the steel bars are covered in concrete. This problem
for the SCS sandwich tunnel is solved by applying a fire resistant layer on the steel outer shell.
25
APPENDIX B
Variants of composite sandwich tunnels
Immersed tunnels can be divided into three main groups: reinforced concrete tunnels, steel shell
tunnels and composite sandwich tunnels. The composite sandwich tunnels can also be subdivided.
There are full sandwich tunnels, open sandwich tunnels and a combination of both.
25.1
Full sandwich tunnel element
In case of a full sandwich tunnel all elements of the tunnel are made out of SCS sandwich
members. Steel plates on both sides are provided with steel studs and or stiffeners and are
interconnected with self-compacting concrete. The shear reinforcement and diapragms connect
both steel plates with eachother. Because of the outer steel plates, which accounts for the tensile
stresses no reinforcement is needed. In figure a- 7, a schematization is given of a tunnel cross
section where all elements are designed as full sandwich.
The first application of the full sandwich immersed tunnel is the Okinawa Naha Port Tunnel in Japan
because all members are made as a SCS sandwich member. This tunnel is a road tunnel of which
the immersed part is 724 m long. It consists of 8 elements with a height of 8,7 m. Because of the
fact that no suitable casting yard was near the tunnel location, the engineers were forced to
construct the steel shell and cast while it was afloat. The biggest advantage of a SCS full sandwich
tunnel element compared with the open sandwich tunnel element is that the full sandwich tunnel
can be built in a shorter time period. Further since all members are SCS sandwich members this
variant is also lighter than the open sandwich tunnel.
Kubilay Bekarlar - Master Thesis
- 164 -
August – 2016
Figure A- 7: Steel - Concrete - Steel full sandwich tunnel
25.2
Open sandwich tunnel element
The immersed tunnel is an open sandwich tunnel if at least one member is made as an open
sandwich and the other elements are of reinforced concrete. An open sandwich member is made
out of a steel plate on the outer side which is connected to concrete by shear studs. On the inner
side of the member reinforced concrete is applied. The other members will be made of reinforced
concrete, figure a- 8. Therefore there are different configurations possible for an open composite
immersed tunnel. Compared with the reinforced concrete tunnel, the open sandwich tunnel allows
the total weight of the structure to be reduced. But compared with the full sandwich it is still
heavier. An advantage of this variant compared with a full sandwich is that it is more cost efficient,
since less steel is used. Conventional concrete can be applied for the bottom slab which is from the
executional point of view advantageuos, easy casting. Further just like the full sandwich tunnel the
concrete can also be casted while it is afloat.
The Osaka Port Sakishima tunnel is an application of an open sandwich member for the floor slab
and reinforced concrete for the roof and inner walls. This tunnel consists of 10 elements with a
height of 8,5 m and a width of 35,2 m. The length of a tunnel element is 103 m.
Figure A- 8: Steel concrete open sandwich tunnel
Kubilay Bekarlar - Master Thesis
- 165 -
August – 2016
25.3
Combination of full sandwich and open sandwich members
A combination of open and full sandwich tunnel has also been designed. In that case some
members will be open sandwich members and the others will be full sandwich members, see figure
a- 9. The bottom slab is often designed as an open sandwich element with a steel plate on the
outer side and reinforced concrete on the inner side, as described above. On the other side the roof
slab and the outer walls are designed as full sandwich members. An advantage of this variant is
that the full sandwich members can be designed more slender, which will reduce the overall weight
compared with the open sandwich tunnel. Reduction of the weight would reduce the draught which
will be an executional advantage. Another aspect is that the full sandwich roof and walls are
important to prevent brittle failure in case the ultimate bearing capacity is exceeded, the same
holds for the full sandwich tunnel. So this variant is a solution in between the two earlier
mentioned.
Osaka Port Yumeshima Tunnel is an example of a combination of full sandwich and open sandwich
tunnel members. The immersed tunnel consists of 8 immersed tunnel elements of 8,6m height and
35,4m in width. The length of the element varies from 93,1 m to 103,5 m.
Figure A- 9: Composite tunnel consisting as a combination of open and full sandwich members
25.4
Elements in a SCS sandwich members
The SCS sandwich member consists of several members such as: upper skin plate, lower skin
plate, stiffeners, shear connectors, diaphragm and shear reinforcement, see figure a- 10.
Kubilay Bekarlar - Master Thesis
- 166 -
August – 2016
Figure A- 10: Schematization of a SCS sandwich tunnel element with all members
25.4.1
Shear Studs
In a SCS sandwich tunnel project hundreds of thousands of shear studs are applied on the steel
plates. The studs are normally made with a length which is less than 200mm. In case of a full
sandwich member the studs are placed on the top and bottom steel plate. Studs are extended till
the compression zone. As stated before these shear studs are a connection between the steel and
concrete and account for the longitudinal shear force. Spacing of the studs can be adjusted
depending to prevent buckling of the compression steel plate and shear failure. Shear studs can be
attached either automated or manually. There is not much difference in the price however, since
the automated system has to suit the design specifications.
25.4.2
Steel plates
The steel plates form the border of a SCS sandwich compartment. Stiffeners give these plates
rigidity, which is essential during concrete casting. These structural plates account for the tensile
forces acting on the cross section. Besides the structural function of these plates, they also provide
two watertight layers. This is an essential aspect for the tunnels.
25.4.3
Shear reinforcement plates
Shear reinforcement are steel plates in the transverse direction of a SCS sandwich member. These
plates account for the shear stresses in the member. Because it connects both steel plates with
each other it gives stiffness to the plates and prevents it from deforming during concrete pouring.
25.4.4
Diaphragm
The diaphragm is installed in the tunnel axis direction to create the compartments. It also accounts
for the shear stresses. Also the diaphragms connect both steel plates with each other it gives the
steel shell stiffness to prevent it from deforming during concrete pouring.
25.4.5
Self-Compacting concrete
The part of the cross section that connects all members with each other is the concrete. Because of
the enclosed steel compartment conventional concrete cannot be used, since compacting by
vibrating is not possible. This is why self-compacting concrete is applied. Self-compacting concrete
is poured in after which the concrete compacts by itself due to its typical composition.
25.4.6
Stiffeners
In order not to deform during towing of the steel shell, stiffeners are attached on the steel plates.
These stiffeners will make the steel shells robust enough to float. They also provide stiffness which
is essential during pouring of concrete which helps it not to deform. Stiffeners have to be applied in
the longitudinal and transverse direction. Different shapes could be used for stiffeners, such as Ishape, T-shape or L-Shape.
Kubilay Bekarlar - Master Thesis
- 167 -
August – 2016
26
APPENDIX C
Identified topics
26.1
Self-compacting concrete
Because the self-compacting concrete is an essential part of the SCS sandwich tunnel and a
relatively new technique, this topic is dealt with in more detail. In order to create durable concrete
adequate compacting is needed. This would mean that when concrete is not well compacted the
quality is reduced. To prevent concrete durability depending on the degree of compaction, selfcompacting concrete was developed. Self-compacting concrete has a special composition which
enables it to compact into every corner of the formwork, purely by means of its own weight. These
are the main reasons why self-compacting concrete is applied in SCS sandwich tunnel elements.
The prototype of self-compacting concrete was first completed in 1988 in Japan.
Besides the high deformability property of self-compacting concrete, it also has a high resistance
against segregation. Dropping the concrete paste from several meters high will not cause any
problem. Paste is viscous in order to be able to flow around the obstacles. High deformability is
achieved by applying superplastizer. In the figure a- 11 below the composition of self-compacting
concrete is compared with normal concrete.
Figure A- 11: Composition of normal and self-compacting concrete, where S fine aggregate, G coarse aggregate
and W water
There can be seen that self-compacting concrete has an aggregate content which is lower than the
conventional concrete. In figure a- 12 there is a sketch which summarizes how self-compacting
concrete can be achieved. The ratio of coarse aggregate in self-compacting relative to the total
solid volume is 50%, this to reduce interaction between coarse agregate particles when concrete
deforms. Whereas the degree of fine aggregates in self-compacting concrete mortar is 60%, see
figure a- 13. The viscosity of self-compacting concrete paste is higher than the conventional
concrete because of its low water powder ratio.
Figure A- 12: Achieving self-compatibility
Kubilay Bekarlar - Master Thesis
- 168 -
August – 2016
Ratio of coarse aggregate volume to the total solid volume given and the ratio of the fine aggrgate
volume to the total solid volume are given in the figure below both for self-compacting concrete
(SCC) and conventional concrete (Normal). The figure on the right hand side gives a comparison of
the water powder ratio of self-compacting concrete and normal concrete.
Figure A- 13: Coarse and fine aggregate ratio and water powder ratio of normal and SCC
Another important component of self-compacting concrete is the superplasticizer. Superplasticizer
in combination with a low water powder ratio will keeps the concrete paste highly deformable.
Depending on the properties of the powder, the water powder ratio is assumed around 0,9 – 1,0.
The flow ability of fresh concrete depends on coarse aggregate and on the spacing of obstacles
(studs). Sufficient deformability of the mortar is needed so the concrete paste can be compacted
by its self-weight into all edges of the structure. In figure a- 14 below the normal stresses in the
mortar due to approaching of coarse particles is given.
Figure A- 14: Mortars shear resistance schematization and test schematization
Besides of the function of the mortar as a fluid as stated before it also has a function as solid
particle. This property is called the pressure transferability, which acts on the coarse particles as
normal stresses when these particles approach each other. The mortars shear resistance is
schematized in the figure above. Further self-compacting concrete saves costs of vibrating
compaction. However the total costs cannot always be reduced. In figure a- 15 below a practical
application of self-compacting concrete can be seen for a steel concrete composite tunnel element.
Figure A- 15: Application of self-compacting concrete in steel concrete composite tunnel
Kubilay Bekarlar - Master Thesis
- 169 -
August – 2016
26.2
Loading
The loading on the immersed tunnel can be divided into two categories:
-
26.2.1
Loading which induces internal forces in the plane of the tunnel walls such as, dead load,
hydrostatic load and backfill pressure.
Loading resulting in internal forces in the longitudinal direction of the tunnel such as,
jacking force and differential forces due to settlement of the subsoil.
Dead load
Dead load of the tunnel includes the weights of concrete, steel plate, studs, spacers and ballast.
Dead weight acts in the gravity direction, but can be resolved into axial and transverse components
for the analysis of the tunnel cross-section. The dead loads can act with or against the hydrostatic
and backfill loading.
26.2.2
Hydrostatic load and backfill
Hydrostatic and backfill pressures constitute the major component of the loading. Both pressures
can be assumed to increase linearly with depth. The hydrostatic pressure Pw at any depth h below
the water surface is given by:
The ρw is the unit weight of water. The pressure is at the top of the tunnel roof is
x
, at the
underside of the tunnel it is ( + D)x ρw. Hydrostatic pressure acts equally in all directions, hw is
determined from the height of the maximum water level above zero level. Variations in the water
level as a result of waves, tides, river flows, and atmospheric conditions should be taken into
account.
The pressure can be divided into three components:
26.2.3
Pressure on the tunnel roof
Pressure on the side walls
Pressure on the floor
Pressure on the tunnel roof
Pressure on the roof Pr is given by:
Pr = hw x ρw + hb (ρsat – ρw) + hs (ρsat – ρw)
Pr = hw x pw + hb (ρsub) + hs (ρsub)
The ρsat is the saturated unit weight and ρsub is the submerged unit weight of the backfill. The
designer should note that the depth of the backfill can change as a result of sedimentation or the
movement of sediment. An appropriate allowance for this, hs, should be made in the design. It
should also be noted that, for the roof, self-weight loads are additive to the hydrostatic and backfill
loading.
26.2.4
Pressure on the side walls
The pressure on the side walls is given by:
Ph = (hw + hf) ρw + k (hb + hf) ρsub + k hs ρsub
Kubilay Bekarlar - Master Thesis
- 170 -
August – 2016
In this formula k is the effective lateral earth pressure coefficient. This value lies between the
active and passive coefficient.
The is the angle of internal friction. Because the backfill is under water the angle of friction may
be assumed =0 which results in k = 1. That is why the horizontal pressure below the tunnel roof
can be calculated as follows:
Ph = (hw + hr) ρw + (hb + hr) ρsub + hs ρsub
A more accurate value for k may be adopted for k if more reliable data about the lateral earth
pressure is available. But for the initial design the earlier assumption is sufficient.
26.2.5
Pressure on the floor
The pressure acting on the base is the hydrostatic pressure. Since the tunnel will normally have
negative buoyancy, the extra weight of the tunnel will be resisted by the soil on which the tunnel
rests. The submerged weight of the backfill on the tunnel roof and any skin friction on the sides of
the tunnel section must be resisted. These are additional pressures on the base of the tunnel. It
can be assumed that these additional load components are reacted by the soil as uniformity
distributed loads.
The hydrostatic pressure on the base is given as:
Base pressure due to hydrostatics = (hw + D) ρw
The weight of the tunnel can be determined from BF2. The base pressure due to the weight of the
tunnel can be calculated as follows.
Base pressure due to tunnel net weight = (D ρw / BF2) – D ρw
Backfill and sedimentation loads will be transferred via the tunnel cross-section to the tunnel base.
The pressure acting on the base can be calculated as follows:
Base pressure due to backfill = hbc ρsub + hs ρsub
The skin friction acts on both sides of the tunnel. It can be calculated from the horizontal earth
pressure forces by multiplying by tan φ where φ is the effective angle of friction. Note that tan φ
should not be less than 0.5. If skin friction is caused by backfill settlement, then skin friction forces
act downward on the base. This gives a tunnel base pressure as follows:
Base pressure due to skin friction =
(2 hs + 2 hb + hr)
Combining the above expression gives the total pressure on the tunnel base:
Ρb = (hw ρw ) + (D ρw / BF2) + (hb + hs) ρsub +
(2 hs + 2hb + hr)
When calculating internal forces in the tunnel base, it should be noted that the self-weight of the
base acts in the opposite direction to the above pressure.
Kubilay Bekarlar - Master Thesis
- 171 -
August – 2016
26.2.6
Loading due to placing
The tunnel elements are placed on hydraulic jacks that can be adjusted. This way a concentrated
end reaction is applied by the jack on the tunnel element. When there is only one jack supporting
the tunnel element then torsion is exerted on the tunnel element
26.2.7
Loading due to subsoil settlement
When the tunnel is resting on uniformly supported subsoil, no longitudinal moments are generated.
However if the subsoil under the tunnel element settles, then there is no uniform support of the
subsoil. This way concentrated load will act on the tunnel which will result in high local stresses.
26.2.8
Wave loading
The waves, tides and high and low pressure conditions can lead to to variations in the height of the
water surface. This causes on its turn variations in hydrostatic pressure on the immersed tunnels.
Variations should be considered to determine the maximum hydrostatic pressure. In general,
immersed tube tunnels are constructed in sheltered waters, and the influence of wave loading is
likely to be small compared with the influence of forces due to jacking and differential settlements.
If tunnel elements are to be floated across open sea from fabrication yards remote from the tunnel
site, then wave loading needs to be considered more rigorously. The waves will cause additional
bending moments in the tunnel element.
When wavelength and the length of a tunnel are of the same order, then the most critical situation
may be estimated as the Wave length L is identical with the length of an element.
The tunnel element will be loaded by a sinusoidal distributed lateral force with its highest action
upwards at the ends of the caisson and the larges downward forces in the middle of the element
figure a- 16.
Figure A- 16: Wave loading on a tunnel element
26.2.9
Thermal loading
The loading is caused by loads induced during service due to small temperature gradients. It is
assumed that material properties are unchanged. Fire response analysis requires a different
approach. Normally under service conditions the temperature of immersed tunnels remains
approximately constant and the effects of temperature differences are small. However, thermal
forces are induced by a relatively small, linear thermal gradient between the inside and outside of
the tunnel wall and this should be assessed.
26.2.10
Sunken ship loading
The chance for a concentrated load on the tunnel due to a sunken ship is relatively small.
Nevertheless the tunnel should fulfill the safety requirements for resisting the loads if such an
event happens. This means that the governing (heaviest) ship should be taken into account in the
calculations.
Kubilay Bekarlar - Master Thesis
- 172 -
August – 2016
26.2.11
Traffic loading
The traffic loading amounts approximately for 5-10% of the upward loading on the floor slab of the
tunnel. This will be balanced by the increased foundation pressure. Due to the thickness of the floor
slab and the ballast concrete layer, the influence of the traffic loading on the forces acting on the
cross section will be limited. That is why the traffic load is neglected in most cases.
26.2.12
Load combinations
The governing situation is that several loads act simultaneously in-plane and longitudinal. Most
unfavorable loading combination is taken in order to calculate the internal forces acting on a
tunnel.
26.3
SCS Sandwich Elements Laboratory Test Results
Experiments were carried out at the University of Wales in Cardiff regarding SCS sandwich
elements in 1985. Various aspects of structural performance of SCS elements were investigated.
The purpose of these tests were to validate the conclusions of the first test series to obtain a
clearer and more thorough understanding of the structural behaviour of SCS and to produce a
published design guide specific to SCS construction. In the initial program several tests were
conducted. There has to be stated that there are differences between the SCS tunnels elements
made in Japan and the elements tested in the UK. The biggest difference is that the tested beams
at the University of Wales don’t have diaphragms and shear reinforcement.
First the ultimate load tests were carried out. For these tests SCS sandwich beams, columns,
radius, joints and tunnel cross sections were used. Also fatigue tests were carried out. Parameters
as plate thickness, shear connection, stud length, loading and concrete strength were examined.
The test results of the beams showed that all beams except one exhibit ductile behaviour. One
suddenly collapsed due to failure of tension plate connectors. Slip was the cause of failure for three
beams. The fatigue test showed that all the beams failed on cracking of the tension plate
connectors at the weld affected zone. Also there could be seen that that with an increase in the
loading, the number of cycles to failure decreased.
For the columns two of the three test pieces showed ductile behaviour with yielding of the tension
plate and reduction of the carrying capacity. The other columned showed also ductile behaviour
where the buckling of the compression plate resulted in a reduction of the load carrying capacity.
There was limited slip between the steel and concrete which concludes that there was a proper
connection between these elements.
There were four radius specimen tested. All four specimen exhibited ductile behaviour. Two failure
modes were distinguished, yielding of the inner plate and stud pull-out. Therefore there was
concluded that an increase in the loads would result in the strengthening in the inner plate. Also
the tension connection with concrete needed to be increased by increasing the length of the studs
and reducing the spacing.
Two of the four tested T-junctions had radius plates and the other two had right angled plates.
Under transverse loading there was only little difference between these two joints. Overall
junctions with radius joints were able to withstand a load which is three to four times more than
the straight plates. There was concluded that for T-joints with straight plates the arrangement of
studs is a crucial factor. In flexural conditions joints fail due to studs pulling out and the right
angled joints straighten out.
Kubilay Bekarlar - Master Thesis
- 173 -
August – 2016
Tunnel cross sections were subjected to horizontal and vertical loads. The tunnel section also
showed ductile behaviour. Collapse of the tunnel section was due to shear failure of the concrete.
The tunnel was repaired by injecting epoxy in the cracked concrete. This confirmed the application
of repairs to these types of SCS composite elements. Tests revealed that where collapse was
caused by failure of concrete than it is possible to carry out repairs.
To summarize these experiments, the following failure modes can be identified, figure a- 17:
-
yielding of the tension steel plate
yielding or buckling of the compression steel plate
crushing of concrete in compression
shear failure of the concrete
horizontal or slip failure of the stud connectors
pull out failure of connectors
Figure A- 17: Failure modes of SCS composite sandwich elements
The behaviour of the test elements showed agreement with the design models. One of the main
conclusions of this research program was that SCS sandwich elements could be designed with
conventional methods for composite construction.
27
APPENDIX D
Project Sharq Crossing
The reason why the Sharq crossing project in Doha Qatar is
related to this research is that TEC (Tunnel Engineering
Consultants) and Royal Hoskoning DHV engineers designed
a steel-concrete-steel immersed tunnel. The knowledge
gathered from this research will give a better insight in the
limits of the design rules as well as the optimization of the
design.
TEC (a joint venture between Witteveen+ Bos and
RoyalHaskoningDHV), together with Santiago Calatrava
Engineers and Architects worked on the validation of the
original concept design of five tunnels for the Sharq
Crossing,
figure a- 18. TEC designed in total five tunnels for
the Sharq crossing. Two are immersed tunnels of 3.1 and
2.8 km and three are cut-and-cover tunnels with a length of
approx. 950-1250 m each connecting the bridges to the
Figure A- 18: Map of the Sharq Crossing and immersed
tunnel
Kubilay Bekarlar - Master Thesis
- 174 -
August – 2016
Marine Interchange of approx. 600 m, connecting the two immersed tunnels and one of the
bridges.
Besides the tunnels TEC also works on the bridge foundations, roads, utilities, mechanical,
electrical and plumbing systems, the integral safety concept including ventilation and construction
schedule.
The sandwich immersed tunnel designed for the Sharq crossing will be the first sandwich tunnel
designed by TEC as well as the first sandwich immersed tunnel is this region of the world. This
explains the relation between this research and the Sharq crossing project.
28
APPENDIX E
28.1
Hand calculation design forces
Table 173: Hand calculation of the design forces for different spans
Design forces 15m Span
Design forces 20 Span
Internal Forces - approximation – ULS
Internal Forces - approximation – ULS
Med - roof
5043,825
kNm
Med - roof
8966,8
kNm
Med - floor
-5129,55
kNm
Med - floor
-9119,2
kNm
V-roof
1681,275
kN
V-roof
2241,7
kN
V-floor
-1709,85
kN
V-floor
-2279,8
kN
N-roof
1294,513
kN
N-roof
1294,513
kN
N-floor
2040,044
kN
N-floor
2040,044
kN
Internal Forces - approximation – SLS
Internal Forces - approximation – SLS
Med - roof
4109,85
kNm
Med - roof
7306,4
kNm
Med - floor
-4004,78
kNm
Med - floor
-7119,6
kNm
V-roof
1369,95
kN
V-roof
1826,6
kN
V-floor
-1334,93
kN
V-floor
-1779,9
kN
N-roof
1125,679
kN
N-roof
1125,679
kN
N-floor
1773,968
kN
N-floor
1773,968
kN
Design forces 25 Span
Design forces 27 Span
Internal Forces - approximation – ULS
Internal Forces - approximation – ULS
Med - roof
14010,63
kNm
Med - roof
16341,99
kNm
Med - floor
-14248,8
kNm
Med - floor
-16619,7
kNm
V-roof
2802,125
kN
V-roof
3026,295
kN
V-floor
-2849,75
kN
V-floor
-3077,73
kN
N-roof
1294,513
kN
N-roof
1294,513
kN
N-floor
2040,044
kN
N-floor
2040,044
kN
Internal Forces - approximation – SLS
Med - roof
11416,25
Kubilay Bekarlar - Master Thesis
Internal Forces - approximation – SLS
kNm
Med - roof
- 175 -
13315,91
August – 2016
kNm
Med - floor
-11124,4
kNm
Med - floor
-12975,5
kNm
V-roof
2283,25
kN
V-roof
2465,91
kN
V-floor
-2224,88
kN
V-floor
-2402,87
kN
N-roof
1125,679
kN
N-roof
1125,679
kN
N-floor
1773,968
kN
N-floor
1773,968
kN
Structural calculation software Matrixframe is used to check the hand calculations for the ULS case.
The bedding is assumed to be uniform. This analysis is done for spans of 15m, 20m, 25m, and
27m. The results are illustrated in figure 168 below.
Internal forces - Span 15 m
Internal forces - Span 20 m
Kubilay Bekarlar - Master Thesis
- 176 -
August – 2016
Internal forces - Span 25 m
Kubilay Bekarlar - Master Thesis
- 177 -
August – 2016
Internal forces - Span 27 m
Figure 168: Internal forces (ULS) for different spans from Matrixframe.
28.2
Capacity calculations for the floor element for a span of 20 m
Moment capacity – span 20 m (ULS)
Also for the floor first the amount of tensile, compressive reinforcement and the stirrups should be
determined. The same steps as described for the roof element are made in order to determine the
moment capacity. But first the strains need to be determined. The only unknown is the
compression zone height in ULS. This is calculated from the spreadsheet, which is 743,5 mm.
Results for the floor element are given in table 174 below.
Table 174: Layout reinforcement, area and the strains
Kubilay Bekarlar - Master Thesis
- 178 -
August – 2016
Distances
ds
Tensile reinforcement
Compressive reinforcement
2
1st layer
2
2nd layer
1st layer
1773
[mm]
1st layer
10053
[mm ]
2nd layer
1683
[mm]
2nd layer
10053
[mm ]
3th layer
1593
[mm]
3th layer
10053
[mm ]
4962
2
[mm ]
2
[mm ]
2
Stirrups
1st layer
d eff
1683,0
[mm]
Total
30159
2
804,2477
[mm ]
Asw
8,47
[mm /mm]
2
[mm ]
Stirrups
Effective depths
Strains
ε'cu,3
-0,350%
ds1
1773
[mm]
εs1
0,485%
ρtensile
1,59 %
ds2
1683
[mm]
εs2
0,442%
ρcompressive
0,26 %
ds3
1593
[mm]
εs3
0,400%
ds4
91
[mm]
εs4
-0,307%
2
After the strains are calculated, the next step is determining the forces in the reinforcement. With
all forces known the design moment resistance Mrd can be calculated by multiplying these loads
with their eccentricities towards the reference point. This value will be checked with the design
moment Med, table 175. There can be concluded from the calculations that for this span of 20 m
the design moment is smaller than the moment resistance of the cross sections.
Table 175: Moment capacity check
Steel, concrete forces
N'cd;1
Moment resistance
-13011,25
[kN]
MN'cd;1
-3763,13
[kNm]
Ns1
4371,23
[kN]
MNs1
7750,19
[kNm]
Ns2
4371,23
[kN]
MNs2
7356,78
[kNm]
Ns3
Ns4
4371,23
[kN]
MNs3
6963,36
[kNm]
-2157,57
[kN]
MNs4
-196,34
[kNm]
Ns5
0,00
[kN]
MNs5
0,00
[kNm]
Nd
2040,04
[kN]
MNd
1938,04
[kNm]
ΣF
0,00
[kN]
ΣMRd
20048,90
[kNm]
eccentricity e0
Med
0,06
9248,40
U-check
4.3.3.2 - Normal stress capacity – span 20 m check (ULS)
Again the compressive stress check will be done, this time for the roof element.
( )
In which:
Kubilay Bekarlar - Master Thesis
- 179 -
August – 2016
[m]
[kNm]
0,46
N is the normal force in the floor element
Ac,eff is the effective cross sectional area of the floor
M is the design moment
W is the sectional modulus
Table 176: Normal stress check
Normal stresses
2
fcd
-23,33
[N/mm ]
σc,top
-16,23
[N/mm ]
2
U-check
0,695
The unity check in Table 176 shows that the roof element holds the condition of not exceeding the
concrete compressive stress.
4.3.3.3 - Shear force capacity – span 20 m check (ULS)
Just like the roof element also the floor will be checked for not exceeding the shear capacity. This is
first done for the case without shear reinforcement (stirrups). Therefor the following formula is
applied, to calculate the shear resistance of concrete (without stirrups).
[
(
)
]
In which:
√
These calculations are made for all the spans that are investigated. The results for a span of 20 m
are listed in table 29 below. As can be seen the cross section is not able to bear the shear force in
case no shear reinforcement is applied. This means that shear reinforcement has to be applied and
the shear capacity check has to be done again, now for the shear reinforced cross section.
(
)
In which:
The minimum value of the two calculated shear force resistances will be used to calculate the unity
check.
(
)
The unity check for the shear capacity for the cross section with 8,47 mm 2/mm of shear
reinforcement, shows that for a span of 20 m the working shear force can be carried, Table 177.
Kubilay Bekarlar - Master Thesis
- 180 -
August – 2016
Table 177: Shear force resistance check with and without shear reinforcement
Shear resistance
Ved
2279,8
[kN]
Nd
2040,0
[kN]
Bearing capacity without stirrups
Bearing capacity with stirrups
Crd,c
0,12
[-]
Θ
45
⁰
αcw
k
1,34
[-]
Α
90
⁰
V1
k1
0,15
[-]
cot θ
ρ1
0,0179198
σcp
1,07
[-]
1
Asw
8,47
5578,5
1
0,6
tan θ
1
2
[mm /mm]
2
[N/mm ]
Vrd,c
1350,1
[kN]
Vrs,d
Ved
2279,8
[kN]
Vrd,max
Ved
U-check
≤ [kN]
10602,9
[kN]
2279,8
[kN]
1,688
U-check
0,41
4.3.3.4 - Crack width control floor (SLS)
The next check is the crack width control check. This is a serviceability limit state (SLS) check,
which means that the moments and normal forces in SLS will be used. In order to calculate the
crack width, first the concrete compression zone is determined. The same steps as for the roof
element will be repeated for the floor element. Results are shown in table 178 below.
Table 178: Strain, forces, moments and steel stress
Serviceability limit state
Nrep
1774,0
[kN]
Eccentricities
Mrep,sls
-7119,6
x
Strains
e'c3
ec
677
[mm]
ε'c
-0,66
‰
es1
823
[mm]
εs1
0,76
‰
es2
733
[mm]
εs2
0,69
‰
es3
643
[mm]
εs3
0,62
‰
es4
859
[mm]
εs4
-0,58
‰
es5
950
[mm]
εs5
-0,66
‰
Forces
-5395,0
kN
MN'c
3649,9
[kNm]
Ns1
1535,2
kN
MNs1
1263,5
[kNm]
Ns2
1390,2
kN
MNs2
1019,0
[kNm]
Ns3
1245,1
kN
MNs3
800,6
[kNm]
Ns4
-580,2
kN
MNs4
498,4
[kNm]
0,0
kN
MNs5
0,0
[kNm]
1774,0
kN
Mrep
-7119,6
[kNm]
Nrep
0,00175
Moments
N'c
Ns5
820,4
Kubilay Bekarlar - Master Thesis
- 181 -
August – 2016
[mm]
ΣF
0,0
kN
ΣM
0
[kNm]
σs
152,715
Since the stress in the reinforcing steel has been determined, the crack width that will occur can be
calculated. In order to do so the following formula is used:
(
)
(
)
These calculation steps have been carried out by making use of a spread sheet program and the
results are given in table 179 below.
Table 179: Crack width control
Crack width
εsm -εcm
0,6103256
‰
2
s1
125
[mm]
wk
wmax
αe
5,8823529
[n/mm ]
s1,max
535
[mm]
ρp,eff
0,0555926
[-]
sr,max
407,26
[mm]
heff
542,5
[mm]
k1
0,8
[-]
k2
0,5
[-]
Ac,eff
542500
2
[mm ]
2
fct,eff
3,21
[n/mm ]
k3
3,4
[-]
ξ1
1
[-]
k4
0,425
[-]
kt
0,4
[-]
φeq
32
[mm]
kx
1
[-]
U-check
0,248558
[mm]
0,3
[mm]
0,83
As there can be seen from the unity check in table 31 above, the occurring crack width exceeds the
maximum allowed crack width. This is valid for a span of 20 m and current reinforcement ratio of
ρtensile :1,59 % ρcompression :0,26%.
28.3
Capacity calculations for the outer wall element for a span of 20 m
4.3.4.1 - Moment capacity – span 20 m (ULS)
The same steps as described for the roof element are made in order to determine the moment
capacity. But first the strains need to be determined. The only unknown is the compression zone in
ULS. This is calculated from the spreadsheet, which is 503 mm. Results for the floor element are
given in table 180 below
Table 180: Reinforcement layout, area and strains
Distances
ds
Tensile reinforcement
Compressive reinforcement
2
1st layer
2
2nd layer
1st layer
1373
[mm]
1st layer
10053
[mm ]
2nd layer
1283
[mm]
2nd layer
10053
[mm ]
3th layer
0
[mm]
4962
2
[mm ]
2
[mm ]
2
3th layer
[mm ]
Stirrups
1st layer
Kubilay Bekarlar - Master Thesis
- 182 -
804,25
August – 2016
2
[mm ]
d eff
1328,00
[mm]
Total
2
20106
[mm ]
Stirrups
Effective depths
Strains
Asw
8,47
2
[mm /mm]
ε'cu,3
-0,350%
ds1
1373
[mm]
εs1
0,605%
ρtensile
1,35 %
ds2
1283
[mm]
εs2
0,543%
ρcompression
0,33 %
ds3
0
[mm]
εs3
ds4
91
[mm]
εs4
ds5
0
[mm]
εs5
-0,287%
With the strains known, the forces in the reinforcement and the concrete compressive zone can be
calculated. With the eccentricities the design moment resistance Mrd will be determined, table 181.
Table 181: Moment capacity check
Steel, concrete forces
N'cd;1
Moment resistance
-8802,50
[kN]
MN'cd;1
-1722,36
[kNm]
Ns1
4371,23
[kN]
MNs1
6001,69
[kNm]
Ns2
4371,23
[kN]
MNs2
5608,28
[kNm]
Ns3
0,00
[kN]
MNs3
0,00
[kNm]
Ns4
-2157,57
[kN]
MNs4
-196,34
[kNm]
Ns5
0,00
[kN]
MNs5
0,00
[kNm]
Nd
2203,00
[kN]
MNd
1652,25
[kNm]
ΣF
0,00
[kN]
ΣMRd
11343,53
[kNm]
eccentricity
e0
Med
0,05
5504,25
U-check
[m]
[kNm]
0,485
As shown above the design moment occurring at a span of 20 m is smaller than the design
moment resistance.
4.3.4.2 - Normal stress capacity – span 20 m check (ULS)
The compressive stress check will be done once more:
( )
Table 182: Normal stress check
Normal stresses
2
fcd
-23,33
[N/mm ]
σc,top
-15,85
[N/mm ]
xu
503,00
[mm]
Kubilay Bekarlar - Master Thesis
2
U-check
- 183 -
0,679411
August – 2016
Table 182 shows, that the normal stress occurring in the outer wall is smaller than the concrete
compressive yield stress.
4.3.4.3 - Shear force capacity – span 20 m check (ULS)
First the shear capacity will be checked for the case when there is no shear reinforcement
(stirrups) applied. Therefor the following formula is applied to calculate the shear resistance of
concrete (without stirrups), table 183. As can be seen the cross section is not able to bear the
shear force in case no shear reinforcement is applied. This means that shear reinforcement has to
be applied and the shear capacity check has to be done again, now for the shear reinforced cross
section.
The unity check for the shear capacity for the cross section with 8,47 mm2/mm of shear
reinforcement, shows that for a span of 20 m the working shear force can be carried, table 183.
Table 183: Shear force capacity check
Shear resistance
Ved
1684,3
[kN]
Nd
2203,0
[kN]
Bearing capacity without stirrups
Bearing capacity with stirrups
Crd,c
0,12
[-]
θ
45
⁰
αcw
k
1,39
[-]
α
90
⁰
V1
k1
0,15
[-]
cot θ
ρ1
0,0151401
[-]
Asw
8,47
σcp
1,47
1
0,6
tan θ
1
2
[mm /mm]
2
[N/mm ]
Vrd,c
1123,4
[kN]
Vrs,d
4401,8
≤ [kN]
Ved
1684,3
[kN]
Vrd,max
8366,4
[kN]
Ved
1684,3
[kN]
U-check
1
1,499273
U-check
0,38
4.3.4.4 - Crack width control floor (SLS)
Now the crack width control check will be performed. The same steps as for the roof and floor
element will be repeated for the outer wall element. Again the stress in the steel in the
serviceability limit state needs to be calculated first, where after the crack width can be
determined. Results are shown in table table 184 and table 185.
Table 184: Strains, forces, moments and the steels stress
Serviceability limit state
Nrep
2000,0
[kN]
Eccentricities
Mrep,sls
-4395
x
Strains
e'c3
ec
536
[mm]
ε'c
-0,68
‰
es1
623
[mm]
εs1
0,77
‰
es2
533
[mm]
εs2
0,68
‰
es3
-750
[mm]
εs3
-0,68
‰
Kubilay Bekarlar - Master Thesis
- 184 -
641,5
0,00175
August – 2016
[mm]
es4
659
[mm]
εs4
-0,58
‰
es5
750
[mm]
εs5
-0,68
‰
Forces
Moments
N'c
-4339,0
kN
MN'c
2326,4
[kNm]
Ns1
1550,7
kN
MNs1
966,1
[kNm]
Ns2
1359,9
kN
MNs2
724,8
[kNm]
Ns3
0,0
kN
MNs3
0,0
[kNm]
Ns4
-576,0
kN
MNs4
379,6
[kNm]
Ns5
0,0
kN
MNs5
0,0
[kNm]
2000,0
kN
Mrep
-4395,0
[kNm]
0,0
kN
ΣM
0
[kNm]
Nrep
ΣF
σs
154,255
Table 185: Crack width control
Crack width
εsm - εcr
0,596
‰
2
s1
125
[mm]
wk
0,254
[mm]
wmax
0,3
[mm]
U-check
0,85
αe
5,882
[n/mm ]
s1,max
535
[mm]
ρp,eff
0,046
[-]
sr,max
425,74
[mm]
heff
430
[mm]
k1
0,8
[-]
k2
0,5
[-]
Ac,eff
430000
2
[mm ]
2
fct,eff
3,21
[n/mm ]
k3
3,4
[-]
ξ1
1
[-]
k4
0,425
[-]
kt
0,4
[-]
φeq
32
[mm]
kx
1
[-]
As there can be seen in table 185 the cross section with the current dimensions and reinforcement
layout also holds for the crack width. The outer wall with these dimensions also fulfils all other
checks. There can be concluded that the outer wall can be applied.
28.4
Calculation of the composed modulus of elasticity
Table 186: Calculation of the composed modulus of elasticity and height of the floor element
Floor
Inner steel plate
Concrete core
t [mm]
20
b [mm]
1000
2
E [N/mm ]
z [mm]
Outer steel plate
Composed
1845
35
1900
1000
1000
1000
210000
34000
210000
10
922,5
17,5
950
2
A [mm ]
20000
1845000
35000
1900000
4
1,67E+09
1,5375E+11
2,92E+09
1,58E+11
4
1,74E+10
5,23E+11
3,09E+10
5,72E+11
4,20E+09
6,27E+10
7,35E+09
7,43E+10
3,50E+14
5,23E+15
6,13E+14
6,19E+15
Ixx [mm ]
Iyy [mm ]
EA [N]
2
EIxx [N mm ]
Kubilay Bekarlar - Master Thesis
- 185 -
August – 2016
2
EIyy [N mm ]
3,65E+15
1,78E+16
h*
2124,63
Exx*
34961,36
[N/mm ]
Eyy*
34961,36
[N/mm ]
6,50E+15
2,79E+16
[mm]
2
2
Table 187: Calculation of the composed modulus of elasticity and height of the roof element
Roof
Inner steel plate
Concrete core
Outer steel plate
Composed
25
1540
35
1600
1000
t [mm]
b [mm]
2
E [N/mm ]
z [mm]
1000
1000
1000
210000
34000
210000
12,5
770
17,5
800
2
A [mm ]
25000
1540000
35000
1600000
4
2,08E+09
1,28333E+11
2,92E+09
1,33E+11
4
1,53E+10
3,04E+11
2,17E+10
3,41E+11
Ixx [mm ]
Iyy [mm ]
EA [N]
5,25E+09
5,24E+10
7,35E+09
6,50E+10
2
4,38E+14
4,36E+15
6,13E+14
5,41E+15
2
3,21E+15
1,03E+16
4,56E+15
1,81E+16
EIxx [N mm ]
EIyy [N mm ]
h*
1829,65
[mm]
Exx*
35503,98
[N/mm ]
Eyy*
35503,98
[N/mm ]
2
2
Table 188: Calculation of the composed modulus of elasticity and height of the wall element
Wall
Inner steel plate
Concrete core
Outer steel plate
Composed
20
1455
25
1500
1000
t [mm]
b [mm]
2
E [N/mm ]
z [mm]
1000
1000
1000
210000
34000
210000
10
727,5
12,5
750
2
A [mm ]
20000
1455000
25000
1500000
4
1,67E+09
1,2125E+11
2,08E+09
1,25E+11
4
1,09E+10
2,57E+11
1,37E+10
2,81E+11
Ixx [mm ]
Iyy [mm ]
EA [N]
4,20E+09
4,95E+10
5,25E+09
5,89E+10
2
3,50E+14
4,12E+15
4,38E+14
4,91E+15
2
2,28E+15
8,73E+15
2,88E+15
1,39E+16
EIxx [N mm ]
EIyy [N mm ]
h*
1681,77
[mm]
Exx*
35034,57
[N/mm ]
Eyy*
35034,57
[N/mm ]
2
2
These values will be used for the definition of the material properties and physical properties of the
SCS sandwich cross section in Diana.
Kubilay Bekarlar - Master Thesis
- 186 -
August – 2016
28.5
Calculation of the prestress force in the floor element
Point A
t=0
Bottom
Boundary condition fulfilled
Top
Boundary condition fulfilled
Point A
t=∞
Bottom
Boundary condition fulfilled
Top
Boundary condition fulfilled
The same steps are performed for point B.
Point B
t=0
Bottom
Kubilay Bekarlar - Master Thesis
- 187 -
August – 2016
Boundary condition fulfilled
Top
Boundary condition fulfilled
t=∞
Bottom
(
)
(
)
Boundary condition fulfilled
Top
(
)
(
)
Boundary condition fulfilled
29
APPENDIX F
29.1
FEA model
29.1.1
Introduction
In the previous studies done for this research project there was concluded that there should be
investigated whether a SCS sanwdwich tunnel design could be optimized. In order to do so insight
needs to be gathered in the structural response to the loadings in servicability limite state (SLS)
and ultimate limt state (ULS). This can either be done for the linear and nonlinear analysis.
However due to the number of equations that needs to be solved, a Finite Element Analysis (FEA)
software program will be used to do the detailed structural analysis. The FEA program that will be
used is DIANA. Dimensions of the earlier designed “Base Case” of the SCS sandwich tunnel will be
used for the model.
In order to reach the goal of achieving reliable results from the FEA program, the following steps
are performed. First the problem is described. Here after there should be investigated what types
Kubilay Bekarlar - Master Thesis
- 188 -
August – 2016
analysis there are, when they should be used and what type of output there will be generated. The
next step is the idealisation of the SCS sandwich tunnel element into a simplified engineering
problem that can be solved with the FEA program DIANA. Here for studying DIANA elements is
essential to apply the elements with the best charachteristics for this particular problem.
The second phase is modelling of the SCS tunnel element. Initially the schematized structure
geometry will be constructed. Here after a proper mesh will be applied to the structure. The next
step will be the application of the material properties / material models. Material models to be used
depend on the type of analysis that will be made as well as the type of material. This means that a
study should be done on the most suitable material models for the steel and concrete in a SCS
sandwich tunnel element. Finally the loading on the structure and the boundary conditions will be
applied. All these steps will be executed in iDIANA pre-processor.
The next phase takes place in DIANA MeshEdit. Here the analysis types will be specified, where
after the analysis will be run.
The final phase in the post-processing, which will be analyzing the results from DIANA. All these
steps are schematized in figure 169 below.
Figure 169: Schematization of the steps to be performed for the FEA of the SCS sandwich tunnel element
29.1.2
Linear and Non-Linear FEA analysis
The structural analysis can be divided into three broad categories. These are hand analysis, linear
FEA and non-linear FEA. With the hand analysis, the order of magnitude of the internal forces can
be determined. This will allow dimensions to be selected for detailed analysis. For detailed
structural analysis linear and non-linear analysis should be preferred. There are three types of
nonlinearities. Material (physical) nonlinearity, geometrical nonlinearity and boundary (contact)
nonlinearity. The geometrical non-linearity is the change of geometry due to large displacement.
Material non-linearity is the non-linear relation between stress and strain. The contact non-linearity
is caused by the impact on the structures.
29.1.3
Linear analysis
Linear analysis is an acceptable approximation of the reality, where the material behaviour is
assumed to be perfectly linear for a certain loading. This way less material constants are used. So
the linear FEA is performed if there is expected that the structure will behave linearly, according to
the Hook’s Law where the stress is proportional to the strain. The induced displacements are so
Kubilay Bekarlar - Master Thesis
- 189 -
August – 2016
small that the change in geometry and material properties is negligible. After the load is removed,
the structure will return to its original configuration. This is the fundamental principle of linear
structural analysis. In figure 170 a linear elastic material model is given.
Figure 170: Linear elastic material model
Throughout the process of loading and unloading in which the structure deforms, the structure will
retain its initial stiffness. This can be simplified by the following equation:
[ ]
[ ]
[ ]
In which:
[F] is the vector of nodal force
[K] is the stiffness matrix
[d] is the vector of nodal displacement
The stiffness matrix [K] depends on the material, geometry and boundary conditions. For the linear
analysis the stiffness does not change. This means that the equations are just solved once. This
also explains why the computation time is short.
29.1.4
Nonlinear analysis
For a more realistic assessment of the structural response nonlinear analysis should be performed.
Full nonlinear analysis covers the complete loading from nonlinear behaviour in SLS to nonlinear
behaviour ULS which results in collapse. Nonlinear FEA is performed to investigate the behaviour of
the structure beyond the elastic limit of the material. In this case the loading produces a significant
change in the stiffness. Since the element is exposed to plastic deformation it will not return to its
original configuration.
The most important difference with the linear analysis is that the nonlinear analysis does not
assume a constant stiffness. In contrary, the stiffness changes during deformation of the structure.
It means that the stiffness matrix [K] must be updated during the iterative calculation process.
This explains the much longer calculation time for the nonlinear FEA program.
Since the structure generally does not collapse after the appearance of the first crack or local
crushing, that is why the linear elastic analysis is a step back with respect to the limit state. This is
also the reason why a nonlinear analysis should be performed for the full understanding of the
structural behaviour.
The nonlinear analysis can be subdivided into material nonlinear analysis, geometrical nonlinear
analysis and contact nonlinear analysis.
7.2.2.1 - Material (physical) nonlinear analysis
In case the stiffness changes during the loading due to the changing material properties, than it is
a material nonlinearity problem. Engineering materials show a linear stress-strain relationship up to
Kubilay Bekarlar - Master Thesis
- 190 -
August – 2016
a certain stress level. This is the linear elastic domain of the material. The maximum stress level of
this domain is called the design yield stress. Beyond this stress-stress strain relationship becomes
nonlinear, also known as the plastic domain. In figure 171 below the elastic perfectly plastic stressstrain curve is given for concrete and steel. This is the most simple nonlinear material model.
Figure 171: Elastic perfectly plastic stress-strain curves of concrete and steel
The elastic perfectly plastic model does not take into account the plastic strength of the material,
also known as hardening. There is assumed that after reaching the yield strength the structure will
collapse. However after exceeding the yield stress the material will resist the higher stresses in its
plastic state. This given real stress-strain diagram of steel and concrete in figure 172.
The material nonlinear stress strain relationship can cause the structure to behave nonlinearly. The
factors that may influence the material stress-strain relationship are the load history,
environmental conditions (temperature) and the time that a certain load is applied (creep).
Figure 172: Actual stress-strain diagram for steel and concrete
7.2.2.2 - Geometrical nonlinear analysis
As stated before, nonlinear analysis is necessary when the stiffness changes during the loading
process. If the stiffness changes due to change in the shape, than the nonlinearity is defined as
geometrical nonlinearity. These changes in the shape that cause a different stiffness are large
deformations. A rule of thumb that gives an indication when to use a nonlinear geometrical analysis
is when the deformation is 1/20th of the largest dimension. In figure 173 below a nonlinear
response of a structure exposed to loading can be seen.
Kubilay Bekarlar - Master Thesis
- 191 -
August – 2016
Figure 173: Geometrical nonlinearity
Another aspect of large deformations is that the direction of the force will also change during the
loading process. The FEA program has two options regarding this aspect: following and nonfollowing load. In case a following load is chosen, the load remains its orientation towards the
structure where the non-following load remains its initial direction, see figure 174.
Figure 174: Schematization of a following and a non-following load
Changes in stiffness can also occur when the deformations are small. However with small deflection
and small strain there is assumed that the resulting stiffness changes are insignificant.
7.2.2.3 - Boundary (contact) nonlinear analysis
This nonlinear analysis is of importance when there is contact between two or more components.
In civil engineering problems this is the interaction between the structure and the support
(boundary). A normal force contacting the surfaces acts on the two bodies where they touch each
other. In case there is friction between the surfaces, shear forces may be created. The aim of this
analysis is to identify the surfaces that are in contact and to calculate the pressures that are
generated.
7.2.2.4 - Choice of analysis
First there should be started with a simple model of the SCS sandwich tunnel element. This way
there could be checked whether the outcome of the model is in accordance with hand calculation
results. If the hand calculation results and the output of the simple model coincide, then it means
that the applied boundary conditions are realistic.
The analysis type that will be used in the initial stage is the linear elastic analysis. This way there
can be seen whether some elements already yield in this stage. In other words, if there are some
problem areas present these can already be identified in the linear elastic stage. But it does not
give a decisive answer whether the structure will fail. For this the nonlinear analysis should be
performed.
Kubilay Bekarlar - Master Thesis
- 192 -
August – 2016
After the linear analysis the nonlinear analysis can be performed depending on the results of the
linear elastic analysis. The nonlinear analysis will be performed if in large parts of the structure the
limit stresses and strains are exceeded.
29.2
DIANA elements
In this section some of the relevant Diana elements which can be used for the SCS sandwich tunnel
model, will be explained in more detail. The study of the Diana elements is essential in order to
choose the most appropriate element for this SCS sandwich tunnel model. This is necessary since
the better the elements represent the reality the more realistic the output of the model will be.
29.2.1
Beam Elements
The beam element is a bar which fulfils the condition that the height d is small in relation to its
length l, see figure a- 18. These elements can be exposed to axial deformation Δl, shear
deformation γ, curvature κ and torsion. That is why this element can describe axial forces, shear
forces and moments. Beam elements are used to do 2-D and 3-D analysis. This element can be
subdivided into three classes.
Class-I
These are the classical beam elements with directly integrated cross sections. They can be used for
linear analysis and the geometrical nonlinear analysis. For the physical nonlinear analysis it only
gives a limited stress-strain diagram.
Class-II
The elements in the second class are fully numerical integrated classical beams. Linear analysis,
geometrical and physical nonlinear analysis can be performed with these elements.
Class-III
The third class is the fully numerical integrated Mindlin beam element. This can also be used for
linear analysis and nonlinear analysis (geometrical and physical).
Figure A- 19: Beam element
For the beam elements the variables are the displacements, translation and the rotation. Diana can
calculate from these variables the forces, moments and Cauchy stresses in the node. For class I, II
and III Diana derives the deformation from the displacement in the node. From these deformations
it derives the strains, stress, forces and the moments
The beam elements result in a simple model, which leads to a reduced computation time. This
element will give insight in the occurring forces and the behaviour. Also modelling with these
elements is rather easy. However a disadvantage of this element that it does not give sufficient
information about the stresses on a detailed level.
Kubilay Bekarlar - Master Thesis
- 193 -
August – 2016
29.2.2
Plane stress elements
The plane stress element is characterized by the element nodes being in one flat plane. Which
means that the thickness t must be small, compared with the b, see figure a- 18. Whereas the
loading must be in the plane of the element.
Figure A- 20: Plane stress element
Diana has also 3-D plane stress elements available. The loads can be defined in the plane of the
element as well as perpendicular to the plane. Since these elements don’t have stiffness in the
transverse direction, this is why loads perpendicular can only be carried when the element is
connected to another element that has stiffness in this direction. One of the characteristics of the
plane stress elements is that the stress components perpendicular to the face σ xx = 0. These
elements can be applied if there is no bending outside the plane of the structure.
From the deformations Diana derives the strain. Where after it calculates the Chauchy stress and
generalized forces.
29.2.3
Plane strain elements
The plane strain elements must be positioned in the XY-plane, where the Z coordinate of the nodes
must be zero. Similar as the plane stress element also here the loading F must be in the plane of
the element, see figure a- 21. One of the characteristics of the plane strain elements is that the
thickness t is equal to unity. Another characteristic is that the strain component perpendicular to
the face of the element εzz = 0. The following plane strain elements are available in Diana:
-
Standard plane strain elements with triangular and quadrilateral cross section. Nonlinear
analysis can be performed with this element.
Another element is the infinite shell element which has a thickness that is small compared
with its length.
The complete plane strain element is an element which can be applied for 3-D models.
The variables for the plane strain elements are the translations of the nodes. These translations
cause deformation of the elements. From these deformations the strains are determined, which on
its turn results in the derivation of the Cauchy stresses.
Kubilay Bekarlar - Master Thesis
- 194 -
August – 2016
Figure A- 21: Plane strain element
29.2.4
Plate bending element
The plate bending elements must fulfill the condition that the element nodes must be in the flat XY
plane. The dimension of this element is characterized by the fact that the thickness t is small
relative to the width b. There can be stated that the loading on this element must be perpendicular
to the element plane and the moment must act around an axis of the element. This can be
observed in figure a- 22 below.
Figure A- 22: Plate bending element
Another characteristic of the plane bending element is that the stress component perpendicular to
the plate face is zero, σzz = 0.
Variables of the plate bending element is the translation Uz, which is perpendicular to the element
plane and rotation φx and φx. The nodal displacements result in the deformations ∂Ux, ∂Ux and ∂Uz.
From these deformations Diana derives the strains, generalized moments, forces and Cauchy
stresses are calculated by Diana.
29.2.5
Flat shell elements
The flat shell elements are a combination of plane stress elements and plate bending elements.
Just like the previous elements the nodes should be in a flat plane, the XY plane. If this is not the
case and the nodes are not in the XY plane than the curved shell element should be applied. The
element should be thin, in other words the thickness t should be small compared with the width b
of the element. This can be seen in figure a- 23 below.
Kubilay Bekarlar - Master Thesis
- 195 -
August – 2016
Figure A- 23: Flat shell element
The forces can act on this element from in all directions, whereas the moment should act in plane
of the element. Diana offers three flat shell elements: regular element, elements with drilling
rotation and the spline element. Regular elements have three translations and two in plane
rotations in each node. The element with the drilling rotation has an additional rotation φz in each
node. As for the spline element, this element is useful for the analysis of post-buckling of prismatic
structures.
Variables in the nodes of these elements are the translations Ux, Uy and Uz and the rotations φzx
and φy. From these deformations the strains are calculated, where after the generalized moments,
forces and Cauchy stresses are calculated.
29.2.6
Curved shell elements
As the name of this element says so, this element is ideal for curved structures. For flat models the
flat shell elements should be preferred. The curved shell element nodes have five degrees of
freedom, three translations Ux, Uy, Uz and rotations φx and φy. Other characteristic of this element
is that they must be thin (thickness t small compared with width b). Further the load can act in any
direction of the element, see figure a- 24 below. The moment should act around an axis of the
element.
Figure A- 24: Curved shell element
The displacements cause deformations to the elements. From these deformations Diana derives the
strains. This way the output of this element will be given which is: Cauchy stress, moments and
forces.
Kubilay Bekarlar - Master Thesis
- 196 -
August – 2016
29.2.7
Solid elements
When the solid elements are applied, the computation time becomes longer since these elements
produce a larger system of equations. That is the reason why this element should be used when
other elements are not suitable or when the output is not accurate.
One of the characteristics of the solid element is that the stress situation is 3-D. The loading on
this element may be arbitrary. Applications of this element are voluminous structures such as
concrete foundations, walls, floors and soil masses. In figure a- 25 below a solid element is
schematized.
Figure A- 25: Solid element
The solid elements in Diana can be used to determine the Cauchy stresses. Herewith the moment
and forces can also be derived.
29.2.8
Interface elements
Diana offers three types of interfaces elements structural interface elements, contact elements and
fluid-structure interface. For the scope of this research project only the first element type is of
importance.
Applications of the interface element are: elastic bedding, nonlinear-elastic bedding, discrete
cracking, friction between surfaces and joints in rock. With respect to shape and connectivity there
are four types of structural elements:
-
30
Nodal interface element
Line interface element
Line-solid connection interface element
Plane interface element
APPENDIX G
PAPERS AND REPORTS ON SCS SANDWICH TUNNELS AND
COMPOSITE FEM ANALYSIS
Paper: Immersed Tunnels in Japan: Recent Technological Trends - 2002
Authors: Keiichi Akimoto, Youichi Hashidate, Hitoshi Kitayama, Kentaro Kumagai
This paper gives general information about the recent technology on steel-concrete-steel composite
sandwich tunnels and what type of variants there are. The differences between the variants are
Kubilay Bekarlar - Master Thesis
- 197 -
August – 2016
further highlighted. Here after it focusses on several SCS tunnel projects that were built in the last
few decennia in Japan. Further the joint between the elements is discussed.
Conclusions of the paper: Recent years there is an increase in SCS sandwich tunnels constructed in
Japan. SCS sandwich tunnels can be divided into full sandwich and open sandwich element. Bellows
joints consist of steel leaf springs and expansion and contraction of the leaf springs absorbs the
displacement of the joints. Crown seal joint consists of a dewatering rubber piece called a crown
and is provided with an opening inside.
This paper was used in the initial literature study stage to get general information about the full
sandwich tunnel, open sandwich tunnel and the combined full and open sandwich tunnel.
It gave insight in the conventional joint as well as the joints used for recent SCS sandwich tunnel
projects in Japan, such as bellow joints and crown seal. The joints in Japan are provided with
coupler cables which make sure that the joint opening doesn’t widen.
Paper: Self-compacting concrete - 2003
Authors: Hajime Okamura, Masahiro Ouchi
This paper highlighted the development of self-compacting concrete. Here after it focusses on the
mechanisms which give the self-compacting concrete its self-compatibility. Comparisons are being
made with the conventional concrete. Especially what the advantages and disadvantages are and
how they are created. Concrete elements made out of self-compacting concrete were also
thoroughly tested before being used. These test results are also discussed in this paper. Further
the current status of self-compacting concrete is explained.
Conclusion: The author states that the main obstacle for the wide range use of self-compacting
concrete has been taken out by the large number of tests carried out. Now it is time for the
engineers to make use the concrete and its construction. In addition new structural systems
making use of self-compacting concrete need to be introduced. When self-compacting concrete
becomes widely used such that it will be seen as normal concrete rather than special concrete, this
will be a big step in acquiring durable and reliable structures.
Paper: The challenges involved in concrete works of Marmaray immersed tunnel with a
service life of 100 years - 2009
Authors: Ahmet Gokce, Fumio Koyama, Masahiko Tsuchiya, Turgut Gencoglu
This paper focusses initially on the waterproofing and corrosion protection of the Marmaray
immersed tunnel. It highlights what measures were taken and why. Also discussed is the execution
sequence of the concrete work, namely the pre-concreting, casting and post concreting.
Conclusion: One of the successful outcomes of the Marmaray immersed tube tunnel project was
the controlled concrete works ensuring the long term durability requirements of the owner. This
was achieved by combining effective design principles, relevant standards, codes, specifications
and expertise of the multidisciplinary specialist in the conception phase.
Report: Double skin composite construction for submerged tube tunnels – Phase3, 1997
Author: European Commission for Technical Steel Research
This report consists of three phases. Phase one the Cardiff tests where different SCS sandwich
elements were tested on failure. The test results were analysed and the main failure mechanisms
were acquired. In phase two the loads and existing design guidelines are discussed in detail. This
Kubilay Bekarlar - Master Thesis
- 198 -
August – 2016
chapter gives a good image how to calculate the loads and how to design the SCS sandwich
composite elements. In the third and last phase the Cardiff fatigue test is discussed.
In the first phase the elements tested were beams, columns, radius, joints and tunnel cross
sections. Nearly all beam elements showed ductile behaviour, except one which showed brittle
failure. Failure due to failure of shear connectors and slip were the main causes for the beam
models.
All test columns showed ductile behaviour where yielding of the tension plate and buckling of the
compression plate was the main failure mechanism. The three radiuses tested showed also ductile
behaviour. Failure mechanisms for these test pieces were, yielding of the inner plate and the pullout of the studs. The main conclusion of joints tests was that the radius joints were able to bear
three to four times more load than the joint with straight plates.
Ductile behaviour was also observed for the tunnel cross section. The collapse of the tunnel was
due to shear failure of the concrete.
This report is useful for the research on SCS sandwich immersed tunnels, since it gives insight in
the failure mechanisms that occurred with the different specimen. In a later stage of this research
the model output could be compared with the test results obtained in Cardiff.
Besides experimental insight, this report also gives information how to design SCS sandwich
tunnels and which checks should be done, what loads should be used and which safety factors
should be applied. There is also an example of a SCS immersed tunnel being worked out.
Report: “Stalen en composiet staalbeton tunnelconstructies – Staalbeton
sandwichelementen, Deel 2: Modelvorming en rekenregels” English: “Steel and
composite steel concrete tunnel structures – Steel concrete sandwich elements” - 2000
Author: Centrum Ondergronds Bouwen
This research focuses on an alternative type of SCS sandwich elements. Commonly used sandwich
element consists of shear studs attached to the steel plate at only one side. The other side with a
flat had is embedded in the concrete compression zone. An alternative is to apply shear connectors
attached to the steel plates with both sides. One side will be welded on the upper steel plate and
the other side on the lower steel plate.
The aim of this report is to determine design rules for a statically determined SCS sandwich beam,
which has shear studs that are connected on both sides. In order to reach this goal result of SCS
sandwich elements were used. Also an analytical and a numerical model are worked out. The
numerical model is used to predict the non-linear behaviour of the element.
From the numerical model there is seen that the shear force is carried by a truss system. In which
the compression diagonals arise in the concrete and the tensile forces in the studs. Besides this
truss contribution to bear the shear force, a part of the shear force also goes directly to the
support.
Paper: “Finite element analysis of steel concrete steel sandwich beams” - 2007
Author: N. Foundoukos, J.C. Chapman
This paper is about finite element analysis of a bi-steel beam. A bi-steel beam is a beam which
consists of steel plates connected with steel studs. For this analysis ABAQUS FEM program has
been used. First the force deflection curves for different beams have been obtained with the FEM
Kubilay Bekarlar - Master Thesis
- 199 -
August – 2016
program. This showed good agreement with the test results. The same has been done for the axial
forces and the slip. With the model insight has been obtained about the cracking pattern that will
occur in the concrete. The failure modes of the FEM model show good agreement with the tested
beam.
The first conclusion of this paper is that the load deflection curves of the FEM model show good
agreement with the tests. Also the ultimate failure load is close to the observed value of the tests.
The same holds for the failure modes observed, which also show good agreement.
The horizontal shear forces show agreement with the truss model. This force is resisted by the
shear connectors and the friction between the steel and concrete.
Cracking pattern obtained with the FEM model showed agreement with the experimental results.
The slip is mainly affected by concrete cracking and shear stud yielding.
Further there is concluded that the parametric studies showed good agreement design guide for
transverse shear capacity. This supports the use design equations for the transverse shear
resistance.
Paper: Behaviour of composite segment for shield tunnel – 2010
Authors: Wenjun Zhang, Atsushi Koizumi
This paper focusses on composite elements in shield tunnels. The purpose of this research is to
study the behaviour of composite segments by results of experiments and a FEM analysis. With this
analysis the failure models of the composite elements will be investigated.
First the author discusses the results of the experiments carried out. After this stage the FEM
analysis starts. From these analysis graphs of moment / curvature and force / deflection is
obtained. These graphs for the experiments and the FEM analysis show good agreement.
One of the conclusions of the authors regarding their research is that, the composite shield
elements with steel studs failed due to the crushing of the concrete within the composite element.
On the other hand the composite elements without shear studs failed due to buckling of the top
steel plate. There were also composite elements carried out with weak studs. For these elements
there was observed that they failed either because of failure of concrete crushing or buckling of the
top plate.
This study also showed that the skin plate has a significant contribution to the ultimate limit
capacity of the composite element. Finally there was also concluded that the segments showed
ductile behaviour after exceeding the ultimate yield strength and that the experimental results and
the FEM analysis showed good agreement.
Kubilay Bekarlar - Master Thesis
- 200 -
August – 2016
Download